Supreme Court Considers Appeal Against Division Bench Order Setting Aside Arbitration Award in Port Trust Tender Work Delay Compensation Dispute. Division Bench Had Set Aside Umpire's Award and Remitted Matter for Fresh Consideration; Supreme Court's Final Ruling Not Stated in Extracted Text.

  • 0
Judgement Image
Font size:
Print

Case Note & Summary

Background — The dispute arose from a contract for certain port works awarded by the Board of Trustees of Madras Port Trust to a contractor in the late 1950s. The contractor submitted a tender on 11 November 1957 with deviations, including a request that the completion period be extended for delays beyond its control and that it be entitled to compensation for such delays. The Board accepted the tender on 6 October 1958. Thereafter, because foreign exchange could not be released to the contractor for purchasing machinery on its own account, the parties agreed that the Board would import the plant and machinery on its own account and hire it out to the contractor. A formal contract was signed on 9 April 1960 without incorporating the contractor's suggested modifications. The total contract value was Rs 1,63,00,000. Delays occurred in importing the machinery: the period envisaged was about six months, but it took about twelve months. The contractor completed the work within an extended period granted by the Board. After completion, the contractor raised a dispute claiming an additional Rs 14,93,654.78, mainly for loss caused by the Board's delay in importing machinery. The arbitration clause was invoked; each side nominated a retired judge, and they in turn appointed Dr. P.V. Rajamannar, retired Chief Justice of Madras High Court, as umpire. The umpire issued a speaking award on 30 October 1965. He found that the Board's offer to import machinery was not gratuitous, but that there was no undertaking to supply the machinery within six months and the Board was not responsible for the delay. He also held that the contractor's claims fell within the scope of the arbitration clause, but that the contractor was not entitled to any compensation. If compensation were payable, he assessed Rs 5 lakhs for delays in importing machinery and Rs 1 lakh for other delays. The Board filed OP No. 276 of 1965 to make the award a rule of court; the contractor filed OP No. 213 of 1966 to set it aside under Sections 16, 30 and 33 of the Arbitration Act, 1940. A Single Judge of the Madras High Court substantially agreed with the award and made it a rule of court, overruling objections of misconduct and error apparent. On Letters Patent Appeal, a Division Bench allowed the appeal, set aside the award, and remitted the matter to the umpire for fresh consideration. The Division Bench affirmed that the contractor's claims were arbitrable and that the Board's undertaking was not gratuitous, but did not record a finding on whether the 9% extra payment covered delay compensation. The present appeal to the Supreme Court by the Board of Trustees challenged the Division Bench's order. The extracted text ends without the Supreme Court's final reasoning or decision.

Headnote

A) Arbitration - Arbitrability of Dispute - Scope of Arbitration Clause - Arbitration Act, 1940, Sections 16, 30, 33 - The contractor's claim for compensation for delayed supply of imported machinery, though based partly on correspondence rather than the formal contract, fell within the scope of the arbitration clause, and the umpire had jurisdiction to decide it. The Division Bench upheld this finding, noting that the contractor was entitled to seek a decision on the disputed claims by arbitration. Held that reservations made unilaterally did not preclude arbitration of the claims. (Paras Not mentioned)

B) Arbitration - Award - Misconduct and Error Apparent - Arbitration Act, 1940, Sections 30, 33 - The contractor challenged the umpire's award on grounds of misconduct and error apparent on the face of the award. The Single Judge substantially agreed with the award and made it a rule of court, overruling these objections. The Division Bench later set aside the award and remitted the matter to the umpire for fresh consideration in light of its findings. Held that the Division Bench's decision was under appeal in the present matter. (Paras Not mentioned)

C) Contract - Obligation to Supply Imported Machinery - Gratuitous Undertaking - Contract terms and corresponding agreements - The Board of Trustees had agreed to import plant and machinery and hire it to the contractor. The umpire and the Division Bench both held that this undertaking was not gratuitous but created rights and obligations; however, the umpire found no specific undertaking to supply within six months, and thus the Board was not responsible for the delay in supply of plant and machinery. Held that supply of imported machinery did not fall within the 'services' contemplated by the contract, but no finding was recorded on whether extra payment of 9% over contract price covered such delay compensation. (Paras Not mentioned)

D) Arbitration - Compensation for Delay - Umpire's Assessment - Arbitration Act, 1940 - The umpire, while denying the contractor's entitlement to compensation under the main heads, assessed that if compensation were payable, Rs 5 lakhs would be fair for delays in supply of imported plant and machinery and Rs 1 lakh for other delays such as inclement weather and breakdown. Held that the contractor was not entitled to any compensation under issues 10, 11 and 14, but the assessment was contingent on an appellate finding of entitlement. (Paras Not mentioned)

E) Civil Procedure - Letters Patent Appeal - Review of Arbitration Award - Arbitration Act, 1940 - The Division Bench in Letters Patent Appeal reversed the Single Judge's decision making the award a rule of court, set aside the award, and remitted the matter for fresh consideration. The present appeal before the Supreme Court challenged that order. Held that the procedural history leading to the Supreme Court was marked by initial award, confirmation by Single Judge, and reversal by Division Bench. (Paras Not mentioned)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Board of Trustees was liable to compensate the contractor for delay in importing machinery; whether the contractor's claims fell within the arbitration clause; whether the award was liable to be set aside for misconduct or error apparent under Sections 16, 30, 33 of Arbitration Act, 1940

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in extracted text; the Division Bench allowed the contractor's Letters Patent Appeal, set aside the umpire's award, and remitted the matter to the umpire for fresh consideration.

Law Points

  • Arbitration clause covers disputes arising from correspondence connected with contract
  • Undertaking to import machinery not gratuitous if creates obligations
  • No liability for delay absent undertaking to supply within specific period
  • Award set aside for error apparent/misconduct under Arbitration Act
  • Unilateral reservations do not preclude arbitration
Subscribe to unlock Law Points Subscribe Now

Case Details

1995 LawText (SC) (08) 80

1995-08-14

B.P. Jeevan Reddy, S.C. Agrawal

1995 AIR 2423, 1995 SCC (5) 531, JT 1995 (6) 48, 1995 SCALE (4)742

Trustees of the Port of Madras

Engineering Constructions Corporation Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration dispute arising from a contract for port works between Madras Port Trust and contractor regarding compensation for delay in supply of imported machinery.

Remedy Sought

Board sought to make arbitration award rule of court; contractor sought to set aside award under Sections 16, 30 and 33 of Arbitration Act, 1940.

Filing Reason

After completion of work, contractor claimed additional amount due to delay in supplying machinery and other causes; umpire made award partly declining compensation; both parties filed OPs.

Previous Decisions

Single Judge made award rule of court overruling contractor's objections; Division Bench on appeal set aside award and remitted to umpire for fresh consideration.

Issues

Whether Board's undertaking to import equipment and spares was gratuitous service? Whether Board had undertaking to supply imported machinery within six months and was responsible for delay? Whether contractor's claims fell within arbitration clause and were arbitrable despite unilateral reservations? Whether contractor was entitled to compensation for delay in supply of imported machinery and other grounds? Whether umpire misconduct or error apparent on face of award warranting setting aside under Sections 16, 30, 33 Arbitration Act?

Submissions/Arguments

Contractor argued that Board was obliged to import machinery within a period of about six months and delay caused loss, entitling compensation for delay and other heads. Board argued that no undertaking to supply within a particular period existed, six months was only an estimate, and extra payment of 9% over contract price covered all such delays. Contractor raised objections under Sections 16, 30 and 33 of Arbitration Act alleging misconduct of umpire and error apparent on face of award. Board sought to make the umpire's award a rule of court.

Ratio Decidendi

Not mentioned in extracted text.

Judgment Excerpts

Interminable, time consuming, complex and expensive court procedures impelled jurists to search for an alternative forum, less formal, more effective and speedy for resolution of disputes avoiding procedural claptrap and this led them to Arbitration Act, 1940. the learned umpire further held that in case the respondent was found entitled to any compensation, a sum of Rupees five lakhs would represent a fair compensation for the delays in the supply of imported plant and machinery and that another sum of Rupees one lakh would be the reasonable compensation for the delay on other grounds like inclement weather, break-down etc. the undertaking by the Board to secure the plant and equipment from abroad was undoubtedly an obligation in the

Procedural History

1957: Port Trust invited tenders; respondent submitted tender on 11 November 1957 with deviations. 1958-10-06: Board accepted tender. 1960-04-09: Respondent signed formal agreement without modifications. Work completed within extended period; respondent claimed additional amount. Arbitration: respondent nominated W.S. Krishnaswamy Naidu; Board nominated Somasundaram; they designated Dr. P.V. Rajamannar as umpire. 1965-10-30: Umpire made speaking award. Board filed O.P.No. 276 of 1965 to make award rule of court; respondent filed O.P.No. 213 of 1966 to set aside award under Sections 16, 30 and 33 of Arbitration Act. Single Judge Palaniswamy J made award rule of court. Letters Patent Appeal to Division Bench allowed appeal, set aside award and remitted to umpire for fresh consideration. Appeal to Supreme Court (present).

Acts & Sections

  • Arbitration Act, 1940: 16, 30, 33
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Allows Wife's Appeal Declaring Marriage Void Under Section 11 of Hindu Marriage Act, 1955 — Inter-Faith Marriage Not Solemnized as per Hindu Rites. Marriage between a Christian and a Hindu is void ab initio under the Hindu M...
Related Judgement
High Court Gujarat High Court Remands Land Acquisition Compensation Case for Fresh Determination of Market Value. The court followed its earlier decision in a related group of appeals to remand the matter for fresh determination based on additional evidence und...