Case Note & Summary
The dispute arose from the Multi Modal International Passenger and Cargo Hub Airport (MIHAN) project at Nagpur, a State Government initiative to develop an international airport and Special Economic Zone. Maharashtra Airport Development Company Limited (MADC) was constituted as the implementing authority and declared Special Planning Authority. Wipro Limited, a global technology services provider, was approached by MADC in 2004 to set up an IT park within the SEZ area. After negotiations, MADC issued a Letter of Acceptance dated 5 April 2007 for 117 acres at Rs.44 lakh per acre on a 99-year lease, with total consideration of Rs.51.48 crores. Wipro paid 20% advance of Rs.10,29,60,000 on 24 April 2007 and also paid monthly establishment costs. Wipro alleged that necessary infrastructure such as approach roads, water supply, power and air connectivity was never provided, making the project unviable. It requested reduction of land to 23 acres, which MADC agreed to on 22 February 2013 with a condition to commence operations within 24 months. On 3 December 2014, MADC threatened termination. Wipro responded on 12 December 2014 citing infrastructure deficiencies. On 27 May 2015, MADC terminated the Letter of Acceptance and forfeited the Rs.10.29 crores paid. Further negotiations for 23.40 acres took place in 2018. Wipro issued notices on 13 September 2024 and 8 November 2024 seeking refund, but MADC refuted the claim on 8 November 2024. Wipro filed Writ Petition No. 395 of 2025 challenging the termination and forfeiture. The petitioner argued that the amount was part consideration, not earnest money, and no forfeiture clause existed in the Letter of Acceptance; that no land was actually allotted; that delay was due to continued discussions; and that MADC, being a State instrumentality, could not act arbitrarily or unjustly enrich itself. It relied on Ramchandra Shankar Deodhar, Unitech Limited, Suresh Kumar Wadhwa, and M/s. Utkal Highways Engineers. The respondent argued gross delay and laches, acquiescence, that the amount was earnest money, and that petitioner breached the Letter of Acceptance, relying on S.S. Balu and Videocon Properties. The provided judgment text ends during the respondent's submissions, and no final analysis or operative order is included. The court had made the rule returnable forthwith and heard the matter finally, reserving judgment on 12 August 2025 and pronouncing on 19 August 2025.
Headnote
A) Contract Law - Forfeiture of Part Consideration - Absence of Forfeiture Clause - Contract Act, 1872 (not mentioned) - Petitioner argued that Rs.10.29 crores was part consideration, not earnest money, and could not be forfeited without a forfeiture clause in Letter of Acceptance dated 5 April 2007; Respondent contended it was earnest money deposit liable to forfeiture for breach. The Court considered the nature of payment and forfeiture clause but final decision not recorded in provided text. (Paras 2, 5, 7, 9) B) Constitutional Law - Writ Jurisdiction - Contractual Disputes with State Instrumentalities - Constitution of India, Article 226 (not expressly mentioned) - Petitioner relied on Unitech Limited and Utkal Highways to argue that writ jurisdiction can be invoked for refund of admitted amount and adjudication of contractual disputes with State authorities; Respondent argued time-barred claim impermissible in writ. The Court noted the dispute but final ruling not present. (Paras 8, 9) C) Limitation - Delay and Laches - Writ Petition - Petitioner explained delay due to continued negotiations and respondent's lack of entire land; Respondent argued gross delay and acquiescence. The Court was to decide whether delay barred relief; no final direction recorded. (Paras 8, 9) D) State Instrumentality - Unjust Enrichment and Arbitrariness - Forfeiture by State Entity - Petitioner argued State instrumentality cannot act arbitrarily or retain money without allotment; Respondent justified forfeiture. The Court considered whether retention of Rs.10.29 crores constituted unjust enrichment; final decision not mentioned. (Paras 8, 9)
Issue of Consideration
Whether Respondent No.1 could forfeit the part consideration of Rs.10.29 crores without a forfeiture clause in the Letter of Acceptance; whether the writ petition was barred by delay and laches; whether the amount paid was earnest money deposit or part consideration; whether contractual disputes with State authorities are amenable to writ jurisdiction; whether retention of the amount constituted unjust enrichment.
Final Decision
Not mentioned in the provided text; the judgment excerpt ends during Respondent No.1's submissions, and no final operative order is included.
Law Points
- forfeiture of part consideration without forfeiture clause impermissible
- writ jurisdiction for contractual disputes with State authorities
- delay and laches not absolute bar
- earnest money vs part consideration distinction
- State instrumentality cannot act arbitrarily
- unjust enrichment



