Bombay High Court Hears Writ Petition Challenging Cancellation of Letter of Acceptance and Forfeiture of Rs.10.29 Crores in MIHAN Land Allotment. Court Called Upon to Decide Legality of Forfeiture Without Forfeiture Clause and Maintainability Despite Delay; Rule Made Returnable Forthwith.

High Court: Bombay High Court Bench: BOMBAY
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from the Multi Modal International Passenger and Cargo Hub Airport (MIHAN) project at Nagpur, a State Government initiative to develop an international airport and Special Economic Zone. Maharashtra Airport Development Company Limited (MADC) was constituted as the implementing authority and declared Special Planning Authority. Wipro Limited, a global technology services provider, was approached by MADC in 2004 to set up an IT park within the SEZ area. After negotiations, MADC issued a Letter of Acceptance dated 5 April 2007 for 117 acres at Rs.44 lakh per acre on a 99-year lease, with total consideration of Rs.51.48 crores. Wipro paid 20% advance of Rs.10,29,60,000 on 24 April 2007 and also paid monthly establishment costs. Wipro alleged that necessary infrastructure such as approach roads, water supply, power and air connectivity was never provided, making the project unviable. It requested reduction of land to 23 acres, which MADC agreed to on 22 February 2013 with a condition to commence operations within 24 months. On 3 December 2014, MADC threatened termination. Wipro responded on 12 December 2014 citing infrastructure deficiencies. On 27 May 2015, MADC terminated the Letter of Acceptance and forfeited the Rs.10.29 crores paid. Further negotiations for 23.40 acres took place in 2018. Wipro issued notices on 13 September 2024 and 8 November 2024 seeking refund, but MADC refuted the claim on 8 November 2024. Wipro filed Writ Petition No. 395 of 2025 challenging the termination and forfeiture. The petitioner argued that the amount was part consideration, not earnest money, and no forfeiture clause existed in the Letter of Acceptance; that no land was actually allotted; that delay was due to continued discussions; and that MADC, being a State instrumentality, could not act arbitrarily or unjustly enrich itself. It relied on Ramchandra Shankar Deodhar, Unitech Limited, Suresh Kumar Wadhwa, and M/s. Utkal Highways Engineers. The respondent argued gross delay and laches, acquiescence, that the amount was earnest money, and that petitioner breached the Letter of Acceptance, relying on S.S. Balu and Videocon Properties. The provided judgment text ends during the respondent's submissions, and no final analysis or operative order is included. The court had made the rule returnable forthwith and heard the matter finally, reserving judgment on 12 August 2025 and pronouncing on 19 August 2025.

Headnote

A) Contract Law - Forfeiture of Part Consideration - Absence of Forfeiture Clause - Contract Act, 1872 (not mentioned) - Petitioner argued that Rs.10.29 crores was part consideration, not earnest money, and could not be forfeited without a forfeiture clause in Letter of Acceptance dated 5 April 2007; Respondent contended it was earnest money deposit liable to forfeiture for breach. The Court considered the nature of payment and forfeiture clause but final decision not recorded in provided text. (Paras 2, 5, 7, 9)

B) Constitutional Law - Writ Jurisdiction - Contractual Disputes with State Instrumentalities - Constitution of India, Article 226 (not expressly mentioned) - Petitioner relied on Unitech Limited and Utkal Highways to argue that writ jurisdiction can be invoked for refund of admitted amount and adjudication of contractual disputes with State authorities; Respondent argued time-barred claim impermissible in writ. The Court noted the dispute but final ruling not present. (Paras 8, 9)

C) Limitation - Delay and Laches - Writ Petition - Petitioner explained delay due to continued negotiations and respondent's lack of entire land; Respondent argued gross delay and acquiescence. The Court was to decide whether delay barred relief; no final direction recorded. (Paras 8, 9)

D) State Instrumentality - Unjust Enrichment and Arbitrariness - Forfeiture by State Entity - Petitioner argued State instrumentality cannot act arbitrarily or retain money without allotment; Respondent justified forfeiture. The Court considered whether retention of Rs.10.29 crores constituted unjust enrichment; final decision not mentioned. (Paras 8, 9)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether Respondent No.1 could forfeit the part consideration of Rs.10.29 crores without a forfeiture clause in the Letter of Acceptance; whether the writ petition was barred by delay and laches; whether the amount paid was earnest money deposit or part consideration; whether contractual disputes with State authorities are amenable to writ jurisdiction; whether retention of the amount constituted unjust enrichment.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the provided text; the judgment excerpt ends during Respondent No.1's submissions, and no final operative order is included.

Law Points

  • forfeiture of part consideration without forfeiture clause impermissible
  • writ jurisdiction for contractual disputes with State authorities
  • delay and laches not absolute bar
  • earnest money vs part consideration distinction
  • State instrumentality cannot act arbitrarily
  • unjust enrichment
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (08) 75

Writ Petition No. 395 of 2025

2025-08-19

Alok Aradhe, CJ and Sandeep V. Marne, J

2025:BHC-OS:13803-DB

Mr. Rahul Narichania, Senior Advocate with Mr. Shubharata Chakraborti, Mr. Naozad Golwalla and Mr. Aayush Barat i/b Mr. Mehernosh Humranwala for the Petitioner; Mr. Zulfiq Multani with Mr. Manoj Kumar Mishra for Respondent No.1; Mr. Atul Vanarse, AGP for Respondent No.2-State

Wipro Limited

Maharashtra Airport Development Company Ltd. and State of Maharashtra

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under the High Court's original jurisdiction challenging a communication dated 27 May 2015 that cancelled a Letter of Acceptance and forfeited an advance amount of Rs.10.29 crores, and seeking refund with interest.

Remedy Sought

Petitioner Wipro Limited sought quashing of the communication dated 27 May 2015 issued by Respondent No.1 MADC and refund of Rs.10.29 crores with interest, alternatively refund of principal amount without interest.

Filing Reason

Petitioner challenged the forfeiture as illegal and arbitrary because no land allotment took place, the Letter of Acceptance lacked a forfeiture clause, and the respondent allegedly failed to provide basic infrastructure and could not allot the entire land.

Previous Decisions

No prior court decisions mentioned; the dispute was preceded by correspondence and notices dated 13 September 2024 and 8 November 2024; Respondent No.1 refuted the claim on 8 November 2024.

Issues

Whether Respondent No.1 could lawfully forfeit the part consideration of Rs.10.29 crores in absence of a forfeiture clause in the Letter of Acceptance. Whether the writ petition was barred by delay and laches. Whether the amount of Rs.10.29 crores constituted earnest money deposit or part consideration. Whether contractual disputes with State authorities can be adjudicated in writ jurisdiction. Whether Respondent No.1 was unjustly enriched by retaining the amount without allotting land.

Submissions/Arguments

Petitioner argued that the amount was part consideration, not earnest money, and could not be forfeited without a forfeiture clause; no allotment of land took place; infrastructure was lacking; delay was due to continued discussions; State instrumentality cannot act arbitrarily or unjustly enrich itself; relied on Ramchandra Shankar Deodhar, Unitech Limited, Suresh Kumar Wadhwa and M/s. Utkal Highways Engineers. Respondent argued that the petition suffered from gross delay and laches; claimant acquiesced in forfeiture; the amount was earnest money deposit; petitioner committed breach of Letter of Acceptance; relied on S.S. Balu and Videocon Properties.

Ratio Decidendi

Not mentioned in the provided text; the Court's final reasoning and ratio cannot be determined because the excerpt ends before the analysis and order.

Judgment Excerpts

Rule. Rule is made returnable forthwith. With the consent of learned counsel appearing for rival parties, the petition is taken for final hearing and disposal. Petitioner has filed the present petition in this Court challenging the communication dated 27 May 2015 issued by Maharashtra Airport Development Company Limited cancelling the Letter of Acceptance ( L OA ) dated 5 April 2007 and forfeiting the advance amount of Rs. 10.29 crores. On 27 May 2015, MADC terminated the LOA and forfeited the amount of Rs.10.29 crores paid by the Petitioner. That the amount of Rs.10.29 crores is not paid towards earnest money deposit, and the impugned communication itself accepts that the same is paid towards part consideration. That in any case, Respondent No. 1, being an Instrumentality of State, cannot be permitted to act arbitrarily or indulging in unjust enrichment.

Procedural History

On 20 October 2004, MADC approached Wipro offering land at concessional rate. On 5 April 2007, Letter of Acceptance issued for 117 acres at Rs.44 lakh per acre on 99-year lease, total consideration Rs.51.48 crores, 20% advance Rs.10,29,60,000. Wipro paid 20% advance on 24 April 2007 and also paid monthly establishment costs totalling Rs.5,26,500. Wipro later requested reduction to 23 acres; MADC agreed on 22 February 2013 with condition to commence operations within 24 months. On 3 December 2014, MADC threatened termination. Wipro responded on 12 December 2014 citing infrastructure deficiencies. On 27 May 2015, MADC terminated the Letter of Acceptance and forfeited Rs.10.29 crores. On 7 February 2018, Wipro expressed interest in allotment of 23.40 acres. On 13 September 2024, Wipro issued notice seeking refund with interest; on 8 November 2024, Wipro sent another notice and MADC refuted the claim. Wipro filed Writ Petition No. 395 of 2025; the High Court made rule returnable forthwith and heard the matter finally, reserving judgment on 12 August 2025 and pronouncing on 19 August 2025.

Acts & Sections

  • Companies Act, 1956:
  • Maharashtra Regional and Town Planning Act, 1966:
  • Special Economic Zones Act, 2005:
  • Special Economic Zones Rules, 2006:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Hears Writ Petition Challenging Cancellation of Letter of Acceptance and Forfeiture of Rs.10.29 Crores in MIHAN Land Allotment. Court Called Upon to Decide Legality of Forfeiture Without Forfeiture Clause and Maintainability Despite...
Related Judgement
High Court High Court of Madras Hears First Appeal against Denial of Specific Performance in Sale Agreement. Trial Court Denied Specific Performance Due to Non-Deposit of Balance Consideration, Appeal Filed Under Section 96 CPC.