Case Note & Summary
The appeal arises from a dispute between Konkan Railway Corporation Limited (appellant) and Chenab Bridge Project Undertaking (respondent) concerning the construction of a bridge at KM 50/800 on the Katra-Laole section of the Udhampur-Srinagar-Baramulla rail link, said to be the highest railway bridge in the world. The respondent's tender was accepted, and a contract was executed on 24.11.2004. Disputes arose, and a Standing Arbitral Tribunal was constituted on 28.02.2012. The respondent raised 35 claims, clubbed into twelve disputes. The Arbitral Tribunal, by award dated 15.11.2014, considered three disputes (Dispute I relating to Claim 9, Dispute III relating to Claims 12, 22, 28, and Dispute IV relating to Claims 13, 23, 29) and rejected all claims. The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before the Single Judge of the Bombay High Court, who confirmed the award and dismissed the challenge. The respondent then appealed under Section 37, and the Division Bench partly allowed the appeal, setting aside the concurrent findings and allowing certain claims. The appellant challenged the Division Bench's order before the Supreme Court. The Supreme Court examined whether the Division Bench exceeded its jurisdiction under Section 37 by interfering with concurrent findings without establishing patent illegality or perversity. The Court held that the Division Bench's order was unsustainable as it reappreciated evidence and substituted its own view, which is impermissible under Section 37. The Supreme Court set aside the Division Bench's order and restored the award of the Arbitral Tribunal and the order of the Single Judge.
Headnote
A) Arbitration Law - Section 37 Appeal - Scope of Interference - The Division Bench under Section 37 of the Arbitration and Conciliation Act, 1996 cannot reappreciate evidence or substitute its own view on merits when the Arbitral Tribunal's findings are plausible and not perverse. The court held that the Division Bench erred in setting aside concurrent findings of the Arbitral Tribunal and Single Judge without establishing patent illegality or perversity (Paras 1-4).
Issue of Consideration
Whether the Division Bench of the High Court exceeded its jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 by interfering with concurrent findings of the Arbitral Tribunal and the Single Judge on the ground of patent illegality.
Final Decision
The Supreme Court allowed the appeal, set aside the order of the Division Bench of the Bombay High Court, and restored the award of the Arbitral Tribunal dated 15.11.2014 and the order of the Single Judge under Section 34.
Law Points
- Scope of Section 37 appeal
- Interference with concurrent findings
- Patent illegality
- Public policy ground under Section 34
- Reappreciation of evidence in arbitration




