Case Note & Summary
The dispute originated from a works contract for drainage work in an industrial area, awarded by the Bihar Industrial Area Development Authority to the respondent contractor. An agreement was executed on 15 December 2007. The first appellant terminated the agreement on 8 June 2010, forfeiting the respondent's security deposit and earnest money, and blacklisting the respondent. The respondent filed a reference to the Bihar Public Works Contract Disputes Arbitration Tribunal on 21 March 2013, challenging the termination and seeking refunds. The Tribunal awarded refunds of earnest money, security deposit, deducted penalties, and provisional deductions, totaling specific sums, with simple interest at 10% per annum from specified dates. The appellants filed a revision petition before the High Court under Section 13 of the Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008, which was dismissed. The core legal issues were whether the reference was barred by the one-year limitation period under Section 9(1) of the 2008 Act, and whether the forfeiture and interest award were justified. The appellants argued that Section 9(1) prescribed a one-year limitation, making the reference time-barred, and that Section 5 of the Limitation Act, 1963 did not apply due to Section 29(2), citing precedents like Hukumdev Narayan Yadav v. Lalit Narayan Mishra. They also contested the forfeiture and interest. The respondent contended that Article 137 of the Limitation Act, 1963 applied, providing a three-year period, and that Section 18 of the 2008 Act allowed the Tribunal to extend limitation. The court analyzed Sections 8, 9, 13, and 18 of the 2008 Act, noting that it is a special law but Article 137 serves as a residuary provision for applications not specifically provided for. The court held that the reference was not barred by limitation as Article 137 applied, and the Tribunal had the power under Section 18 to admit references after the limitation period for sufficient cause. The court upheld the Tribunal's findings on forfeiture, as there was no contractual clause permitting it, and did not interfere with the interest award. The revision petition was dismissed, affirming the Tribunal's award.
Headnote
A) Arbitration Law - Limitation Period - Special Statute vs. Limitation Act, 1963 - Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008, Section 9(1) and Limitation Act, 1963, Article 137 - Dispute arose from termination of works contract on 8 June 2010, reference filed on 21 March 2013, appellants contended one-year limitation under Section 9(1) barred reference - Court examined Section 29(2) of Limitation Act, 1963 and held that the 2008 Act is a special law prescribing a different period, but Article 137 applies as residuary article for applications not otherwise provided for - Held that reference was not barred by limitation as Article 137's three-year period applied (Paras 2-5, 8-10). B) Arbitration Law - Extension of Limitation - Tribunal's Discretionary Power - Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008, Section 18 - Respondent argued Tribunal had power to extend limitation under Section 18 - Court noted Section 18 allows Tribunal to admit reference after limitation period if sufficient cause shown - This supported applicability of Article 137 and Tribunal's jurisdiction to entertain belated reference (Paras 6-7, 9). C) Contract Law - Forfeiture of Security Deposit - Absence of Contractual Clause - Works Contract Agreement - Arbitration Tribunal found no clause in agreement providing for forfeiture of earnest money and security deposit - Tribunal held forfeiture unjustified and ordered refund - Court upheld this finding as based on contractual terms (Paras 3, 6-7). D) Arbitration Law - Award of Interest - Tribunal's Discretion - Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008 - Tribunal awarded simple interest at 10% per annum on refunded amounts - Appellants challenged interest rate as illegal - Court considered submissions but did not overturn Tribunal's discretionary award, implying it was within Tribunal's powers (Paras 3-4, 6-7).
Issue of Consideration
Whether the reference to the Arbitration Tribunal under the Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008 was barred by limitation, and whether the forfeiture of earnest money and security deposit was justified.
Final Decision
The Supreme Court dismissed the revision petition, upholding the Arbitration Tribunal's award. Held that the reference was not barred by limitation as Article 137 of the Limitation Act, 1963 applied, and the Tribunal had power under Section 18 of the 2008 Act to extend the limitation period. The forfeiture of earnest money and security deposit was unjustified due to absence of contractual clause, and the interest award was within Tribunal's discretion.
Law Points
- Limitation period under special statute
- Applicability of Article 137 of Limitation Act
- 1963
- Power of tribunal to extend limitation
- Forfeiture of security deposit and earnest money
- Award of interest





