Case Note & Summary
The Supreme Court heard two appeals arising from a Delhi High Court order concerning land acquisition proceedings initiated in 1989-1992. The respondent had filed a writ petition in 2015 claiming that the acquisition had lapsed under Section 24(2) of the 2013 Act because possession had not been taken and compensation had not been paid. The High Court, relying on the Pune Municipal Corporation judgment, allowed the writ petition and declared the acquisition lapsed, while keeping open the question of title to the land. The appellants argued before the Supreme Court that the Constitution Bench judgment in Indore Development Authority had overruled Pune Municipal Corporation and established that for acquisition to lapse under Section 24(2), both conditions—non-taking of possession AND non-payment of compensation—must be satisfied. The Court examined the facts and found that possession of the land had been taken after the award and handed over to the Forest Department. Although compensation had not been paid, this was due to a title dispute as the land was recorded in the name of Gaon Sabha. Applying the Indore Development Authority ruling, the Supreme Court held that since possession had been taken, the acquisition had not lapsed under Section 24(2). The Court allowed the appeals, set aside the High Court order, and dismissed the writ petition.
Headnote
A) Land Acquisition Law - Lapse of Acquisition Proceedings - Section 24(2) Interpretation - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - The Supreme Court examined whether acquisition proceedings had lapsed under Section 24(2) where possession was taken but compensation was not paid due to title dispute. The Court applied the Constitution Bench ruling in Indore Development Authority which held that lapse requires both non-taking of possession AND non-payment of compensation. Held that since possession was admittedly taken, there was no lapse under Section 24(2) (Paras 9, 12, 15). B) Land Acquisition Law - Precedent Overruling - Binding Effect of Constitution Bench Judgment - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - The Supreme Court considered the effect of the Constitution Bench judgment in Indore Development Authority which overruled Pune Municipal Corporation. The High Court had relied on Pune Municipal Corporation to hold acquisition lapsed. The Supreme Court held that the Constitution Bench ruling was binding and required setting aside of the High Court order (Paras 9, 11, 13). C) Land Acquisition Law - Compensation Payment - Title Dispute - Land Acquisition Act, 1894, Section 31 - The Court noted that compensation could not be paid to the predecessor-in-interest due to dispute regarding title of the land, which was recorded in the name of Gaon Sabha. The High Court had kept the question of title open. The Supreme Court observed that non-payment due to title dispute did not result in lapse when possession had been taken (Paras 8, 9, 14).
Issue of Consideration
Whether the land acquisition proceedings had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, in light of the Constitution Bench judgment in Indore Development Authority vs. Manoharlal and Others
Final Decision
The appeals are allowed. The impugned order passed by the High Court is set aside. The writ petition filed by the respondents in the High Court stands dismissed.
Law Points
- Interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition
- Rehabilitation and Resettlement Act
- 2013
- deemed lapse of land acquisition proceedings
- possession and compensation requirements
- overruling of Pune Municipal Corporation judgment
- application of Indore Development Authority Constitution Bench ruling





