Bombay High Court Considers Section 34 Petition Against Arbitral Award in Railway Construction Contract Dispute. Petition Challenges Tribunal's Findings on Payment for Additional Work, Restricted Quantities, and Extension of Time Under General Conditions of Contract.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a railway construction contract between Union of India through the General Manager Central Railway (Railways) and PLR HC RBR JV, a joint venture contractor, concerning work on the railway line between Wardha and Nanded. The agreement dated September 24, 2018 followed a tender notice dated October 25, 2017 and a letter of acceptance dated May 24, 2018, with an approximate contract value of Rs 124.96 crores and an original completion deadline of May 23, 2020. The contractor was required to furnish a performance bank guarantee of Rs 6.24 crores and a security deposit of the same amount. Running Account Bills (RA Bills) were to be raised from time to time. The contractor completed work valued at about Rs 108.73 crores up to the sixth RA Bill, which was cleared. Delays arose due to failure of the Railways to acquire forest, revenue, and farmer land, and restrictions from the Covid-19 pandemic. The contractor sought extensions under Clauses 17-A(ii) and 17-A(iii) of the General Conditions of Contract, initially on April 29, 2020 and again on May 8, 2020. The Railways did not object and granted extension until December 31, 2020 without penalty, accepting price variation. A joint measurement on June 22, 2020 led to the seventh RA Bill prepared on July 13, 2020, showing cumulative work of Rs 138.78 crores. Despite joint measurement, the Railways withheld payment, contending that excess work fell within restricted quantities. Another joint measurement on March 16, 2021 for the eighth RA Bill reflected work valued at Rs 8.22 crores, but the eighth RA Bill was never prepared or approved. Thus, total work value was about Rs 147 crores while only Rs 124.95 crores was paid. A change in personnel, including a new Deputy Chief Engineer in January 2021, marked a shift in the Railways' stance. Extension was eventually granted on July 22, 2021 under Clause 17-B with a token penalty of Rs 1,000 and refusal to accept price variation, leading to a breakdown and arbitration. The arbitrator allowed the contractor's claims for restricted quantities of Rs 13,82,78,075, eighth RA Bill amount of Rs 8,22,68,293.35, price variation of Rs 2.87 crores, work completion certificate, refund of security deposit of Rs 6,24,78,130, costs of Rs 30 lakh, and interest at 8% pre-award and 10% post-award. The Railways filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award. The court's analysis, as per the available excerpt, focused on the arbitrator's factual findings regarding additional work, joint measurements, and extension. It noted that the extra work was directed and confirmed by Railways officials, recorded in the measurement book, and included in the seventh RA Bill prepared by Railways. The court observed that refusing to pay for executed work despite such direction and confirmation would lead to unjust enrichment. The final operative order is not included in the provided text, but the reasoning supports the arbitrator's findings.

Headnote

A) Arbitration Law - Scope of Section 34 Challenge - Limited Judicial Interference - Arbitration and Conciliation Act, 1996, Section 34 - The petition challenged the arbitral award on findings relating to additional work, RA bills, and extension of time. The court's analysis focused on whether the tribunal's factual findings were perverse or patently illegal. Held that the tribunal had examined evidence and returned reasoned findings after considering the record (Paras 1, 14-17).

B) Contract Law - Additional Work Beyond Restricted Quantities - Payment for Executed Work - General Conditions of Contract, Clause 41 - The tribunal found that the contractor executed excess work under directions and oversight of Railways officials, recorded in measurement book and seventh RA Bill prepared by Railways. Railways contended that absent formal written modification under Clause 41, no payment was due. Held that allowing Railways to repudiate payment despite directed and confirmed work would cause unjust enrichment (Paras 6-8, 14-17).

C) Contract Law - Running Account Bills and Joint Measurement - Obligation to Prepare and Pay - General Conditions of Contract - The seventh RA Bill was prepared based on joint measurement but not paid due to restricted quantities. The eighth RA Bill was not prepared despite joint measurement on March 16, 2021. The tribunal awarded amounts for both; the court noted that Railways itself prepared seventh RA Bill and acknowledged excess work (Paras 6-8, 14-16).

D) Contract Law - Extension of Time - Delay Attribution Clauses 17-A and 17-B - General Conditions of Contract, Clauses 17-A(ii), 17-A(iii), 17-B - The contractor sought extensions citing land acquisition, Covid-19 lockdown, and Railways' failure to grant approvals. Railways initially extended time without penalty then later granted extension under Clause 17-B with token penalty, indicating delay attributable to contractor. The tribunal's findings considered these circumstances and the breakdown in relations; the court analyzed the extension correspondence (Paras 4-5, 10-12).

E) Contract Law - Price Variation Claim - Entitlement to Price Variation - General Conditions of Contract - The tribunal awarded price variation of Rs 2.87 crores. Railways initially accepted price variation in extension letter dated June 29, 2020 but later refused. The court noted the initial acceptance of price variation arising from delay and the subsequent refusal after change in personnel (Paras 5, 10-12, 14).

F) Arbitration Law - Interest and Costs - Arbitral Tribunal's Power - Arbitration and Conciliation Act, 1996 - The tribunal awarded pre-award interest at 8%, post-award interest at 10% if amounts unpaid within three months, and costs of Rs 30 lakh. These reliefs were part of the award under challenge (Paras 14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award dated May 31, 2023 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality or perversity; whether the contractor was entitled to payment for additional work beyond restricted quantities despite absence of formal written modification under Clause 41 of the General Conditions of Contract; whether the Railways were justified in not preparing or approving the eighth Running Account Bill despite joint measurement; whether extension of time was correctly granted under Clause 17-B with token penalty; whether the tribunal's award of interest and costs was sustainable

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the provided text (final operative order not included); the court's reasoning in the available excerpt appears to favor upholding the arbitral award.

Law Points

  • Arbitral awards under Section 34 cannot be set aside merely on re-appreciation of evidence
  • extra work directed and confirmed by employer must be paid despite lack of written modification
  • refusal to pay for executed work leads to unjust enrichment
  • extension of time under GCC clauses depends on attribution of delay
  • joint measurement and RA bills prepared by employer create payment obligations
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (06) 54

Commercial Arbitration Petition No. 51 of 2024 along with Interim Application (L) No. 20681 of 2024

2025-06-24

Somasekhar Sundaresan, J.

2025:BHC-OS:9305

R.V. Govilkar, Senior Advocate for Petitioner; Vishwajit P. Sawant, Senior Advocate a/w. Vasudeva Naidu i/b. Prabhakar M. Jadhav for Respondent

Union of India Through The General Manager Central Railway

PLR HC RBR JV

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated May 31, 2023 arising from disputes under a railway construction contract.

Remedy Sought

Union of India (Railways) sought setting aside of the arbitral award; the respondent contractor sought dismissal of the petition and enforcement of the claims allowed by the tribunal, including through an interim application.

Filing Reason

Disputes over payment for additional work beyond restricted quantities, non-preparation and non-payment of the eighth Running Account Bill despite joint measurement, denial of price variation, and differing attribution of delay under extension clauses.

Previous Decisions

Arbitral tribunal passed award on May 31, 2023 allowing the contractor's claims; no prior court decisions are mentioned in the provided text.

Issues

Whether the arbitral award dated May 31, 2023 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality or perversity. Whether the contractor was entitled to payment for additional work beyond restricted quantities despite absence of formal written modification under Clause 41 of the General Conditions of Contract. Whether the Railways were justified in not preparing or approving the eighth Running Account Bill despite joint measurement having been carried out. Whether extension of time was correctly granted under Clause 17-B with token penalty, affecting price variation and delay claims. Whether the tribunal's award of interest and costs was sustainable.

Submissions/Arguments

Railways contended that additional work constituted modification of the agreement requiring written instrument under Clause 41 of the General Conditions of Contract, so no payment was due for excess quantities. Railways contended that deficiencies and inadequate manpower and machinery deployed by the contractor caused delay, justifying extension under Clause 17-B with token penalty. Railways contended that the eighth Running Account Bill was not prepared due to deficiencies found in the joint measurement and that the contractor abandoned work in November 2020. Contractor contended that excess work was carried out under directions and oversight of Railways officials, recorded in the measurement book and seventh Running Account Bill, and refusal to pay would unjustly enrich the Railways. Contractor contended that non-payment of the approved seventh Running Account Bill, refusal to prepare the eighth Running Account Bill despite joint measurement, and denial of price variation made it impossible to continue work; delay was due to land acquisition and Covid-19 lockdown, not attributable to the contractor.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, the court does not re-appreciate evidence; concurrent factual findings by the arbitral tribunal are not to be interfered with unless perverse or patently illegal. Extra work carried out under directions of Railways officials, recorded in the measurement book, and included in Running Account Bills prepared by Railways must be paid; refusing payment would lead to unjust enrichment. Formal written modification under Clause 41 of the General Conditions of Contract cannot be used to repudiate payment where work was directed, executed, and confirmed.

Judgment Excerpts

This is a Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) challenging an arbitral award dated May 31, 2023 (“Impugned Award”) in connection with disputes and differences relating to an agreement dated September 24, 2018 (“Agreement”). The Learned Arbitral Tribunal considered the evidence presented by the parties, examined the record, and has returned factual findings analysing the evidence to rule as follows: permitting the Railways to repudiate the obligation to pay in the teeth of the demonstrated direction to carry out the work and confirmation of the work actually done, would lead to unjust enrichment of the Railways

Procedural History

Tender notice issued by Railways on October 25, 2017. Letter of acceptance issued on May 24, 2018 with approximate contract value of Rs 124.96 crores. Agreement executed on September 24, 2018. Original completion deadline was May 23, 2020. Contractor sought extension on April 29, 2020 and May 8, 2020 under Clauses 17-A(ii) and 17-A(iii) of GCC. Railways granted extension until December 31, 2020 on June 29, 2020 without penalty and accepting price variation. Joint measurement on June 22, 2020 and seventh RA Bill prepared on July 13, 2020, but payment withheld. Joint measurement for eighth RA Bill on March 16, 2021; eighth RA Bill not prepared or approved. New deadline became May 31, 2021; contractor sought extension on May 31, 2021 to December 31, 2021. Railways granted extension on July 22, 2021 under Clause 17-B with token penalty of Rs 1,000 and refused price variation. Disputes led to arbitration, culminating in arbitral award dated May 31, 2023. Railways filed Commercial Arbitration Petition No. 51 of 2024 under Section 34 of the Arbitration and Conciliation Act, 1996. Interim Application (L) No. 20681 of 2024 was also filed by the respondent contractor.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
  • General Conditions of Contract: 17, 17-A(ii), 17-A(iii), 17-B, 41
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Considers Section 34 Petition Against Arbitral Award in Railway Construction Contract Dispute. Petition Challenges Tribunal's Findings on Payment for Additional Work, Restricted Quantities, and Extension of Time Under General Condit...
Related Judgement
High Court NOTICE OF MOTION NO. 443 OF 2012