Supreme Court Upheld Claimant's Right to Additional Amount Under Section 23(1-A) of Land Acquisition Act, 1894 from Date of Section 4(1) Notification. The Court Ruled That When Possession Is Taken Before Amendment Act 68 of 1984 and Award Is Made After, Additional Amount Runs from Notification Date, Not Date of Possession.

  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose in the context of land acquisition compensation under the Land Acquisition Act, 1894. The Special Tahsildar (Land Acquisition), P.W.D. Schemes, Vijayawada (the State) had acquired land belonging to M.A. Jabbar. The Section 4(1) notification was published on March 6, 1980, but possession of the land had already been taken on February 15, 1965. The Collector made the award under Section 11 on September 30, 1983. The High Court of Andhra Pradesh in A.S. No. 95 of 1987 determined compensation at Rs. 120 per square yard and awarded solatium at 30% on the enhanced compensation. It also awarded additional amount at 12% per annum on the market value from the date of notification (March 6, 1980) to the date of award (September 30, 1983), and interest at 9% per annum for the first year after possession and 15% per annum thereafter until payment. The State appealed, contending that since possession was taken before the Land Acquisition (Amendment) Act, 1984 (Act 68 of 1984) came into force, the claimant was not entitled to the additional amount under Section 23(1-A). The claimant cross-appealed, arguing that because possession was taken earlier, the additional amount should be paid from the date of possession, i.e., February 15, 1965, relying on the statutory language 'whichever is earlier'. The Supreme Court confined the leave to the question of entitlement to benefits under the Amending Act 68 of 1984. The Court examined Section 23(1-A), which provides for an additional amount at 12% per annum on the market value for the period from the date of publication of the notification under Section 4(1) to the date of the Collector's award or the date of taking possession, whichever is earlier. The Court reasoned that since possession had already been taken on February 15, 1965, before the notification under Section 4(1) on March 6, 1980, awarding additional amount from the date of possession would effectively give retrospective effect to sub-section (1-A) of Section 23 introduced by the Amendment Act. The Amendment Act was prospective, and its transitory provision had only limited retrospective activity. Therefore, the correct starting point for the additional amount was the date of publication of the notification under Section 4(1), not the earlier date of possession. The Supreme Court held that the claimant was entitled to additional amount at 12% per annum on the enhanced market value from March 6, 1980 to September 30, 1983. Accordingly, the Court dismissed both the State's appeal and the claimant's cross-appeal, with no order as to costs.

Headnote

A) Land Acquisition - Additional Amount Under Section 23(1-A) - Interpretation of Period Between Section 4(1) Notification and Award - Land Acquisition Act, 1894, Section 23(1-A) - The central issue was whether a claimant whose land was taken possession of before the commencement of the Land Acquisition (Amendment) Act, 1984 and before the Section 4(1) notification could claim additional amount under Section 23(1-A) from the date of possession. The Supreme Court held that when possession was already taken before the Amendment Act came into force, awarding additional amount from the date of possession would give retrospective effect to the amending provision. Held that the claimant was entitled to additional amount at 12% per annum on enhanced market value from the date of publication of the notification under Section 4(1) (March 6, 1980) to the date of award (September 30, 1983) (Paras 1-4).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a claimant whose land was taken possession of before the commencement of the Land Acquisition (Amendment) Act, 1984, but where the award was made after the Amendment Act, is entitled to the additional amount under Section 23(1-A) of the Land Acquisition Act, 1894, and from what date such amount is payable.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed both the State's appeal and the claimant's cross-appeal, holding that the claimant is entitled to additional amount at 12% per annum on enhanced market value from the date of publication of the notification under Section 4(1) (March 6, 1980) to the date of award (September 30, 1983). No costs.

Law Points

  • Interpretation of Section 23(1-A)
  • Land Acquisition Act
  • 1894
  • additional amount payable at 12% per annum on enhanced market value from date of Section 4(1) notification to date of award or earlier possession
  • prospective operation of Amendment Act 68 of 1984
  • no retrospective application to possession taken before amendment.
Subscribe to unlock Law Points Subscribe Now

Case Details

1995 LawText (SC) (01) 67

C.A. No. 1891 of 1989

1995-01-11

K. Ramaswamy, Sujata V. Manohar

1995 AIR 762, 1995 SCC (2) 142, JT 1995 (1) 383, 1995 SCALE (1)144

The Special Tahsildar (LA), P.W.D. Schemes, Vijayawada

M.A. Jabbar

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Land acquisition compensation dispute concerning additional amount under Section 23(1-A).

Remedy Sought

State appealed against High Court award of additional amount from date of notification; claimant cross-appealed seeking additional amount from date of possession (February 15, 1965).

Filing Reason

The dispute arose because possession of acquired land was taken on February 15, 1965, before the Land Acquisition (Amendment) Act, 1984 came into force, but the Section 4(1) notification was issued later on March 6, 1980 and the award was made on September 30, 1983, creating uncertainty about the starting point for the additional amount.

Previous Decisions

High Court of Andhra Pradesh in A.S. No. 95 of 1987 determined compensation at Rs.120 per square yard, awarded solatium at 30%, additional amount at 12% per annum on market value from the date of notification under Section 4(1) (March 6, 1980) to date of award (September 30, 1983), and interest at 9% per annum for one year from possession then 15% per annum till payment.

Issues

Whether the claimant is entitled to the additional amount under Section 23(1-A) of the Land Acquisition Act, 1894 when possession was taken before the Amendment Act 68 of 1984 and before the Section 4(1) notification; and if so, from which date the additional amount should be calculated.

Submissions/Arguments

The State argued that since possession had already been taken prior to the Amending Act 68 of 1984 coming into force, the claimant was not entitled to the additional amount. The claimant argued that as possession was taken earlier and the owner was deprived of enjoyment of the land, the additional amount should be paid from the date of taking possession, relying on the phrase 'whichever is earlier' in Section 23(1-A).

Ratio Decidendi

When possession of land has been taken before the Land Acquisition (Amendment) Act 68 of 1984 came into force, and the award is made after the Amendment Act, the additional amount under Section 23(1-A) is payable for the period from the date of publication of the notification under Section 4(1) to the date of award, because awarding from the earlier date of possession would amount to giving retrospective effect to the amending provision, which is prospective.

Judgment Excerpts

In addition to the market value of the land, the Court shall in every case award an amount calculated at the rate of twelve per centum per annum on such market value for the period commencing on and from the date of the publication of the notification under s.4(1), in respect of such land to the date of the award of the Collector or the date of taking possession of the land, whichever is earlier. Therefore, we hold that the claimants would be entitled to additional amount of the enhanced market value at 12% per annum from the date of the publication of the notification under s.4(1) till the date of the award, since possession had already been taken before the Amending Act has come into force.

Procedural History

Collector made award under Section 11 on September 30, 1983. On reference, the High Court of Andhra Pradesh in A.S. No. 95 of 1987 enhanced compensation and granted statutory benefits. The State filed Civil Appeal No. 1891 of 1989 and the claimant filed a cross-appeal before the Supreme Court; leave was confined to the question of entitlement to benefits under the Land Acquisition (Amendment) Act, 1984. The Supreme Court dismissed both the appeal and the cross-appeal.

Acts & Sections

  • Land Acquisition Act, 1894: Section 4(1), Section 11, Section 23(1-A), Section 23(2), Section 28
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Co-operative Registrar in Misfeasance Proceedings Against Managing Committee Members Due to Absence of Bias. Registrar's Prior Show-Cause Notice and Administrative Supervision Did Not Disqualify Him from Acting as Arbitrator Und...
Related Judgement
Supreme Court Supreme Court Directs State of Uttar Pradesh to Expedite Premature Release Cases for Life Convicts Under Article 32. The Court held that the State must apply its premature release policies non-arbitrarily and transparently, considering cases based on...