Case Note & Summary
The petitioner, Maheshkumar G. Garodia, filed a writ petition under Article 226 of the Constitution of India before the Bombay High Court challenging the validity of transmission tower construction carried out by the second respondent, Kharghar Vikhroli Transmission Ltd. (KVTL), on land leased to the petitioner. KVTL, a licensee under Section 14 of the Electricity Act, 2003, was tasked with setting up a 400 KV Receiving Station and laying transmission towers to strengthen the Mumbai Transmission System. After obtaining all requisite permissions, including leave from the High Court in a related PIL, KVTL commenced work. Seven of the forty-seven towers were to be located on the petitioner's leased land, affecting an area of 1,250 sq. mtrs. When the petitioner obstructed the work, KVTL approached the Resident Deputy Collector and Additional District Magistrate under Section 16 of the Indian Telegraph Act, 1885. On 3rd May 2023, the Magistrate passed a restraint order under Section 16(2) of the Act, directing the petitioner not to obstruct the work. KVTL completed the tower construction by 8th May 2023. Subsequently, on 15th May 2023, the Magistrate revoked the order, holding that it was passed without jurisdiction as the dispute was not between the telegraph authority and the petitioner but between KVTL and the petitioner. The petitioner then filed the present writ petition seeking restoration of the land to its original condition. The key legal issue was whether work carried out under a restraint order that was later revoked for lack of jurisdiction could be considered valid. The court analyzed Section 16 of the Indian Telegraph Act, 1885, which empowers a District Magistrate to resolve disputes regarding the laying of telegraph lines. The court noted that the restraint order was in force when the work was executed, and the Magistrate had apparent jurisdiction to pass it. The subsequent revocation did not render the work illegal ab initio. The court emphasized that the order was not void but voidable, and acts done under it before revocation were protected. The court also considered the public interest involved in strengthening the transmission system. The petitioner's arguments that the order was without jurisdiction and that the work should be undone were rejected. The court held that the writ petition was not maintainable to challenge acts done under a valid order at the time of execution. The petition was dismissed, and the rule was discharged. No order as to costs.
Headnote
A) Telegraph Act - Section 16(2) - Restraint Order - Validity of Acts Done Under Subsequently Revoked Order - Indian Telegraph Act, 1885, Section 16(2) - The court considered whether work carried out under a restraint order passed under Section 16(2) of the Indian Telegraph Act, 1885, which was later revoked for lack of jurisdiction, remains valid. Held that the work done under the order prior to its revocation is not rendered illegal or invalid, as the order was in force at the time of execution and the authority acted within its apparent jurisdiction. (Paras 2, 10-12) B) Electricity Act - Transmission License - Telegraph Act Powers - Indian Telegraph Act, 1885, Section 16; Electricity Act, 2003, Section 14 - A transmission licensee under the Electricity Act, 2003 is entitled to invoke the provisions of the Indian Telegraph Act, 1885 for laying transmission lines. The court held that the licensee's actions under the restraint order were protected even after the order was set aside, as the order was not void ab initio but only voidable. (Paras 3, 10-12) C) Constitutional Law - Article 226 - Writ Jurisdiction - Interference with Administrative Orders - Constitution of India, Article 226 - The court declined to interfere with the work already completed under the restraint order, as the petitioner had not challenged the order at the time it was passed and the work was in public interest for strengthening the Mumbai Transmission System. Held that the writ petition was not maintainable to undo acts done under a valid order at the time of execution. (Paras 2, 12-13)
Issue of Consideration
What would be the effect of work of laying transmission towers under provisions of the Indian Telegraph Act, 1885, being carried out on the strength of a restraint order passed under Section 16(2) of the Act of 1885, which order is subsequently revoked as having been issued without jurisdiction?
Final Decision
The Bombay High Court dismissed the writ petition, holding that the work carried out under the restraint order dated 3rd May 2023 was valid despite the subsequent revocation of the order. The court ruled that the order was not void ab initio but voidable, and acts done under it before revocation are protected. The petition was dismissed with no order as to costs.
Law Points
- Effect of revocation of restraint order under Section 16(2) of Indian Telegraph Act
- 1885
- Validity of acts done under order subsequently found without jurisdiction
- Doctrine of de facto authority
- Section 16 Indian Telegraph Act
- Section 14 Electricity Act
- 2003
- Article 226 Constitution of India




