Supreme Court Partly Allows Appeal Against Dismissal of Injunction Against Bank Guarantee Invocation in Arbitration Dispute. Conditional Bank Guarantee for Retention Money Was Not Encashable Until Successful Completion of Trial Operations, and Its Invocation Was Restrained as Not in Terms of the Guarantee.

  • 1
Judgement Image
Font size:
Print

Case Note & Summary

By special leave, Larsen & Toubro Limited appealed against the Bombay High Court order dismissing its arbitration petition under Section 41 of the Arbitration Act, 1940, seeking injunction against Maharashtra State Electricity Board from invoking bank guarantees. The dispute arose from a contract dated 9 March 1989 for supply and commissioning of a Coal Handling Plant, valued at Rs.61,11,07,200. Larsen & Toubro furnished five bank guarantees: advance payment, performance, partial release of retention money (two), and security against liquidated damages. The plant was completed after delay, and the Board took it over on 10 June 1994 with a takeover certificate. On 29 March 1994, Larsen & Toubro lodged its claim, which the Board denied. Larsen & Toubro invoked arbitration on 4 June 1994, and the arbitrators directed it to file a claim on 30 September 1994, giving the Board time until 30 November 1994 to file a counter-claim. On 1 October 1994, the Board invoked all bank guarantees except the performance guarantee. The High Court initially ordered status quo on 17 October 1994. Larsen & Toubro filed Arbitration Petition Lodging No. 240/94 seeking injunction, alleging fraudulent and dishonest invocation and that advance and liquidated damages guarantees were invoked after expiry. The High Court, per Justice N.D. Vyas, dismissed the petition, holding that no fraud or irretrievable injustice was made out and that the appellant could claim damages before the arbitrators. The interim order was made final, and the petition was dismissed. The main legal issues were whether the High Court erred in applying the strict test for injunctions against bank guarantees; whether invocation of certain guarantees was after expiry; and whether the conditional Citi Bank guarantee for retention money could be invoked before successful completion of trial operations. Larsen & Toubro argued that no amount remained under the advance guarantee, that retention guarantees should be returned after takeover, that liquidated damages required proof and quantification before invocation, and that advance and liquidated damages guarantees were invoked after expiry. The Board argued that letters dated 14 September 1994 and 10 May 1994 to the banks requesting extension contained a clause that if extension was not received, the communication would be treated as notice for encashment; thus invocation was in time. The Board also contended that unconditional guarantees were independent and that damages were available in arbitration. Relying on United Commercial Bank v. Bank of India, U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers (P) Ltd., General Electric Technical Services Company Inc. v. Punj Sons (P) Ltd., Elian and Rabbath v. Matsas and Matsas, and Svenska Handelsbanken v. Indian Charge Chrome, the Supreme Court reiterated that an irrevocable bank guarantee or letter of credit can be interfered with only in cases of established fraud and irretrievable injustice; mere irretrievable injustice without a prima facie case of established fraud is insufficient. The Court found no fraud or irretrievable injustice for the unconditional guarantees. It upheld the High Court's conclusion that invocation of the advance guarantee was timely due to the letter dated 10 May 1994, and that the appellant had an adequate remedy before the arbitrators. However, for the Citi Bank guarantee (Item No. 3) covering partial release of retention money for Rs.2,72,39,850, the Court examined the guarantee terms: the bank guaranteed the amount "till successful completion of trial operations" and the validity was extendable "till successful completion of trial operations." Since the plant had been taken over after trial and performance tests, the condition for encashment had not been fulfilled. Therefore, the invocation of the Citi Bank guarantee was not in terms of the guarantee. The Supreme Court partly allowed the appeal, modifying the High Court order only in respect of Item No. 3 and restraining its invocation. The refusal of injunction for the other guarantees (advance, liquidated damages, and Standard Chartered retention money) was upheld. The performance guarantee was not invoked and was not part of the proceedings.

Headnote

A) Bank Guarantee - Injunction - Fraud and Irretrievable Injustice - Arbitration Act, 1940, Section 41 - Injunction against encashment of unconditional bank guarantees cannot be granted unless there is established fraud and irretrievable injustice. The Supreme Court followed Svenska Handelsbanken and held that mere irretrievable injustice without prima facie case of established fraud is insufficient. The appellant failed to make out such a case for advance, liquidated damages, and Standard Chartered retention money guarantees. Held that High Court's refusal of injunction for these guarantees was correct.

B) Bank Guarantee - Conditional Guarantee - Invocation as per terms - Arbitration Act, 1940, Section 41 - A conditional bank guarantee can be invoked only upon fulfillment of its express conditions. Citi Bank guarantee covering retention money stated that it was valid until successful completion of trial operations; the plant had been taken over after trial and performance tests, so the condition for encashment was not met. The Supreme Court modified the High Court order and restrained invocation of this guarantee. Held that invocation was not in terms of the guarantee.

C) Bank Guarantee - Validity of Invocation - Notice for extension - Arbitration Act, 1940, Section 41 - A communication requesting extension of a bank guarantee that states if extension is not received the letter will be treated as notice for encashment, sent before expiry, constitutes timely invocation. The High Court found that letters dated 14.9.1994 and 10.5.1994 to banks served this purpose. The Supreme Court upheld that invocation of advance and liquidated damages guarantees was in time. Held that invocation was not after expiry.

D) Arbitration - Irretrievable Injustice - Availability of Damages - Arbitration Act, 1940, Section 41 - The availability of a remedy before arbitrators to claim damages for wrongful encashment negates irretrievable injustice. The Supreme Court agreed with the High Court that the appellant could seek damages before arbitrators for amounts wrongly recovered. Therefore no injunction was warranted for unconditional guarantees. Held that no irretrievable injustice existed.

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court erred in refusing injunction against invocation of bank guarantees absent established fraud or irretrievable injustice; whether invocation of certain guarantees was after expiry; whether conditional bank guarantee for retention money could be invoked before successful completion of trial operations.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court partly allowed the appeal. It modified the High Court's order only in respect of Item No. 3, the bank guarantee issued by Citi Bank for partial release of retention money of Rs.2,72,39,850, and restrained its invocation. The High Court's refusal to injunct the other bank guarantees (advance payment, liquidated damages, and retention money guarantee by Standard Chartered Bank) was upheld. The performance guarantee was not invoked and was not part of the proceedings.

Law Points

  • irrevocable bank guarantee/letter of credit cannot be interfered with unless fraud and irretrievable injustice
  • fraud must be established fraud
  • irretrievable injustice without prima facie fraud insufficient
  • conditional guarantee must be invoked as per terms
  • notice requesting extension with encashment clause before expiry valid
  • damages before arbitrator negates irretrievable injustice
Subscribe to unlock Law Points Subscribe Now

Case Details

1995 LawText (SC) (09) 65

Arbitration Petition Lodging No. 240/94 (High Court of Judicature at Bombay); Civil Appeal by Special Leave (number not mentioned in judgment text)

1995-09-13

Jagdish Saran Verma, K.S. Paripoornan

1996 AIR 334, 1995 SCC (6) 68, JT 1995 (7) 18, 1995 SCALE (5)342

B.M. Naik, Harish N. Salve

Larsen & Toubro Limited

Maharashtra State Electricity Board & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal by special leave against dismissal of arbitration petition seeking injunction restraining invocation of bank guarantees.

Remedy Sought

Appellant sought injunction against first respondent from invoking/claiming/demanding/releasing amounts under five bank guarantees furnished for a Coal Handling Plant contract.

Filing Reason

Appellant alleged fraudulent and dishonest invocation of bank guarantees; some guarantees invoked after expiry; first respondent invoked all except performance guarantee after arbitration commenced.

Previous Decisions

Bombay High Court (N.D. Vyas, J.) dismissed Arbitration Petition Lodging No. 240/94 and declined injunction, holding no fraud or irretrievable injustice; interim status quo order made final; appeal by special leave.

Issues

Whether injunction against encashment of bank guarantees can be granted absent established fraud or irretrievable injustice. Whether invocation of advance and liquidated damages guarantees was after expiry and thus invalid. Whether conditional bank guarantee for retention money (Item No. 3, Citibank) could be invoked before successful completion of trial operations and taking over. Whether irrevocable bank guarantees/letters of credit should be interfered with only in case of fraud or irretrievable injustice.

Submissions/Arguments

Appellant contended that guarantees were fraudulently and dishonestly invoked; no balance remained under advance guarantee; retention guarantees should be returned after takeover; liquidated damages require proof of suffering and quantification before invocation; advance and liquidated damages guarantees were invoked after expiry. Respondents contended that no fraud or irretrievable injustice existed; letters dated 14.9.1994 and 10.5.1994 to banks requesting extension stated that if extension not received, communication treated as notice for encashment prior to expiry; bank guarantees were independent and unconditional; appellant could claim damages before arbitrator.

Ratio Decidendi

An irrevocable bank guarantee or confirmed letter of credit cannot be interfered with unless there is established fraud and irretrievable injustice; mere irretrievable injustice without a prima facie case of established fraud is of no consequence. A conditional bank guarantee can be invoked only in accordance with its express terms; invocation of a guarantee that is conditional on successful completion of trial operations is invalid if that condition is not fulfilled. A communication requesting extension of a bank guarantee that states that if extension is not received the letter will be treated as notice for encashment, sent before expiry, constitutes valid invocation in time. Availability of damages before arbitrators for wrongful encashment negates irretrievable injustice.

Judgment Excerpts

...... in case of confirmed bank guarantees/irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud. ...... ...... there should be prima facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining the encashment of bank guarantee. The Bank hereby agree unequivocally and uncondition to guarantee the said amount released by the Board till successful completion of trial operations in due performance of the contract and undertakes to at Bombay within 48 hrs. on demand in writing from MSEB...

Procedural History

Appellant's tender for Coal Handling Plant was accepted, and contract dated 9.3.1989 was executed for Rs.61,11,07,200. Appellant furnished five bank guarantees. Plant completion was delayed; after trial and performance test, the Plant was taken over by first respondent on 10.6.1994 with takeover certificate. Appellant lodged claim on 29.3.1994; first respondent denied claim. Appellant invoked arbitration on 4.6.1994; arbitrators met on 14.9.1994 and gave directions. Appellant filed claim on 30.9.1994; first respondent given time to file counter-claim until 30.11.1994. On 1.10.1994 first respondent invoked all bank guarantees except performance guarantee. Court passed status quo order on 17.10.1994. Appellant filed Arbitration Petition Lodging No. 240/94 under Section 41 of Arbitration Act, 1940. High Court (N.D. Vyas, J.) dismissed petition on 20.10.1994 and made interim order final. Appeal by special leave to Supreme Court; leave granted; Supreme Court partly allowed appeal.

Acts & Sections

  • Arbitration Act, 1940: Section 41
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds High Court in Civil Appeal on Benami Transaction — Plaintiffs Fail to Discharge Burden of Proof. Source of Purchase Money Held Most Important Test for Determining Benami; Apparent Purchaser Presumed Real Owner.
Related Judgement
High Court Madras High Court Dismisses Second Appeal in Succession Dispute — Concurrent Findings of Fact Not Interfered With. Court holds that plaintiffs failed to prove they are legal heirs of deceased Perumal Naidu and that the third defendant's claim as so...