Case Note & Summary
By special leave, Larsen & Toubro Limited appealed against the Bombay High Court order dismissing its arbitration petition under Section 41 of the Arbitration Act, 1940, seeking injunction against Maharashtra State Electricity Board from invoking bank guarantees. The dispute arose from a contract dated 9 March 1989 for supply and commissioning of a Coal Handling Plant, valued at Rs.61,11,07,200. Larsen & Toubro furnished five bank guarantees: advance payment, performance, partial release of retention money (two), and security against liquidated damages. The plant was completed after delay, and the Board took it over on 10 June 1994 with a takeover certificate. On 29 March 1994, Larsen & Toubro lodged its claim, which the Board denied. Larsen & Toubro invoked arbitration on 4 June 1994, and the arbitrators directed it to file a claim on 30 September 1994, giving the Board time until 30 November 1994 to file a counter-claim. On 1 October 1994, the Board invoked all bank guarantees except the performance guarantee. The High Court initially ordered status quo on 17 October 1994. Larsen & Toubro filed Arbitration Petition Lodging No. 240/94 seeking injunction, alleging fraudulent and dishonest invocation and that advance and liquidated damages guarantees were invoked after expiry. The High Court, per Justice N.D. Vyas, dismissed the petition, holding that no fraud or irretrievable injustice was made out and that the appellant could claim damages before the arbitrators. The interim order was made final, and the petition was dismissed. The main legal issues were whether the High Court erred in applying the strict test for injunctions against bank guarantees; whether invocation of certain guarantees was after expiry; and whether the conditional Citi Bank guarantee for retention money could be invoked before successful completion of trial operations. Larsen & Toubro argued that no amount remained under the advance guarantee, that retention guarantees should be returned after takeover, that liquidated damages required proof and quantification before invocation, and that advance and liquidated damages guarantees were invoked after expiry. The Board argued that letters dated 14 September 1994 and 10 May 1994 to the banks requesting extension contained a clause that if extension was not received, the communication would be treated as notice for encashment; thus invocation was in time. The Board also contended that unconditional guarantees were independent and that damages were available in arbitration. Relying on United Commercial Bank v. Bank of India, U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers (P) Ltd., General Electric Technical Services Company Inc. v. Punj Sons (P) Ltd., Elian and Rabbath v. Matsas and Matsas, and Svenska Handelsbanken v. Indian Charge Chrome, the Supreme Court reiterated that an irrevocable bank guarantee or letter of credit can be interfered with only in cases of established fraud and irretrievable injustice; mere irretrievable injustice without a prima facie case of established fraud is insufficient. The Court found no fraud or irretrievable injustice for the unconditional guarantees. It upheld the High Court's conclusion that invocation of the advance guarantee was timely due to the letter dated 10 May 1994, and that the appellant had an adequate remedy before the arbitrators. However, for the Citi Bank guarantee (Item No. 3) covering partial release of retention money for Rs.2,72,39,850, the Court examined the guarantee terms: the bank guaranteed the amount "till successful completion of trial operations" and the validity was extendable "till successful completion of trial operations." Since the plant had been taken over after trial and performance tests, the condition for encashment had not been fulfilled. Therefore, the invocation of the Citi Bank guarantee was not in terms of the guarantee. The Supreme Court partly allowed the appeal, modifying the High Court order only in respect of Item No. 3 and restraining its invocation. The refusal of injunction for the other guarantees (advance, liquidated damages, and Standard Chartered retention money) was upheld. The performance guarantee was not invoked and was not part of the proceedings.
Headnote
A) Bank Guarantee - Injunction - Fraud and Irretrievable Injustice - Arbitration Act, 1940, Section 41 - Injunction against encashment of unconditional bank guarantees cannot be granted unless there is established fraud and irretrievable injustice. The Supreme Court followed Svenska Handelsbanken and held that mere irretrievable injustice without prima facie case of established fraud is insufficient. The appellant failed to make out such a case for advance, liquidated damages, and Standard Chartered retention money guarantees. Held that High Court's refusal of injunction for these guarantees was correct. B) Bank Guarantee - Conditional Guarantee - Invocation as per terms - Arbitration Act, 1940, Section 41 - A conditional bank guarantee can be invoked only upon fulfillment of its express conditions. Citi Bank guarantee covering retention money stated that it was valid until successful completion of trial operations; the plant had been taken over after trial and performance tests, so the condition for encashment was not met. The Supreme Court modified the High Court order and restrained invocation of this guarantee. Held that invocation was not in terms of the guarantee. C) Bank Guarantee - Validity of Invocation - Notice for extension - Arbitration Act, 1940, Section 41 - A communication requesting extension of a bank guarantee that states if extension is not received the letter will be treated as notice for encashment, sent before expiry, constitutes timely invocation. The High Court found that letters dated 14.9.1994 and 10.5.1994 to banks served this purpose. The Supreme Court upheld that invocation of advance and liquidated damages guarantees was in time. Held that invocation was not after expiry. D) Arbitration - Irretrievable Injustice - Availability of Damages - Arbitration Act, 1940, Section 41 - The availability of a remedy before arbitrators to claim damages for wrongful encashment negates irretrievable injustice. The Supreme Court agreed with the High Court that the appellant could seek damages before arbitrators for amounts wrongly recovered. Therefore no injunction was warranted for unconditional guarantees. Held that no irretrievable injustice existed.
Issue of Consideration
Whether the High Court erred in refusing injunction against invocation of bank guarantees absent established fraud or irretrievable injustice; whether invocation of certain guarantees was after expiry; whether conditional bank guarantee for retention money could be invoked before successful completion of trial operations.
Final Decision
The Supreme Court partly allowed the appeal. It modified the High Court's order only in respect of Item No. 3, the bank guarantee issued by Citi Bank for partial release of retention money of Rs.2,72,39,850, and restrained its invocation. The High Court's refusal to injunct the other bank guarantees (advance payment, liquidated damages, and retention money guarantee by Standard Chartered Bank) was upheld. The performance guarantee was not invoked and was not part of the proceedings.
Law Points
- irrevocable bank guarantee/letter of credit cannot be interfered with unless fraud and irretrievable injustice
- fraud must be established fraud
- irretrievable injustice without prima facie fraud insufficient
- conditional guarantee must be invoked as per terms
- notice requesting extension with encashment clause before expiry valid
- damages before arbitrator negates irretrievable injustice



