Case Note & Summary
The dispute arose from two agreements between the petitioners, who were landowners, and the respondents, who were purchasers, relating to land at Karjat, District Raigad. The first agreement dated March 6, 2010, covered 108.9 acres, and a memorandum of understanding dated March 9, 2010, added 22.9 acres. Title documents were placed in escrow in April 2010. The petitioners terminated both agreements on August 22, 2015, and arbitration was invoked on January 25, 2016. The Section 11 court initially held that the arbitration agreement did not survive because the parties could not agree on a sole arbitrator, but the Supreme Court appointed an arbitrator on November 6, 2017. In a meeting before the arbitrator on November 27, 2017, the parties consented to record Mumbai as the seat. The arbitrator passed a status quo order under Section 17 on March 7, 2018. Petitioners filed three applications for extension of arbitral mandate under Section 29-A before the District Court, Raigad at Alibag; the first two were allowed on April 29, 2018, and June 15, 2020, with mutual consent. The third was filed on June 16, 2021. Meanwhile, respondents chose to pursue damages rather than specific performance on April 10, 2019, and petitioners sought release of escrow documents through a Section 17 application dated January 31, 2024. When the arbitrator postponed that application, petitioners filed a Section 9 petition in the High Court seeking release of escrow, and later a Section 29-A petition in the High Court on June 9, 2025, withdrawing the pending District Court application on June 30, 2025. The core legal issue was whether the High Court had territorial jurisdiction to entertain these petitions, given the original contractual seat was Karjat/Thane but the parties had recorded consent before the arbitrator to change the seat to Mumbai. Petitioners argued that the seat had changed to Mumbai, so the High Court was the proper court. Respondents contended that the reference to 'seat' in the minutes was actually a change of venue only, and that the petitioners' repeated filings in the District Court and the two extensions obtained with consent showed that the seat remained Karjat/Thane, making Section 42 of the Arbitration and Conciliation Act, 1996 applicable. The court observed that parties can change the seat by consent, but the consent must be read holistically with subsequent conduct. The judge noted that the parties had approached the District Court twice for extensions, which amounted to consent reaffirming the original seat. The court referred to Ravi Ranjan Developers (P) Ltd. v. Aditya Kumar Chatterjee, which held that the High Court exercising supervisory jurisdiction over the Section 2(1)(e) court would have jurisdiction, but found that the subsequent conduct of the parties pointed to the District Court. The court reasoned that the change of seat to Mumbai could be reconciled as a change of venue only, and that the District Court remained the court under Section 2(1)(e) for purposes of Section 42. The available excerpt did not record a final operative order, but the analysis strongly indicated that the High Court lacked territorial jurisdiction.
Headnote
A) Arbitration Law - Territorial Jurisdiction - Seat and Venue - Arbitration and Conciliation Act, 1996, Sections 2(1)(e), 9, 29-A, 42 - The court examined whether the High Court or District Court had territorial jurisdiction to entertain a Section 29-A extension petition where the original seat was Karjat/Thane but parties recorded consent before the arbitrator to change the seat to Mumbai. The court held that later consent of parties in approaching the District Court twice for extension of mandate indicated reaffirmation of the original seat and that the change to Mumbai operated as change of venue only. Held, the District Court remained the court under Section 2(1)(e) for purposes of Section 42 (Paras 8-14). B) Arbitration Law - Party Autonomy and Consent - Consent to Change Seat - Arbitration and Conciliation Act, 1996, Section 2(1)(e) - The court observed that parties are capable of amending consent to change seat, but such consent must be interpreted holistically with subsequent conduct. The consent recorded in minutes of meeting before the arbitrator on November 27, 2017, to shift seat to Mumbai was considered alongside the petitioners' repeated filing of Section 29-A applications before the District Court and the respondents' consent to extensions there. Held, conflicting positions could be reconciled by treating the change of seat to Mumbai as change of venue, consistent with parties' approach to District Court whenever judicial intervention was sought (Paras 9-13). C) Arbitration Law - Section 42 Exclusive Jurisdiction - Concurrent Jurisdiction - Arbitration and Conciliation Act, 1996, Sections 42, 9, 29-A - The court considered whether Section 42 required all subsequent applications to be filed before the same court that first received an earlier application. Because parties had obtained two extensions from the District Court with mutual consent, the court reasoned that the District Court was the court of first instance for arbitration-related applications. Held, the High Court would not have territorial jurisdiction for the Section 29-A and Section 9 petitions in view of the prior District Court proceedings (Paras 10-14). D) Arbitration Law - Precedent on Court under Section 2(1)(e) - Ravi Ranjan Developers - Arbitration and Conciliation Act, 1996, Sections 2(1)(e), 11 - The court referred to Ravi Ranjan Developers (P) Ltd. v. Aditya Kumar Chatterjee, 2022 SCC OnLine SC 568, which reconciled the difference between the court under Section 2(1)(e) and the Section 11 court by holding that the High Court exercising supervisory jurisdiction over the Section 2(1)(e) court would have jurisdiction. The court observed that while the Section 11 petition was filed on the Appellate Side of the High Court, this alone did not determine seat because subsequent consent and conduct before the District Court indicated primary jurisdiction. Held, party autonomy and consent determined the relevant court for arbitration applications (Paras 12-14).
Issue of Consideration
Whether the High Court of Judicature at Bombay had territorial jurisdiction to entertain a Section 29-A petition when the original seat was Karjat/Thane but parties recorded consent to change seat to Mumbai, and whether prior consent to District Court extensions reaffirmed original seat under Section 42.
Final Decision
The available excerpt of the judgment did not record a final operative order; the court analyzed territorial jurisdiction and indicated, by reconciling the parties' conduct, that the District Court remained the court under Section 2(1)(e) for purposes of Section 42.
Law Points
- Seat and venue are determined by consent
- party autonomy governs arbitration jurisdiction
- subsequent conduct of parties can reaffirm seat
- Section 42 bars subsequent applications in different court
- Ravi Ranjan reconciles Section 2(1)(e) and Section 11 court



