Supreme Court Dismisses Appeal in Railway Supply Contract Dispute; Formal Supply Order Constituted Binding Contract Despite Cancellation Clause. Cancellation Clause in Tender Did Not Apply to Formal Supply Order Once Specific Quantities and Delivery Dates Were Fixed.

In Favour of Prosecution
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a contract for the supply of jaggery to railway grain shops owned by the Dominion of India, represented by the General Manager of the Madras and Southern Mahratta Railway. The railway administration invited tenders for the supply of 14,000 imperial maunds of cane jaggery during February and March 1948. The respondent, a supplier, submitted a tender which was accepted by the Deputy General Manager by letter dated January 29, 1948, subject to payment of a security deposit of Rs. 7,900. The tender form contained a note in paragraph 2 stating that the administration reserved the right to cancel the contract at any stage during the tenure of the contract without calling up the outstandings on the unexpired portion of the contract. Under paragraph 9 of the tender, a formal order for supply would be placed only after the security deposit was made. On February 16, 1948, the Deputy General Manager reiterated acceptance subject to terms and conditions including a delivery programme of 3,600 maunds on March 1, 1948, 3,500 maunds on March 22, 1948, 3,500 maunds on April 5, 1948, and 3,500 maunds on April 21, 1948; the same cancellation note was repeated at the end of these terms. Delivery dates were slightly changed by a letter dated February 28, 1948. By letter dated March 8, 1948, the Deputy General Manager cancelled the balance quantity of jaggery outstanding against the order dated February 16, 1948, and closed the contract. The respondent protested but the administration relied on the cancellation clause. The respondent then instituted a suit against the Union of India for damages for breach of contract. The trial court dismissed the suit holding that the railway administration could cancel the contract at any time without liability. The High Court held the cancellation clause void and, since the trial court had not decided damages, remanded the suit for that purpose. The Union of India appealed to the Supreme Court by special leave. The principal legal issues were whether the cancellation clause in the tender applied to formal supply orders after specific quantities and delivery dates had been fixed, whether the contract imposed a binding obligation to purchase the entire 14,000 maunds or only up to that maximum as required, and whether the cancellation stipulation was valid and enforceable. The appellant contended that the agreement was only for such quantity as it might require up to a maximum of 14,000 maunds and that the cancellation clause was expressly agreed and valid. The respondent argued that the contract was complete for a definite quantity on specified dates, the cancellation clause was repugnant and void, and even if valid, cancellation could be exercised only for good and reasonable grounds. The Supreme Court construed the tender conditions, particularly paragraphs 2, 8, 9 and 13. It observed that mere acceptance of the tender did not amount to placing an order for any definite quantity on a definite date; it only established the terms that would govern future orders. Paragraph 9 required a formal order after security deposit. The court held that the note reserving the right to cancel the contract at any stage during its tenure referred to the preliminary agreement before a formal order was placed. The expressions "tenure of the contract" and "outstandings on the unexpired portion of the contract" indicated a continuing arrangement that could be terminated as to future, unexpired supplies for which no formal order had been made. Once a formal order was placed for specific quantities and specific delivery dates, that order amounted to a binding contract making it incumbent on the supplier to deliver and on the railway administration to accept the goods. Therefore, the cancellation clause did not apply to the formal order of February 16, 1948. The court relied on Chatturbhuj Vithaldas Jasani v. Moneshwar Parashram. The appeal was dismissed, and the High Court's view that the clause could not defeat the binding obligation was upheld, though on the ground of construction rather than invalidity.

Headnote

A) Contract Construction - Interpretation of Cancellation Clause - Reservation of right to cancel contract at any stage applies only to agreement before formal supply order and not to binding supply orders already placed - Not mentioned - The tender contained a note reserving the right to cancel the contract at any stage during its tenure without calling up outstandings on the unexpired portion. The court construed this clause as applying to the preliminary agreement between acceptance of tender and placement of formal order, not to supply orders specifying definite quantities and delivery dates. Held that once a formal order was placed, it constituted a binding contract that could not be cancelled under this clause. (Paras 2, 8, 9, 13)

B) Formation of Contract - Tender Acceptance and Formal Order - A formal order for supply specifying quantity and delivery dates creates enforceable obligations on both parties - Not mentioned - Paragraph 9 of the tender provided that a formal order would be placed only after security deposit was made and receipt furnished. The court held that mere acceptance of the tender did not amount to placing an order for definite quantity on a definite date. Held that the formal order dated February 16, 1948, for delivery of 3,600 maunds on March 1, 1948, and other installments, amounted to a binding contract. (Paras 8, 9)

C) Obligation to Purchase - Definite Quantity Requirement - Once formal order placed, the purchaser is bound to accept delivery of the specified quantities, not merely a maximum limit - Not mentioned - The appellant contended that it had agreed to buy only such quantity as it might require up to a maximum of 14,000 maunds with no enforceable obligation to purchase the entire quantity. The court rejected this contention with respect to quantities covered by formal orders. Held that the formal order made it incumbent on the Deputy General Manager to accept the jaggery delivered in pursuance of that order. (Paras 2, 13)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the cancellation clause in the tender applied to formal supply orders after definite quantities and dates were fixed; whether the contract imposed a binding obligation on the appellant to purchase the entire quantity of 14,000 maunds or only a maximum quantity as per appellant's requirement; whether the stipulation allowing cancellation at any stage was valid and binding, or repugnant and invalid.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court, on construction, held that the cancellation clause did not apply to the formal order placed for specific quantities on specified dates, which constituted a binding contract; the appeal by the Union of India was dismissed.

Law Points

  • Tender acceptance alone does not amount to placing a formal order for definite quantity
  • formal order creates binding contract
  • cancellation clause applies only to pre-formal order agreement
  • once formal order placed purchaser bound to accept goods
  • reservation of right to cancel cannot be used to cancel binding supply orders
Subscribe to unlock Law Points Subscribe Now

Case Details

1963 LawText (SC) (05) 30

Civil Appeal No. 53 of 1961

1963-05-09

Raghubar Dayal, K. Subbarao, J.R. Mudholkar

1966 AIR 1724, 1964 SCR (3) 774

H. N. Sanyal, Additional Solicitor-General of India, K. L. Gosain, P. D. Xenon, A. V. Viswanatha Sastri, M. S. K. Sastri

Union of India

Maddala Thathiah

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for damages for breach of contract

Remedy Sought

Respondent sought damages from appellant (Union of India) for breach of contract arising out of cancellation of supply order for jaggery.

Filing Reason

Appellant cancelled balance quantity of jaggery due under formal supply order dated February 16, 1948, claiming right under cancellation clause.

Previous Decisions

Trial Court dismissed suit holding appellant could cancel contract without liability; Madras High Court held cancellation clause void and remanded suit for determination of damages.

Issues

Whether the cancellation clause in the tender applied to formal supply orders after definite quantities and dates were fixed. Whether the contract imposed a binding obligation on the appellant to purchase the entire quantity of 14,000 maunds or only a maximum quantity as per appellant's requirement. Whether the stipulation allowing cancellation at any stage was valid and binding, or repugnant and invalid.

Submissions/Arguments

Appellant contended that the contract was only for such quantity as appellant might require, up to a maximum of 14,000 maunds, with no enforceable obligation to purchase the entire quantity, and that the cancellation clause was expressly agreed and valid, amounting to a provision for discharge or determination. Respondent contended that the contract was complete for a definite quantity of 14,000 maunds on dates specified in the order dated February 16, 1948, that the cancellation stipulation was repugnant and void, and even if valid, appellant could rescind only for good and reasonable ground and not arbitrarily.

Ratio Decidendi

A tender acceptance followed by a formal order for supply of definite quantities on definite dates creates a binding contract. A reservation clause in the tender allowing cancellation 'at any stage during the tenure of the contract' applies only to the unexpired portion of the agreement before a formal order is placed; it does not permit unilateral cancellation of obligations arising from a formal supply order already issued.

Judgment Excerpts

This Administration reserves the right to cancel the contract at any stage during the tenure of the contract without calling up the outstandings on the unexpired portion of the contract. Once the order was placed for such supply on such dates, that order amounted to a binding contract making it incumbent on the respondent to supply jaggery in accordance with the terms of the order and also making it incumbent on the Deputy General Manager to accept the jaggery delivered in pursuance of that order. The expression 'tenure of the contract' contemplates the contract being of a continuing nature.

Procedural History

The respondent instituted a suit for damages against the Union of India after cancellation of the balance supply order. The trial court dismissed the suit holding that the railway administration could cancel the contract at any time without liability. The Madras High Court held the cancellation clause void and remanded the suit for determination of damages. The Union of India appealed to the Supreme Court by special leave.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Union of India in Essential Commodities Act Price Control Case — Ex-Factory Price Notification Valid. Essential Commodities Act, 1955 Section 3 and Sugar (Control) Order, 1955 Clause 5 Validly Authorize Ex-Factory Price Fixati...
Related Judgement
Supreme Court Supreme Court Dismisses Appeal in Railway Supply Contract Dispute; Formal Supply Order Constituted Binding Contract Despite Cancellation Clause. Cancellation Clause in Tender Did Not Apply to Formal Supply Order Once Specific Quantities and Delivery ...