High Court of Judicature at Bombay Rejects Petitioners' Choice of Forum in Section 29-A Extension and Section 9 Petitions Under Arbitration and Conciliation Act, 1996 Due to Prior District Court Consent. District Court Consent for Two Extensions Under Section 29-A Reaffirmed Original Seat at Karjat/Thane, Rendering Section 42 Bar to High Court Jurisdiction.

High Court: Bombay High Court Bench: BOMBAY
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from two agreements between the petitioners, who were landowners, and the respondents, who were purchasers, relating to land at Karjat, District Raigad. The first agreement dated March 6, 2010, covered 108.9 acres, and a memorandum of understanding dated March 9, 2010, added 22.9 acres. Title documents were placed in escrow in April 2010. The petitioners terminated both agreements on August 22, 2015, and arbitration was invoked on January 25, 2016. The Section 11 court initially held that the arbitration agreement did not survive because the parties could not agree on a sole arbitrator, but the Supreme Court appointed an arbitrator on November 6, 2017. In a meeting before the arbitrator on November 27, 2017, the parties consented to record Mumbai as the seat. The arbitrator passed a status quo order under Section 17 on March 7, 2018. Petitioners filed three applications for extension of arbitral mandate under Section 29-A before the District Court, Raigad at Alibag; the first two were allowed on April 29, 2018, and June 15, 2020, with mutual consent. The third was filed on June 16, 2021. Meanwhile, respondents chose to pursue damages rather than specific performance on April 10, 2019, and petitioners sought release of escrow documents through a Section 17 application dated January 31, 2024. When the arbitrator postponed that application, petitioners filed a Section 9 petition in the High Court seeking release of escrow, and later a Section 29-A petition in the High Court on June 9, 2025, withdrawing the pending District Court application on June 30, 2025. The core legal issue was whether the High Court had territorial jurisdiction to entertain these petitions, given the original contractual seat was Karjat/Thane but the parties had recorded consent before the arbitrator to change the seat to Mumbai. Petitioners argued that the seat had changed to Mumbai, so the High Court was the proper court. Respondents contended that the reference to 'seat' in the minutes was actually a change of venue only, and that the petitioners' repeated filings in the District Court and the two extensions obtained with consent showed that the seat remained Karjat/Thane, making Section 42 of the Arbitration and Conciliation Act, 1996 applicable. The court observed that parties can change the seat by consent, but the consent must be read holistically with subsequent conduct. The judge noted that the parties had approached the District Court twice for extensions, which amounted to consent reaffirming the original seat. The court referred to Ravi Ranjan Developers (P) Ltd. v. Aditya Kumar Chatterjee, which held that the High Court exercising supervisory jurisdiction over the Section 2(1)(e) court would have jurisdiction, but found that the subsequent conduct of the parties pointed to the District Court. The court reasoned that the change of seat to Mumbai could be reconciled as a change of venue only, and that the District Court remained the court under Section 2(1)(e) for purposes of Section 42. The available excerpt did not record a final operative order, but the analysis strongly indicated that the High Court lacked territorial jurisdiction.

Headnote

A) Arbitration Law - Territorial Jurisdiction - Seat and Venue - Arbitration and Conciliation Act, 1996, Sections 2(1)(e), 9, 29-A, 42 - The court examined whether the High Court or District Court had territorial jurisdiction to entertain a Section 29-A extension petition where the original seat was Karjat/Thane but parties recorded consent before the arbitrator to change the seat to Mumbai. The court held that later consent of parties in approaching the District Court twice for extension of mandate indicated reaffirmation of the original seat and that the change to Mumbai operated as change of venue only. Held, the District Court remained the court under Section 2(1)(e) for purposes of Section 42 (Paras 8-14).

B) Arbitration Law - Party Autonomy and Consent - Consent to Change Seat - Arbitration and Conciliation Act, 1996, Section 2(1)(e) - The court observed that parties are capable of amending consent to change seat, but such consent must be interpreted holistically with subsequent conduct. The consent recorded in minutes of meeting before the arbitrator on November 27, 2017, to shift seat to Mumbai was considered alongside the petitioners' repeated filing of Section 29-A applications before the District Court and the respondents' consent to extensions there. Held, conflicting positions could be reconciled by treating the change of seat to Mumbai as change of venue, consistent with parties' approach to District Court whenever judicial intervention was sought (Paras 9-13).

C) Arbitration Law - Section 42 Exclusive Jurisdiction - Concurrent Jurisdiction - Arbitration and Conciliation Act, 1996, Sections 42, 9, 29-A - The court considered whether Section 42 required all subsequent applications to be filed before the same court that first received an earlier application. Because parties had obtained two extensions from the District Court with mutual consent, the court reasoned that the District Court was the court of first instance for arbitration-related applications. Held, the High Court would not have territorial jurisdiction for the Section 29-A and Section 9 petitions in view of the prior District Court proceedings (Paras 10-14).

D) Arbitration Law - Precedent on Court under Section 2(1)(e) - Ravi Ranjan Developers - Arbitration and Conciliation Act, 1996, Sections 2(1)(e), 11 - The court referred to Ravi Ranjan Developers (P) Ltd. v. Aditya Kumar Chatterjee, 2022 SCC OnLine SC 568, which reconciled the difference between the court under Section 2(1)(e) and the Section 11 court by holding that the High Court exercising supervisory jurisdiction over the Section 2(1)(e) court would have jurisdiction. The court observed that while the Section 11 petition was filed on the Appellate Side of the High Court, this alone did not determine seat because subsequent consent and conduct before the District Court indicated primary jurisdiction. Held, party autonomy and consent determined the relevant court for arbitration applications (Paras 12-14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court of Judicature at Bombay had territorial jurisdiction to entertain a Section 29-A petition when the original seat was Karjat/Thane but parties recorded consent to change seat to Mumbai, and whether prior consent to District Court extensions reaffirmed original seat under Section 42.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The available excerpt of the judgment did not record a final operative order; the court analyzed territorial jurisdiction and indicated, by reconciling the parties' conduct, that the District Court remained the court under Section 2(1)(e) for purposes of Section 42.

Law Points

  • Seat and venue are determined by consent
  • party autonomy governs arbitration jurisdiction
  • subsequent conduct of parties can reaffirm seat
  • Section 42 bars subsequent applications in different court
  • Ravi Ranjan reconciles Section 2(1)(e) and Section 11 court
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (07) 69

Commercial Arbitration Petition (L) No. 18764 of 2025 with Commercial Arbitration Petition (L) No. 33968 of 2024

2025-07-29

Somasekhar Sundaresan

2025:BHC-OS:12526

A.S. Khadeparkar, Amogh Karnadikar, Amogh Karandikar, Nishant Tripathi, Pranav Vaidya

Ramesh Ramchandra Kalyankar, Rachana Ramesh Kalyankar, Rasiiek Kalyankar

Suresh K. Haware, Sanjay K. Haware, Pravin K. Haware, Haware Engineers & Builders Pvt. Ltd., Himanshu Bheda & Associates (through Mr. Himanshu Bheda)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petitions under Sections 9 and 29-A of the Arbitration and Conciliation Act, 1996, concerning territorial jurisdiction, extension of arbitral mandate, and release of title documents from escrow.

Remedy Sought

Petitioners sought extension of the mandate of the Arbitral Tribunal under Section 29-A and release of title documents from escrow under Section 9.

Filing Reason

Arbitration proceedings had continued since 2017 and mandate was to expire; petitioners filed Section 29-A petition in High Court after withdrawing from District Court, and Section 9 petition to release escrow due to arbitral tribunal postponing Section 17 application.

Previous Decisions

Section 11 Court held arbitration agreement did not survive; Supreme Court appointed arbitrator on November 6, 2017. District Court allowed first and second Section 29-A extension applications on April 29, 2018 and June 15, 2020. Arbitral Tribunal passed status quo order under Section 17 on March 7, 2018. Third Section 29-A application pending before District Court was withdrawn on June 30, 2025.

Issues

Whether the High Court of Judicature at Bombay had territorial jurisdiction to entertain a Section 29-A petition when the original seat was Karjat/Thane but parties recorded consent to change seat to Mumbai. Whether the minutes of meeting dated November 27, 2017, before the arbitrator, recording consent to seat at Mumbai, effected a change of seat or merely of venue. Whether prior consent of parties before the District Court for two extensions under Section 29-A reaffirmed the original seat and attracted Section 42 of the Arbitration and Conciliation Act, 1996. Application of the principle in Ravi Ranjan Developers (P) Ltd. v. Aditya Kumar Chatterjee regarding court under Section 2(1)(e) and Section 11 court in light of subsequent conduct.

Submissions/Arguments

Petitioners argued that the seat of arbitration was changed to Mumbai by mutual consent recorded in the minutes of meeting before the arbitrator on November 27, 2017, and therefore the High Court had territorial jurisdiction to entertain the Section 29-A petition. Respondents argued that the reference to 'seat' in the minutes was to be read as a reference to venue only, and that the seat remained Karjat/Thane because the petitioners had filed Section 29-A applications before the District Court three times, and the first two extensions were obtained with mutual consent. Respondents further argued that Section 42 of the Act barred the High Court from entertaining the Section 9 and Section 29-A petitions because all prior applications had been filed before the District Court, which was the court under Section 2(1)(e). Petitioners relied on the fact that the Section 11 petition had been filed on the Appellate Side of the High Court, but the court noted that this alone did not determine the seat because subsequent consent and conduct before the District Court indicated primary jurisdiction.

Ratio Decidendi

Consent of parties determines the seat of arbitration; subsequent conduct of the parties, including obtaining extensions from a particular court, can reaffirm the original seat. A change of seat recorded before the arbitrator can be reconciled as a change of venue when the parties later repeatedly approach the District Court by consent. The court under Section 2(1)(e) is determined by the parties' consistent understanding, and Section 42 bars subsequent applications in another court when the first application was made to the District Court.

Judgment Excerpts

The phrase “ peculiar facts of the case ” is so routinely used that it tends to not speak to real peculiarity. However, in the instant case, the factual matrix arising out of the conduct of the parties, renders this case, a true tale of the peculiar. If one were to infer consent to change the seat from the minutes of meeting before the Learned Arbitral Tribunal one would also need to interpret the same parties’ consent before the District Court, made twice over, when the Section 29-A Applications filed there came up for consideration. In this view of the matter, a plausible and reasonable means of reconciling the conflicting positions emerging from the parties’ conduct (all by consent) would be that there was a foundational reinforcement of what was in any case, originally contained in the agreements as the seat, owing to the parties getting two extensions from the District Court.

Procedural History

On March 6, 2010, parties executed an Agreement for Sale for 108.9 acres; on March 9, 2010, a Memorandum of Understanding added 22.9 acres. In April 2010, an escrow agent was given title documents. The agreements were terminated on August 22, 2015, and arbitration was invoked on January 25, 2016. The Section 11 Court held that the arbitration agreement did not survive, but the Supreme Court appointed an arbitrator on November 6, 2017. Minutes of meeting on November 27, 2017 recorded consent to seat at Mumbai. The Arbitral Tribunal passed a status quo order under Section 17 on March 7, 2018. The District Court allowed first and second Section 29-A extension applications on April 29, 2018 and June 15, 2020; the third was filed on June 16, 2021. Respondents chose damages over specific performance on April 10, 2019. Petitioners made a Section 17 application on January 31, 2024 to release escrow, and filed a Section 9 petition in the High Court in 2024. Petitioners filed the Section 29-A petition in the High Court on June 9, 2025 and withdrew the District Court application on June 30, 2025. The available excerpt ends during the court's analysis of jurisdiction without recording the final disposal.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 2(1)(e), 9, 11, 17, 29-A, 42
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature at Bombay Rejects Petitioners' Choice of Forum in Section 29-A Extension and Section 9 Petitions Under Arbitration and Conciliation Act, 1996 Due to Prior District Court Consent. District Court Consent for Two Extensions Unde...
Related Judgement
High Court Bombay High Court Allows Teacher's Inclusion in Shalarth System for Salary Payment Despite Prior Approval of Transfer from Unaided to Aided Post. The court held that the approval granted by the Education Officer for appointment to an aided post canno...