Case Note & Summary
The Supreme Court dealt with appeals by the State of Gujarat against enhancement of compensation in land acquisition proceedings. The dispute arose from acquisition of large extents of land for an irrigation dam No.2 Project under notification dated 18 December 1980 under Section 4(1) of the Land Acquisition Act, 1894. Landowners entered into written consent agreements on 11 March 1983 accepting compensation determined by the Land Acquisition Officer plus 25 per cent extra and expressly agreeing not to seek reference under Section 18. The Collector determined market value on 25 March 1983 and awarded compensation with the additional 25 per cent, which was paid to the landowners. Despite this, the landowners sought reference under Section 18 on 26 April 1986. The Assistant Judge, Rajkot, by award and decree dated 29 June 1991 enhanced compensation to Rs.200 per are for Bagayat land and Rs.140 per are for Jirayat land. The Gujarat High Court confirmed the enhancement on 3 July 1992. The State appealed to the Supreme Court. The core legal issue was whether landowners who entered into a consent agreement under Section 11(2) of the Land Acquisition Act, 1894 and received compensation without protest could later seek reference under Section 18. The State contended that the written agreement, which included a clause expressly stating that landowners would not go to court under Section 18, barred any reference. The landowners, whose argument was accepted by the Reference Court, contended that the agreements were unregistered under the Registration Act, 1908 and therefore could not contract out of the statutory right to seek reference. The Supreme Court examined Sections 11(2), 11(4), 18, 31(2), 23, and 28 of the Land Acquisition Act. It held that Section 11(2) permits parties to enter into a written agreement and that an award made in terms of such agreement is conclusive and binding. Section 11(4) expressly provides that no agreement made under Section 11(2) shall be liable to registration under the Registration Act, 1908, thereby negating the argument based on non-registration. The Court also noted the second proviso to Section 31(2), which bars a person who received compensation otherwise than under protest from making an application under Section 18. Since the landowners received compensation under the consent agreement without protest, they manifested acceptance of the award and lost the right to seek reference. The Court reasoned that the right to seek reference arises only upon non-acceptance of the award, evidenced by protest in writing. A valid reference under Section 18 is a precondition for the civil court to consider adequacy of compensation and grant statutory benefits such as solatium and interest. Because the consent agreement under Section 11(2) obviated the necessity of reference, the civil court lacked jurisdiction to enhance compensation. Accordingly, the Supreme Court allowed the appeals, set aside the orders of the Reference Court and the High Court, and held that the landowners were not entitled to any enhancement. No costs were awarded.
Headnote
A) Land Acquisition - Consent Award under Section 11(2) - Bars Reference under Section 18 - Land Acquisition Act, 1894, Sections 11(2), 18 - The landowners entered into a written agreement under Section 11(2) accepting compensation plus 25% and waiving reference under Section 18; Clause 14 expressly stated no court under Section 18. The Court held that such agreement is conclusive and binds parties, obviating reference; valid consent award under Section 11(2) precludes any later challenge to compensation. Held that no option is left to seek reference under Section 18 (Paras 3-9, 11). B) Land Acquisition - Agreement Not Requiring Registration - Section 11(4) of Land Acquisition Act, 1894 - Registration Act, 1908 - The Reference Court had rejected the State's reliance on the agreement because it was unregistered under the Registration Act; the Supreme Court clarified that Section 11(4) expressly obviates registration of agreements made under Section 11(2). Therefore, absence of registration did not invalidate the consent award. Held that the agreement need not be registered (Paras 7-8, 11). C) Land Acquisition - Receipt of Compensation Without Protest - Section 31(2) Proviso and Section 18 - Land Acquisition Act, 1894, Sections 31(2), 18 - Under second proviso to Section 31(2), a person who receives compensation without protest cannot apply under Section 18. The respondents accepted payment in terms of the consent agreement without protest, manifesting acceptance of award. Held that receipt of compensation otherwise than under protest bars reference under Section 18 (Paras 6, 10-11). D) Land Acquisition - Civil Court Jurisdiction - Enhancement of Compensation - Land Acquisition Act, 1894, Sections 18, 23(1), 23(2), 28 - The civil court's jurisdiction to consider adequacy of compensation arises only upon valid reference under Section 18. Since no reference was permissible, the civil court lacked jurisdiction to determine higher market value or grant statutory benefits like solatium and interest. Held that the reference court and High Court orders enhancing compensation were set aside (Paras 10-12).
Issue of Consideration
Whether landowners who accepted compensation under a written consent agreement under Section 11(2) of the Land Acquisition Act, 1894 and waived reference under Section 18 can still seek reference for enhancement; whether civil court can determine higher compensation.
Final Decision
Appeals allowed; orders of reference court as confirmed by High Court set aside; landowners not entitled to seek reference under Section 18; no costs.
Law Points
- Consent award under Section 11(2) Land Acquisition Act
- 1894 binds parties and bars reference under Section 18
- agreement under Section 11(2) need not be registered under Registration Act
- 1908 due to Section 11(4)
- receipt of compensation without protest bars application under Section 18
- civil court jurisdiction contingent on valid reference
- waiver of statutory right to reference in exchange for 25% extra compensation is permissible



