Bombay High Court Dismisses Petition Challenging Transmission Tower Construction Under Subsequently Revoked Restraint Order. Work done under Section 16(2) Indian Telegraph Act, 1885 order held valid despite later revocation for lack of jurisdiction, as order was in force at time of execution.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Maheshkumar G. Garodia, filed a writ petition under Article 226 of the Constitution of India before the Bombay High Court challenging the validity of transmission tower construction carried out by the second respondent, Kharghar Vikhroli Transmission Ltd. (KVTL), on land leased to the petitioner. KVTL, a licensee under Section 14 of the Electricity Act, 2003, was tasked with setting up a 400 KV Receiving Station and laying transmission towers to strengthen the Mumbai Transmission System. After obtaining all requisite permissions, including leave from the High Court in a related PIL, KVTL commenced work. Seven of the forty-seven towers were to be located on the petitioner's leased land, affecting an area of 1,250 sq. mtrs. When the petitioner obstructed the work, KVTL approached the Resident Deputy Collector and Additional District Magistrate under Section 16 of the Indian Telegraph Act, 1885. On 3rd May 2023, the Magistrate passed a restraint order under Section 16(2) of the Act, directing the petitioner not to obstruct the work. KVTL completed the tower construction by 8th May 2023. Subsequently, on 15th May 2023, the Magistrate revoked the order, holding that it was passed without jurisdiction as the dispute was not between the telegraph authority and the petitioner but between KVTL and the petitioner. The petitioner then filed the present writ petition seeking restoration of the land to its original condition. The key legal issue was whether work carried out under a restraint order that was later revoked for lack of jurisdiction could be considered valid. The court analyzed Section 16 of the Indian Telegraph Act, 1885, which empowers a District Magistrate to resolve disputes regarding the laying of telegraph lines. The court noted that the restraint order was in force when the work was executed, and the Magistrate had apparent jurisdiction to pass it. The subsequent revocation did not render the work illegal ab initio. The court emphasized that the order was not void but voidable, and acts done under it before revocation were protected. The court also considered the public interest involved in strengthening the transmission system. The petitioner's arguments that the order was without jurisdiction and that the work should be undone were rejected. The court held that the writ petition was not maintainable to challenge acts done under a valid order at the time of execution. The petition was dismissed, and the rule was discharged. No order as to costs.

Headnote

A) Telegraph Act - Section 16(2) - Restraint Order - Validity of Acts Done Under Subsequently Revoked Order - Indian Telegraph Act, 1885, Section 16(2) - The court considered whether work carried out under a restraint order passed under Section 16(2) of the Indian Telegraph Act, 1885, which was later revoked for lack of jurisdiction, remains valid. Held that the work done under the order prior to its revocation is not rendered illegal or invalid, as the order was in force at the time of execution and the authority acted within its apparent jurisdiction. (Paras 2, 10-12)

B) Electricity Act - Transmission License - Telegraph Act Powers - Indian Telegraph Act, 1885, Section 16; Electricity Act, 2003, Section 14 - A transmission licensee under the Electricity Act, 2003 is entitled to invoke the provisions of the Indian Telegraph Act, 1885 for laying transmission lines. The court held that the licensee's actions under the restraint order were protected even after the order was set aside, as the order was not void ab initio but only voidable. (Paras 3, 10-12)

C) Constitutional Law - Article 226 - Writ Jurisdiction - Interference with Administrative Orders - Constitution of India, Article 226 - The court declined to interfere with the work already completed under the restraint order, as the petitioner had not challenged the order at the time it was passed and the work was in public interest for strengthening the Mumbai Transmission System. Held that the writ petition was not maintainable to undo acts done under a valid order at the time of execution. (Paras 2, 12-13)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

What would be the effect of work of laying transmission towers under provisions of the Indian Telegraph Act, 1885, being carried out on the strength of a restraint order passed under Section 16(2) of the Act of 1885, which order is subsequently revoked as having been issued without jurisdiction?

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Bombay High Court dismissed the writ petition, holding that the work carried out under the restraint order dated 3rd May 2023 was valid despite the subsequent revocation of the order. The court ruled that the order was not void ab initio but voidable, and acts done under it before revocation are protected. The petition was dismissed with no order as to costs.

Law Points

  • Effect of revocation of restraint order under Section 16(2) of Indian Telegraph Act
  • 1885
  • Validity of acts done under order subsequently found without jurisdiction
  • Doctrine of de facto authority
  • Section 16 Indian Telegraph Act
  • Section 14 Electricity Act
  • 2003
  • Article 226 Constitution of India
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (04) 141

Writ Petition No.2155 of 2023

2024-04-17

A.S. Chandurkar, Jitendra Jain

2024:BHC-OS:6260-DB

Shyam Mehta (Senior Advocate), Aditya Bapat, Shehzad A.K. Najam-es-sani for Petitioner; Shriram Redij, Savita Ganoo for Respondent No.1; Venkatesh Dhond (Senior Advocate), Shrinivas Bobde, Shweta Jaydev, Neha Sonawane for Respondent No.2; P.H. Kantharia (Government Pleader), Nazia Shaikh for Respondent No.3

Maheshkumar G. Garodia

Union of India, Kharghar Vikhroli Transmission Ltd., Collector and District Magistrate

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 of the Constitution of India challenging the validity of transmission tower construction carried out under a restraint order under Section 16(2) of the Indian Telegraph Act, 1885, which was later revoked for lack of jurisdiction.

Remedy Sought

Petitioner sought restoration of the leased land to its original condition by removal of the transmission towers.

Filing Reason

Petitioner alleged that the restraint order under Section 16(2) of the Indian Telegraph Act, 1885 was passed without jurisdiction and that the work carried out under it was illegal, and sought restoration of the land.

Previous Decisions

The Resident Deputy Collector and Additional District Magistrate passed a restraint order on 3rd May 2023 under Section 16(2) of the Indian Telegraph Act, 1885, which was later revoked on 15th May 2023 on the ground that it was passed without jurisdiction.

Issues

Whether work carried out under a restraint order under Section 16(2) of the Indian Telegraph Act, 1885, which is subsequently revoked for lack of jurisdiction, is valid? Whether the writ petition under Article 226 is maintainable to challenge acts done under an order that was in force at the time of execution?

Submissions/Arguments

Petitioner argued that the restraint order dated 3rd May 2023 was passed without jurisdiction as the dispute was not between the telegraph authority and the petitioner, and therefore the work done under it was illegal and must be undone. Respondent No.2 (KVTL) argued that the order was valid when passed, the work was completed before revocation, and the order was not void ab initio but only voidable, thus the work remains valid. Also submitted that the petition was not maintainable as the order was not challenged in time.

Ratio Decidendi

A restraint order under Section 16(2) of the Indian Telegraph Act, 1885, even if subsequently revoked for lack of jurisdiction, does not render acts done under it while it was in force illegal or invalid. The order is voidable, not void ab initio, and the authority had apparent jurisdiction at the time of passing the order. Therefore, work completed under such an order cannot be challenged after revocation.

Judgment Excerpts

The question that arises for consideration in this writ petition filed under Article 226 of the Constitution of India is what would be the effect of work of laying transmission towers under provisions of the Indian Telegraph Act, 1885, being carried out on the strength of a restraint order passed under Section 16(2) of the Act of 1885, which order is subsequently revoked as having been issued without jurisdiction? The facts lie in a narrow compass.

Procedural History

On 3rd May 2023, the Resident Deputy Collector and Additional District Magistrate passed a restraint order under Section 16(2) of the Indian Telegraph Act, 1885, directing the petitioner not to obstruct KVTL's work. KVTL completed the tower construction by 8th May 2023. On 15th May 2023, the Magistrate revoked the order, holding it was without jurisdiction. The petitioner then filed the present writ petition on an unspecified date. The petition was heard on 22nd March 2024 and judgment pronounced on 17th April 2024.

Acts & Sections

  • Indian Telegraph Act, 1885: Section 16, Section 16(2)
  • Electricity Act, 2003: Section 14
  • Constitution of India: Article 226
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Transmission Tower Construction Under Subsequently Revoked Restraint Order. Work done under Section 16(2) Indian Telegraph Act, 1885 order held valid despite later revocation for lack of jurisdiction, ...
Related Judgement
High Court High Court Allows Special Civil Application for Continuity of Service Benefits -- Reinstated Workers Entitled to Government Resolution Benefits Despite Labour Court Award Silence on Continuity