Supreme Court Allows Appeal in Part, Upholds Arbitrator's Jurisdiction on Extra Work Claim and Interest Pendente Lite. Arbitrator's Award for Extra Earth Work Is Within Scope of Reference; Interest Pendente Lite Permissible but Pre-Reference Interest Denied.

  • 0
Judgement Image
Font size:
Print

Case Note & Summary

This case arose from a construction contract between a contractor and the State of U.P. for lining of the Upper Ganga Canal. The agreement dated 17.2.1989 included Clause 32 on extra items and Clause 51 providing for arbitration under the Indian Arbitration Act, 1940. Disputes arose regarding payment for extra earth work and other claims. By Office Memorandum dated 4.10.1992, the disputes were referred to sole arbitrator Shri Thakur Das. The arbitrator gave a speaking award dated 23.5.1994, awarding Rs. 72,22,740 for extra earth work beyond lip cutting in reach km 189.50-190.70, along with interest at 18% per annum from 1.1.1991 to the date of award on the total claim of Rs. 1,71,11,208 and further interest at 6% per annum from award to decree/payment. The District Judge granted decree in terms of the award. The High Court partly allowed the State's objections, disallowing the extra earth work claim on the ground that the arbitrator exceeded the scope of reference. The contractor appealed to the Supreme Court challenging this finding; the State cross-appealed against the award of interest at 18% from 1.1.1991. The Supreme Court considered two legal issues: (1) whether the arbitrator exceeded the scope of reference in deciding the rate for extra earth work; and (2) whether the arbitrator had jurisdiction to award interest for the period from 1.1.1991 to the date of award. On the first issue, the Court noted that the Office Memorandum expressly referred the dispute regarding rate for extra earth work to arbitration. Both parties argued the issue before the arbitrator, who gave detailed reasons. The Court held that interpretation of the contract is within the arbitrator's domain once the dispute is referred, and the High Court erred in holding otherwise. On the second issue, the Court relied on the Constitution Bench decision in Secretary, Irrigation Department, Government of Orissa v. G.C. Roy, which established that an arbitrator has power to award interest pendente lite unless excluded by the contract, analogous to Section 34 of the Code of Civil Procedure, 1908. The Court examined Clause 1.18 of the Technical Specifications, which barred claims for interest or damage, but found that it did not specifically exclude interest pendente lite. The Court distinguished Durga Ram Parsad v. Government of Andhra Pradesh, where interest was denied due to a specific contractual clause. The Court held that the arbitrator could award interest from the date of reference to the date of award, but not for the pre-reference period, which the appellant conceded. Accordingly, the Supreme Court allowed the contractor's appeal except that no interest was payable for the pre-reference period, and dismissed the State's cross-appeal with modification. No order as to costs was made.

Headnote

A) Arbitration - Scope of Reference and Contract Interpretation - Expressly Referred Disputes Are Within Arbitrator's Jurisdiction - Indian Arbitration Act, 1940 (Sections not specified) - The High Court erred in holding that the arbitrator exceeded his scope by deciding the rate for extra earth work beyond lip cutting. The dispute was item (i) in the Office Memorandum referring disputes to arbitration; both parties argued before the arbitrator; the arbitrator gave a speaking award with detailed reasons. Held that interpretation of the contract is a matter for the arbitrator once the dispute is referred (Paras 4-5).

B) Arbitration - Interest Pendente Lite - Arbitrator's Power Analogous to Section 34 CPC - Code of Civil Procedure, 1908, Section 34 and Indian Arbitration Act, 1940 - Clause 1.18 of the Technical Specifications did not bar interest pendente lite; relying on G.C. Roy, the arbitrator has discretion to award interest from date of reference to date of award to do complete justice. Pre-reference interest cannot be awarded unless contract provides. Held that arbitrator's award of interest was modified to deny pre-reference interest but allow pendente lite (Para 5).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitrator exceeded the scope of reference in awarding rate for extra earth work; whether the arbitrator had jurisdiction to award interest for the period from 1.1.1991 to the date of award (pre-reference and pendente lite)

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal arising out of SLP(C) No. 4328/1997 allowed save and except appellant not entitled to any interest on principal amount prior to arbitrator entering upon reference; respondent's appeal dismissed with modification; no order as to costs.

Law Points

  • Arbitrator's jurisdiction over disputes expressly referred
  • interpretation of contract within scope
  • interest pendente lite power analogous to Section 34 CPC
  • pre-reference interest not allowed unless contract provides
  • clause must specifically exclude interest to bar arbitrator
Subscribe to unlock Law Points Subscribe Now

Case Details

1997 LawText (SC) (10) 36

SLP(C) No. 4328 of 1997; SLP(C) No. 20055 of 1997 (arising out of CC 6248/97) [Civil Appeal No. 7375 of 1997]

1997-10-21

Sujata V. Manohar, D.P. Wadhwa

M/s. Ram Nath International Construction Pvt. Ltd.

State of U.P.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against High Court judgment modifying arbitral award; cross-appeals by contractor and State.

Remedy Sought

Appellant sought restoration of arbitrator's award on extra earth work; respondent sought to set aside interest awarded for pre-reference period.

Filing Reason

High Court disallowed claim for extra earth work holding arbitrator exceeded scope; respondent challenged interest award.

Previous Decisions

District Judge granted decree in terms of award; High Court partly allowed objections, disallowed extra work claim, and modified interest; cross-appeals filed.

Issues

Whether the arbitrator exceeded the scope of reference in awarding rate for extra item of earth work beyond lip cutting in reach km 189.50 to 190.70 Whether the arbitrator had jurisdiction to award interest for the period from 1.1.1991 to the date of award, particularly pre-reference interest

Submissions/Arguments

Appellant: The dispute was expressly referred to arbitration; arbitrator has jurisdiction to interpret contract; interest pendente lite permissible under G.C. Roy. Respondent: Extra work claim beyond scope; clause 1.18 bars interest; Durga Ram Parsad denies interest pendente lite.

Ratio Decidendi

An arbitrator does not exceed scope of reference when deciding a dispute expressly referred to him; interpretation of contract is within arbitrator's domain. Arbitrator has power to award interest pendente lite unless expressly excluded by contract, analogous to Section 34 CPC; pre-reference interest cannot be awarded unless specifically provided for.

Judgment Excerpts

The first item of Office Memorandum referring the dispute to arbitration relates to rate for extra work of earth work beyond lip cutting in the reach kms. 189.50 to Kms. 190.70. In view of the fact that this dispute was expressly referred to arbitration, we fail to see how it can be said that the decision on this dispute by the arbitrator is beyond the scope of the reference. As is held by the Constitution Bench in the case of G.C. Roy (supra), the power of the arbitrator to grant interest pendente lite is based on principles analogous to Section 34 of the Civil Procedure Code.

Procedural History

Disputes arose from contract dated 17.2.1989; Office Memorandum dated 4.10.1992 referred disputes to sole arbitrator; arbitrator gave award dated 23.5.1994; District Judge granted decree in terms of award; High Court partly allowed objections on extra work claim and interest; cross-appeals to Supreme Court.

Acts & Sections

  • Indian Arbitration Act, 1940: Sections not specified
  • Code of Civil Procedure, 1908: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Tribunals NCLAT Dismisses Appeals Challenging Admission of Section 7 Application by Allottees Against Corporate Debtor. The Tribunal upheld the NCLT order allowing impleadment of allottees and admitting the insolvency petition under Section 7 of the Insolvency...
Related Judgement
High Court High Court of Bombay Hears Writ Petition Challenging Maharashtra Revenue Tribunal's Order on Tenancy Fixation. Tenancy Dispute Involving Mahar Watan Lands and Deemed Purchaser Status under Section 32-G of Bombay Tenancy and Agricultural Lands Act, 19...