Case Note & Summary
The dispute arose between the State of Maharashtra and a power company over the levy of irrigation restoration charges for diverting water from agricultural to industrial use. The State had issued a circular in 2004 prescribing Rs.50,000 per hectare, which was increased to Rs.1,00,000 per hectare by a Government Resolution in 2009. The power company, intending to set up a thermal power plant, received in-principle approval in 2008 and final approval in 2008, with the State demanding Rs.1,00,000 per hectare. After negotiations, the parties entered into a water supply agreement on 22.05.2012, stipulating Rs.1,00,000 per hectare, and the company issued an undertaking to pay this amount in instalments. Subsequently, the company challenged the charges, leading to writ petitions. The High Court initially dismissed the challenge in 2012, but in a later writ petition, it reduced the charges to Rs.50,000 per hectare, ruling that the rate prevailing at the time of in-principle approval should apply. The State appealed to the Supreme Court. The core legal issue was whether a party could question the consideration after signing a contract. The State argued that the contract was sacrosanct and the company was estopped from challenging it, while the company contended that the rate should be based on the circular at the time of approval and that similarly placed companies had received relief. The Supreme Court analyzed the facts, noting that the company had signed the agreement and issued an undertaking accepting the higher charge. The court held that the company was estopped from disputing the consideration, emphasizing the principle of estoppel and the binding nature of contractual obligations. The court set aside the High Court's order, restoring the contractual rate of Rs.1,00,000 per hectare, and dismissed the company's challenge, affirming that post-contract challenges to consideration are not permissible when the party has expressly agreed to it.
Headnote
A) Contract Law - Estoppel - Post-Contract Challenge to Consideration - Indian Contract Act, 1872 - The Supreme Court considered whether a party could question consideration after signing a contract. The court held that Respondent No.1 was estopped from challenging the irrigation restoration charges of Rs.1,00,000 per hectare as it had signed the agreement and issued an undertaking accepting this amount. The court emphasized that the contract reflected consensus ad idem and the party could not later dispute the agreed consideration. (Paras 1-17) B) Administrative Law - Government Circulars - Prospective Application - Government Resolution dated 01.03.2009 - The court addressed the applicability of a government circular increasing irrigation restoration charges. It was argued that the circular should apply prospectively and not to ongoing contracts. The court, in its analysis, considered this issue but ultimately based its decision on estoppel and contractual obligations, implying that the circular's application was subsumed by the contractual agreement. (Paras 8-16)
Issue of Consideration
Whether a party to a contract is entitled to question the amount of consideration after signing the contract.
Final Decision
The Supreme Court set aside the impugned order of the High Court, holding that Respondent No.1 is estopped from questioning the irrigation restoration charges after signing the contract and issuing an undertaking. The court restored the contractual rate of Rs.1,00,000 per hectare.
Law Points
- Estoppel
- Contractual Obligation
- Consideration
- Government Resolution
- Judicial Review





