High Court of Judicature at Bombay Considered Extension of Arbitral Tribunal Mandate Under Section 29-A of Arbitration and Conciliation Act, 1996 in Chenab Bridge Project Dispute. The Court Analyzed Objections Regarding Tribunal's Procedural Decisions and Delay While Examining Whether to Extend the Mandate of the Standing Arbitral Tribunal Until December 31, 2026.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a contract dated November 24, 2004 for the design and construction of a special rail bridge across the river Chenab on the Katra-Laole Section of the Udhampur-Srinagar-Baramulla Rail Link Project. The parties executed a separate arbitration agreement on February 28, 2012 constituting a three-member Standing Arbitral Tribunal (SAT) to adjudicate disputes and differences under the contract on a half-yearly claims basis. The SAT's composition was heavily influenced by the respondent, Konkan Railway Corporation Limited, which curated the list of arbitrators. After initial changes, the Supreme Court on September 23, 2013 appointed Justice (Retd.) R.V. Raveendran as Presiding Arbitrator, forming the Raveendran SAT for claims 1 to 3, while the Jain SAT handled claims 4 onwards. Subsequently, due to dissatisfaction with the Jain SAT, the parties constituted the Mittal SAT on January 16, 2021, which became seized of claims 4 to 24. The present petitions under Section 29-A of the Arbitration and Conciliation Act, 1996 sought extension of the mandate of the Mittal SAT, which had expired on March 1, 2024, until December 31, 2026. The petitioner argued that significant progress had been made, including conclusion of submissions for claims 10 to 19 on February 6, 2025 and filing of written submissions by April 5, 2025. The respondent Konkan Railway contended that the tribunal's operational and procedural decisions conflicted with the Arbitration Agreement, that the tribunal did not proceed without undue delay, that further amendments could cause delay, and that the court should replace the tribunal's constituents. The court analyzed the scope of its jurisdiction under Section 29-A, noting that the arbitral tribunal is the master of proceedings and that judicial interference in operational and procedural matters is minimal. The court also observed that the parties had no quarrel with the sequential handling of claims and that the Raveendran SAT had already rendered an award for claims 1 to 3, while the Mittal SAT had reserved judgment on claims 4 to 9. The excerpt ends before the final holding.

Headnote

A) Arbitration Law - Extension of Arbitral Tribunal Mandate - Section 29-A, Arbitration and Conciliation Act, 1996 - Court Approval Required for Extension Beyond 12 Months - The petitions sought extension of the mandate of the Mittal SAT, which had expired on March 1, 2024, until December 31, 2026. The court noted that under Section 29-A, parties need approval of the court to extend the mandate beyond 12 months, and consent of parties may extend it only by another six months. The court emphasized that its jurisdiction under Section 29-A is limited and it cannot sit in judgment on the wisdom of operational and procedural decisions of the arbitral tribunal. (Paras 11-14)

B) Contract Law - Standing Arbitral Tribunal - Arbitration Agreement dated February 28, 2012 - Consistency in Adjudication of Multiple Claims - The parties executed a contract for design and construction of a rail bridge and later an arbitration agreement constituting a three-member Standing Arbitral Tribunal (SAT) to adjudicate disputes on a half-yearly claims basis, with the same body having jurisdiction over all claims relating to the same project. The SAT was intended to provide a stable and continuous dispute resolution platform but lacked institutional support, operating as an ad hoc tribunal. After changes in composition, the Mittal SAT became seized of disputes from the fourth to the twenty-fourth half-yearly claim, including claims no. 10 to 19 which are the subject of these petitions. (Paras 3-10)

C) Arbitration Law - Procedural Autonomy - Sections 29-A, Arbitration and Conciliation Act, 1996 - Tribunal as Master of Proceedings - The court held that the arbitral tribunal is the master of proceedings and has full freedom on how to conduct the proceedings and sequence actions necessary for adjudication. The court observed that the parties had no quarrel with the sequential nature of dealing with the claims and that the scope for judicial interference under Section 29-A is minimal, precluding review of operational decisions like amendment of Statement of Claim or grouping of claims. (Paras 14-15)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the mandate of the Mittal Standing Arbitral Tribunal should be extended until December 31, 2026 under Section 29-A of the Arbitration and Conciliation Act, 1996; whether the court should replace the constituents of the tribunal; whether the tribunal's procedural and operational decisions conflicted with the Arbitration Agreement and caused undue delay

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Section 29-A of Arbitration and Conciliation Act
  • 1996 requires court approval for extension of arbitral tribunal mandate beyond 12 months and consent for additional 6 months
  • arbitral tribunal is master of proceedings
  • court cannot review operational or procedural decisions of tribunal under Section 29-A
  • standing arbitral tribunal intended for consistent adjudication of multiple claims under same contract
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (06) 51

Commercial Arbitration Petition (L) No. 12314 of 2025 with connected petitions 12318, 12323, 12326, 12333, 12337, 12340, 12376, 12396, 12397 of 2025

2025-06-09

Somasekhar Sundaresan, J.

2025:BHC-OS:8422

Mr. Zal Andhyarujina, Senior Advocate a/w Mr. Karl Tamboly, Mr. Punit Damodar, Ms. Raveena Kinkhabwala, Mr. Hitesh Singhvi, Mr. Akshay Dhayalkar, i/b Kanga & Co., for Petitioner in CARBPL/12376/2025; Mr. Ashish Kamat, Senior Advocate, a/w Mr. Sarosh Bharucha, Mr. D.J. Kakalia, Ms Bhavna Jaipuria, Mr Paresh Patkar & Kartik Hede i/b Mulla & Mulla & CBC, for Respondent

Chenab Bridge Project Undertaking

Konkan Railway Corporation Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petitions under Section 29-A of the Arbitration and Conciliation Act, 1996 seeking extension of the mandate of the Mittal Standing Arbitral Tribunal.

Remedy Sought

Petitioner Chenab Bridge Project Undertaking sought extension of the mandate of the Mittal SAT until December 31, 2026, after it expired on March 1, 2024; respondent Konkan Railway opposed and sought dismissal and replacement of tribunal constituents.

Filing Reason

The mandate of the Mittal SAT expired on March 1, 2024, and the tribunal had not completed adjudication of half-yearly claims no. 10 to 19 (and others up to 24).

Previous Decisions

The Raveendran SAT rendered award for half-yearly claims no. 1 to 3; the Mittal SAT reserved judgment for claims no. 4 to 9; the High Court rejected Konkan Railway's intervention against the SAT's amendment order on September 16, 2022; the Supreme Court appointed Justice R.V. Raveendran as Presiding Arbitrator on September 23, 2013.

Issues

Whether the mandate of the Mittal SAT should be extended under Section 29-A of the Arbitration and Conciliation Act, 1996 until December 31, 2026. Whether the court should replace the constituents of the SAT due to alleged conflict with the Arbitration Agreement and delay. Whether the court can review the procedural and operational decisions of the arbitral tribunal under Section 29-A.

Submissions/Arguments

Konkan Railway contended that the Mittal SAT's operational and procedural decisions conflicted with the Arbitration Agreement, particularly regarding dates and deadlines for half-yearly claims no. 10 to 19. Konkan Railway argued that the Mittal SAT did not proceed without undue delay and alacrity. Konkan Railway submitted that the Mittal SAT may permit amendment of the Statement of Claim for half-yearly claims no. 10 to 19, which would cause further delay. Konkan Railway requested that the court replace the constituents of the SAT with a retired judge of a High Court or the Supreme Court under Section 29-A.

Ratio Decidendi

The arbitral tribunal is the master of proceedings and has full freedom on how to conduct the proceedings and sequence the actions necessary for appropriate adjudication. The scope for court to interfere with conduct of arbitration is minimal and under Section 29-A, court cannot sit in judgment on the wisdom of operational and procedural decisions of the arbitral tribunal. Extension of mandate beyond 12 months requires court approval, and consent of parties may extend it only by another six months.

Judgment Excerpts

These Petitions are essentially applications under Section 29-A of the Arbitration and Conciliation Act, 1996 (“the Act”) seeking an extension of mandate of the Arbitral Tribunal, which is said to have expired on March 1, 2024. The extension sought is for until December 31, 2026. Under Section 29-A of the Act, the parties would need approval of this Court for extension of the mandate of the arbitral tribunal beyond a period of 12 months, which period is extendable by consent of the parties by only another six months. The arbitral tribunal is the master of proceedings and has full freedom on how to conduct the proceedings and sequence the actions necessary for appropriate adjudication.

Procedural History

The parties executed a contract on November 24, 2004 for design and construction of a special rail bridge across river Chenab. On February 28, 2012, they executed an arbitration agreement constituting a three-member Standing Arbitral Tribunal (SAT). On September 23, 2013, the Supreme Court appointed Justice (Retd.) R.V. Raveendran as Presiding Arbitrator, forming the Raveendran SAT for claims 1 to 3, while the Jain SAT handled claims 4 onwards. On January 3, 2020, Chenab sought termination of the Jain SAT for undue delay, which was denied. Chenab nominated a new arbitrator on January 2, 2021, and Konkan Railway appointed a new Presiding Arbitrator, Mr. Aditya Kumar Mittal, on January 16, 2021, constituting the Mittal SAT for claims 4 to 24. On July 23, 2022, the Mittal SAT allowed amendment of Statement of Claim for certain claims. The High Court rejected Konkan Railway's intervention against that amendment on September 16, 2022. On February 8, 2024, Konkan Railway filed an application for framing issues, including res judicata, limitation, and jurisdictional objections. Submissions for half-yearly claims no. 10 to 19 concluded on February 6, 2025, and written submissions were filed by April 5, 2025. The present petitions were filed seeking extension of the Mittal SAT mandate, which had expired on March 1, 2024.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 29-A, Section 11
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature at Bombay Considered Extension of Arbitral Tribunal Mandate Under Section 29-A of Arbitration and Conciliation Act, 1996 in Chenab Bridge Project Dispute. The Court Analyzed Objections Regarding Tribunal's Procedural Decision...
Related Judgement
High Court High Court of Bombay's Writ Petition No. 5424 of 2014 Challenges College Tribunal Order Reinstating Lecturer; Employer's Non-Compliance with Reinstatement Order Precludes Reliance on Employee's Non-Compliance with VRS Direction