High Court of Judicature at Bombay Considered a Writ Petition Challenging Retrospective Application of Section 4-A(4) of Mines and Minerals (Development and Regulation) Act, 1957. Court Examined Whether Amended Provision Applies to Pre-2021 Mining Leases and Whether Government Delay Should Be Excluded in Computing Revival Period.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The matter concerned a writ petition under Article 226 of the Constitution of India before the Bombay High Court, arising from the statutory lapse of a bauxite mining lease in Village Sakhri, District Ratnagiri. The petitioner, a mining company, had applied for grant of mining lease on 15 September 2003 over an area of 62.77 hectares. The Ministry of Mines granted prior approval on 3 July 2009 under Section 5(1) of the Mines and Minerals (Development and Regulation) Act, 1957, subject to compliance with amended provisions, Mineral Concession Rules, 1960, Forest (Conservation) Act, 1980, and the Environment Impact Assessment Notification dated 27 January 1994 as amended in 2006. The State Government requested necessary documents within six months on 12 August 2009. A moratorium on EIA projects from 16 August 2010 to 25 July 2017 affected the project, but the Maharashtra Coastal Zone Management Authority clarified by letter dated 11 September 2015 that the moratorium ceased to apply. Mining plans were approved on 26 December 2011 and modified on 26 November 2015 on a without-prejudice basis. The petitioner applied for Terms of Reference on 10 December 2015 and obtained TOR valid until 15 March 2019, but did not obtain environmental clearance despite extension requests. The Ministry of Mines issued the Mines and Minerals (Development and Regulation) Removal of Difficulties Order dated 4 January 2017 clarifying that non-compliance with environmental clearance condition by 11 January 2017 could still be condoned if other conditions were met. However, respondent no. 2 issued a lapsing order dated 16 June 2021, which was revoked by order dated 24 March 2023, followed by an order dated 9 February 2024 imposing condition to commence production and dispatch by 28 March 2024. The petitioner challenged these orders and the constitutional validity of erstwhile Rule 8(4) of Mineral Concession Rules, 2016, and sought a declaration that Section 4-A(4) as amended with effect from 28.3.2021 does not apply to leases executed prior thereto, or in the alternative, that government delay be excluded in computing revival period, and mandamus for issuance of mine code. The court heard counsel and reserved judgment on 5 March 2025, pronouncing on 6 June 2025. The available extract did not include the final operative part, but the court framed the core issue whether it could regularize claims by judicial imprimatur even if outside statutory scope, and emphasized the trusteeship principle for state largesse. The extract ends at paragraph 13, so the final decision and ratio are not provided.

Headnote

A) Mines and Minerals - Retrospective Application of Section 4-A(4) - Mines and Minerals (Development and Regulation) Act, 1957, Section 4-A(4) as amended 2021 - The petitioner sought a declaration that amended Section 4-A(4) does not apply to leases executed prior to 28.3.2021 and that retrospective application violates Articles 14, 19(1)(g), 21 of the Constitution. The court framed the issue whether it could regularize claims by judicial imprimatur even if outside statutory scope, noting the trusteeship principle for state largesse. Held: Not mentioned in the available extract (Paras 1-3).

B) Mines and Minerals - Computation of Revival Period Excluding Government Delay - Mines and Minerals (Development and Regulation) Act, 1957, Section 4-A(4) - The petitioner alternatively prayed for exclusion of time taken by government authorities in passing revival orders, aggregating 32 months out of 36 months, while computing the period of two years or one year under amended Section 4-A(4). The court was required to examine whether such exclusion is permissible under the statutory scheme. Held: Not mentioned in the available extract (Paras 1-3).

C) Constitutional Law - Fundamental Rights Violation - Constitution of India, Articles 14, 19(1)(g), 21 - The petitioner claimed that retrospective application of the amended provision and imposition of production deadline violated its fundamental rights. The court was to assess reasonableness and statutory compliance, considering the principle that state largesse is rooted in trusteeship. Held: Not mentioned in the available extract (Paras 1-3).

D) Environment Law - Mandatory Environmental Clearance - Environment Protection Act, 1986 and Environment Impact Assessment Notification, 1994 as amended 2006 - Facts showed that the petitioner did not obtain environmental clearance despite obtaining TOR valid until 15 March 2019 and making extension requests; the lease lapsed due to non-compliance with statutory provisions. The court noted that compliance with environmental clearance, Forest (Conservation) Act, and allied laws was mandatory before grant of mining lease. Held: Not mentioned in the available extract (Paras 2, 6-12).

E) Administrative Law - State Largesse and Trusteeship - General Principle on State Largesse - The court opened with the observation that "Any State Largess is rooted in the foundation of trusteeship, which is premised on need and not on the individual greed." This principle informed the examination of the petitioner's claim for mining lease and mine code. Held: Not mentioned in the available extract (Para 1).

F) Writ Jurisdiction - Judicial Review of Administrative Orders - Constitution of India, Article 226 - The petitioner sought writs of certiorari, prohibition, and mandamus to quash orders dated 24 March 2023 and 9 February 2024, to set aside letter dated 27 November 2018, and to direct grant of mine code. The court was required to test the legality, validity, and propriety of these administrative actions. Held: Not mentioned in the available extract (Paras 1-3).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether Section 4-A(4) of the Mines and Minerals (Development and Regulation) Act, 1957 as amended with effect from 28.3.2021 applies to leases executed prior thereto; whether retrospective application violates Articles 14, 19(1)(g) and 21 of the Constitution; whether period taken by government authorities should be excluded in computing revival period; validity of orders dated 24 March 2023 and 9 February 2024 imposing production deadline; constitutionality of erstwhile Rule 8(4) of Mineral Concession Rules, 2016; entitlement to mine code.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the available extract. The judgment was reserved on 5 March 2025 and pronounced on 6 June 2025, but the final operative part is not provided in the extracted text.

Law Points

  • State largesse rooted in trusteeship
  • statutory compliance mandatory for mining lease
  • environmental clearance mandatory
  • lease lapses on non-compliance
  • retrospective application of Section 4-A(4) challenged
  • government delay exclusion
  • judicial review of administrative orders
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (06) 96

Writ Petition No. 4160 of 2024

2025-06-06

G.S. Kulkarni, Advait M. Sethna

2025:BHC-AS:22567-DB

Harsh Meghani, Ashish Parwani, Dikshet Mehra, Shubham Mithilesh Challa, Anjali N. Helekar, Anu C. Kaladharan, S.D. Vyas, T.J. Karpe

Ashapura Minechem Ltd.

1. Indian Bureau of Mines through Ministry of Mines, Goa Regional Office; 2. Directorate of Geology and Mining, Government of Maharashtra; 3. Ministry of Ports and Mining, Government of Maharashtra; 4. Industries, Energy & Labour Department, Government of Maharashtra; 5. Ministry of Mines, Government of India

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 challenging orders imposing production deadline and seeking declaration, certiorari, prohibition, and mandamus regarding mining lease revival and mine code

Remedy Sought

Petitioner sought declaration that amended Section 4-A(4) of MMDR Act does not apply to pre-2021 leases; alternative relief to exclude government delay in computing revival period; quashing of orders dated 24 March 2023 and 9 February 2024; declaration that erstwhile Rule 8(4) of MCR 2016 is unconstitutional; setting aside letter dated 27 November 2018; mandamus directing Respondent No.1 to provide mine code

Filing Reason

Petitioner's mining lease statutorily lapsed due to non-compliance with MMDR Act, Rules, Environment Protection Act, and EIA Notification; subsequent revival orders imposed condition to commence production and dispatch by 28 March 2024, which petitioner challenged as arbitrary and violative of fundamental rights

Previous Decisions

Lapsing order dated 16 June 2021 by Respondent No.2 was revoked by order dated 24 March 2023, followed by order dated 9 February 2024; no prior judicial decisions mentioned in the available extract

Issues

Whether Section 4-A(4) of Mines and Minerals (Development and Regulation) Act, 1957 as amended with effect from 28.3.2021 applies to leases executed prior thereto Whether retrospective application of amended Section 4-A(4) violates fundamental rights under Articles 14, 19(1)(g) and 21 of the Constitution Whether time taken by government authorities (32 months out of 36 months) should be excluded in computing period under amended Section 4-A(4) Validity of orders dated 24 March 2023 and 9 February 2024 imposing condition to commence production and dispatch by 28 March 2024 Constitutionality of erstwhile Rule 8(4) of Mineral Concession Rules, 2016 Legality of letter dated 27 November 2018 issued by Respondent No.5 Entitlement to mine code from Respondent No.1

Submissions/Arguments

Petitioner contended that amended Section 4-A(4) of MMDR Act should not apply retrospectively to leases executed prior to 28.3.2021 and that such retrospective application violates Articles 14, 19(1)(g) and 21 of the Constitution; alternatively, government delay should be excluded in computing revival period; challenged Rule 8(4) of MCR 2016 as unconstitutional; sought quashing of impugned orders and mandamus for mine code. Respondents' contentions not mentioned in the available extract.

Ratio Decidendi

Not mentioned in the available extract. The extract includes the court's opening observation on state largesse and trusteeship, but does not contain the final legal reasoning or holding.

Judgment Excerpts

Any State Largess is rooted in the foundation of "trusteeship, which is premised on need and not on the individual greed." the issue that falls for consideration before the court is whether it can regularize the claims of the petitioner by an imprimatur of the court, even if, it would otherwise fall outside the statutory scope, ambit as the law would mandate, is to be tested in these proceedings.

Procedural History

Petitioner initially applied for grant of mining lease on 15 September 2003 for bauxite over 62.77 hectares in Village Sakhri, District Ratnagiri. Prior approval was granted by Respondent No.5 on 3 July 2009 under Section 5(1) of MMDR Act, subject to compliance with statutory provisions including environmental clearance. State Government requested necessary documents on 12 August 2009. Moratorium on EIA projects imposed from 16 August 2010 to 25 July 2017; MCZMA clarified on 11 September 2015 that moratorium ceased to apply. Mining plan approved on 26 December 2011; modified mining plan approved on 26 November 2015 on without prejudice basis. Petitioner applied for Terms of Reference on 10 December 2015; obtained TOR valid until 15 March 2019; requested extension on 8 February 2019 but did not obtain environmental clearance. Ministry of Mines issued Removal of Difficulties Order on 4 January 2017. Lapsing order passed by Respondent No.2 on 16 June 2021; revoked by order dated 24 March 2023; followed by order dated 9 February 2024 imposing production deadline of 28 March 2024. Writ petition filed in 2024; heard by division bench; reserved on 5 March 2025; pronounced on 6 June 2025.

Acts & Sections

  • Mines and Minerals (Development and Regulation) Act, 1957: Section 4-A(4), Section 5(1), Section 10A(2)(c)
  • Mineral Concession Rules, 1960:
  • Mineral Concession Rules, 2016: Rule 8(4)
  • Environment Protection Act, 1986:
  • Forest (Conservation) Act, 1980:
  • Constitution of India: Article 14, Article 19(1)(g), Article 21, Article 226
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Refusal to Injunction Bank Guarantee Encashment in Commercial Dispute. No Case of Fraud or Irretrievable Injustice Made Out to Restrain Bank Guarantee Invocation Under Contract Law Principles.
Related Judgement
High Court High Court of Karnataka Quashes Notification Appointing Retired District Judge as Judicial Member of Land Grabbing Court — Appointment Held Invalid for Non-Compliance with Section 7(7) of Karnataka Land Grabbing Prohibition Act, 2011. The court hel...