Case Note & Summary
The dispute arose from an alleged joint venture between U.P. Rajkiya Nirman Nigam Ltd., a state government undertaking, and Indure Pvt. Ltd. for submitting tenders to the U.P. State Electricity Board for construction, supply, and erection of mechanical equipment and construction work including consultancy services. The appellant had purchased tender documents on February 6, 1984, and the respondent approached it for joint participation. Negotiations led to a draft agreement dated June 22, 1984, which the appellant sent to the respondent for signature. The appellant did not sign the draft. On June 27, 1984, the respondent returned the agreement signed but with clause 10 deleted and clause 12 materially altered to convert joint liability into individual liability of the appellant. Tenders were submitted by the appellant alone on June 30, 1984, the last date, but withdrawn on February 23, 1985, before negotiations with the Board. The respondent later invoked clause 14 of the draft agreement for arbitration, claiming damages of Rs.1,68,73,628. The appellant filed an application under Section 33 of the Arbitration Act, 1940, seeking a declaration that no agreement or arbitration agreement existed. The Delhi High Court held that a concluded contract emerged from the respondent's counter-proposal and the appellant's conduct, including submission of tenders and absence of communication rejecting alterations. The Supreme Court examined the requirements of Sections 3, 4, 7, and 10 of the Indian Contract Act, 1872, and Section 2(a) of the Arbitration Act, 1940. It held that the respondent's counter-proposal with material alterations destroyed consensus ad idem and required fresh acceptance by the appellant, which never occurred. The appellant's submission of tenders to the Board was not an acceptance of the counter-proposal, as the tenders were unilateral and later withdrawn, and the respondent had disowned material responsibilities. The Court also noted that the appellant, being a government undertaking, could not be bound without due execution as per its Articles of Association. The indoor management doctrine did not cure the lack of acceptance of materially altered terms. Consequently, no concluded contract or independent arbitration agreement came into existence. The Supreme Court allowed the appeal and set aside the High Court order.
Headnote
A) Contract Law - Formation of Contract - Counter-Proposal and Acceptance - Indian Contract Act, 1872, Sections 3, 4, 7 - A counter-proposal containing material alterations operates as rejection of original offer and requires fresh acceptance; silence or conduct not amounting to absolute and unqualified acceptance cannot form contract - Court held respondent's counter-proposal deleting clause 10 and altering clause 12 was not accepted by appellant; tenders submitted by appellant were unilateral and withdrawn before acceptance by Board; no concluded contract emerged (Paras 1-8). B) Arbitration - Existence of Arbitration Agreement - Section 2(a), Arbitration Act, 1940 - An arbitration agreement must be a written agreement to submit differences to arbitration, but parties must be ad idem; arbitration clause integral to draft agreement cannot survive if no concluded contract - Court held no independent arbitration agreement existed; clause 14 was part of draft agreement which never became binding because of lack of consensus ad idem; respondent had no right to invoke arbitration (Paras 1-8). C) Contract Law - Government Undertaking - Execution of Contract per Articles of Association - Indian Contract Act, 1872, Section 10 - A government undertaking is bound only by contracts duly executed in accordance with its Articles of Association; indoor management doctrine cannot cure lack of execution when material terms are altered - Court rejected respondent's reliance on Palmer on Companies Law; appellant not bound because no authorized signing and material alterations destroyed consensus (Paras 4-5). D) Contract Law - Acceptance by Conduct - Material Alterations - Indian Contract Act, 1872, Section 7 - Acceptance by conduct cannot be inferred when offeree has made counter-offer altering material terms; conduct must be unequivocal and referable to terms offered - Court held appellant's submission of tenders to Board was not acceptance of respondent's counter-proposal because respondent had disowned responsibilities under clauses 10 and 12 (Paras 4-6).
Issue of Consideration
Whether a concluded contract emerged between the parties from the draft agreement and counter-proposal, and consequently whether an arbitration agreement existed under Section 2(a) of the Arbitration Act, 1940.
Final Decision
Supreme Court allowed appeal and set aside High Court order; held that no concluded contract emerged between parties and no arbitration agreement existed; appellant not bound by clause 14 of draft agreement.
Law Points
- Arbitration agreement requires consensus ad idem
- counter-proposal with material alterations destroys consensus
- acceptance by conduct must be unequivocal
- government undertaking bound only by duly executed contracts
- no independent arbitration agreement without concluded contract



