Supreme Court Allows Appeal in Arbitration Execution Matter — Post-Award Interest Calculation Must Follow Hyder Consulting Principle. Court holds that post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 is payable on the entire sum awarded including pre-award interest, overruling S.L. Arora.

In Favour of Accused
  • 603
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a contract awarded by the North Delhi Municipal Corporation (appellant) to M/s. S.A. Builders Ltd. (respondent) in 1983 for construction of approaches to a flyover. The work could not be completed due to non-availability of site and was closed in March 1990. The respondent's final bill was not paid, leading to arbitration under the Arbitration Act, 1940, but proceedings were conducted under the Arbitration and Conciliation Act, 1996. The sole arbitrator passed an award on 16.12.1997, awarding Rs. 1,70,70,720.80 with simple interest at 18% per annum from 01.04.1990 till payment, later corrected to Rs. 1,70,40,720.80. The appellant's challenge under Section 34 was dismissed on 08.01.2002, and the appeal under Section 37 was dismissed on 14.03.2002. The SLP against that was dismissed on 03.02.2010. In execution proceedings, the Single Judge framed an issue on whether post-award interest under Section 31(7) should be calculated on the principal sum or on the principal plus pre-award interest. The matter was referred to the Division Bench, which permitted the respondent to seek clarification from the arbitrator. The arbitrator clarified on 15.03.2005 that post-award interest is payable on the awarded sum including pre-award interest. The appellant challenged this clarification, and the Single Judge set it aside on 19.02.2008, holding the arbitrator functus officio. The respondent appealed, but the Division Bench on 23.02.2012 dismissed the appeal relying on State of Haryana v. S.L. Arora, which held that compound interest is not payable. The respondent appealed to the Supreme Court, which tagged the matter with Hyder Consulting (UK) Ltd. v. Governor, State of Orissa. On 12.03.2015, the Supreme Court overruled S.L. Arora and held that post-award interest is payable on the entire sum awarded including pre-award interest. The matter was remanded to the High Court for computation. The Division Bench on 01.07.2019 set aside the Single Judge's order on calculations and directed the Single Judge to decide the quantum. The appellant then appealed to the Supreme Court. The Supreme Court dismissed the appeal, holding that the Division Bench correctly followed the law laid down in Hyder Consulting and that the award had attained finality. The Court directed the executing court to compute the amount payable in accordance with Hyder Consulting.

Headnote

A) Arbitration Law - Post-Award Interest - Section 31(7)(b) Arbitration and Conciliation Act, 1996 - Calculation of Interest - The issue was whether post-award interest under Section 31(7)(b) is payable on the principal sum only or on the entire sum awarded including pre-award interest. The Supreme Court held that the sum directed to be paid by the award includes both principal and interest, and post-award interest is payable on that entire sum, following Hyder Consulting (UK) Ltd. v. Governor, State of Orissa, (2015) 2 SCC 189, and overruling State of Haryana v. S.L. Arora, (2010) 3 SCC 690. (Paras 20-22)

B) Arbitration Law - Arbitrator's Clarification - Section 31(7) and Section 32 Arbitration and Conciliation Act, 1996 - Functus Officio - The Arbitrator issued a clarification on 15.03.2005 regarding the nature of interest awarded, after being permitted by the High Court. The Single Judge set aside the clarification holding the Arbitrator functus officio. The Supreme Court did not disturb that part as the appeal was confined to the interest calculation issue. (Paras 14-16)

C) Arbitration Law - Execution of Award - Section 36 Arbitration and Conciliation Act, 1996 - Finality of Award - The award dated 16.12.1997 had attained finality after dismissal of the appellant's challenge under Section 34 and subsequent appeals. The only issue left was computation of interest in execution. (Paras 8-10, 20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 is to be calculated on the principal sum adjudged or on the principal sum plus interest accrued from the date of cause of action to the date of award?

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, holding that the Division Bench correctly followed the law laid down in Hyder Consulting (UK) Ltd. v. Governor, State of Orissa. The Court directed the executing court to compute the amount payable to the respondent in accordance with the principles stated in Hyder Consulting, i.e., post-award interest under Section 31(7)(b) is payable on the entire sum awarded including principal and pre-award interest.

Law Points

  • Post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act
  • 1996 is payable on the entire sum awarded including principal and pre-award interest
  • Arbitrator's clarification on interest is valid if within scope of reference
  • functus officio principle does not bar clarification sought with court permission
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (SC) (12) 174

Civil Appeal No. 1878 of 2024 (@ Special Leave Petition (Civil) No. 3421 of 2024)

2024-12-13

Ujjal Bhuyan

2024 INSC 988

North Delhi Municipal Corporation

M/s. S.A. Builders Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against order of Division Bench of Delhi High Court in execution proceedings of an arbitral award, concerning calculation of post-award interest.

Remedy Sought

Appellant (North Delhi Municipal Corporation) sought to set aside the Division Bench order dated 01.07.2019 which directed the Single Judge to decide the quantum of amount payable to the respondent in accordance with Hyder Consulting.

Filing Reason

Appellant challenged the Division Bench order that required recalculation of post-award interest on the entire sum awarded including pre-award interest, contrary to appellant's contention that interest should be on principal only.

Previous Decisions

Arbitral award dated 16.12.1997; Single Judge order dated 19.02.2008 setting aside arbitrator's clarification; Division Bench order dated 23.02.2012 dismissing appeal relying on S.L. Arora; Supreme Court order dated 12.03.2015 overruling S.L. Arora and remanding for computation; Division Bench order dated 01.07.2019 setting aside Single Judge's calculations and directing fresh determination.

Issues

Whether post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 is to be calculated on the principal sum adjudged or on the principal sum plus interest accrued from the date of cause of action to the date of award? Whether the Division Bench correctly applied the law laid down in Hyder Consulting (UK) Ltd. v. Governor, State of Orissa?

Submissions/Arguments

Appellant argued that the Division Bench erred in setting aside the Single Judge's calculations and that the award had not attained finality on the interest component. Respondent contended that the award had attained finality and the Division Bench correctly followed the Supreme Court's direction to compute interest as per Hyder Consulting.

Ratio Decidendi

Post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 is payable on the entire sum awarded, which includes the principal amount adjudged and the interest thereon up to the date of the award. The decision in State of Haryana v. S.L. Arora, which held otherwise, was overruled by Hyder Consulting (UK) Ltd. v. Governor, State of Orissa.

Judgment Excerpts

This Court referred to its earlier decision in M/s. Hyder Consulting (UK) Ltd. (supra) and held that the decision in S.L. Arora (supra) does not lay down the correct law. In M/s. Hyder Consulting (UK) Ltd. (supra), it has been held that the sum directed to be paid by the award would mean a sum inclusive of the principal amount adjudged and the interest thereon. Therefore, the post-award interest that may be awarded would be on the principal amount as well as on the interest on the principal amount which together would constitute the sum awarded.

Procedural History

Arbitral award passed on 16.12.1997; appellant's challenge under Section 34 dismissed on 08.01.2002; appeal under Section 37 dismissed on 14.03.2002; SLP dismissed on 03.02.2010. In execution, Single Judge framed issue on 26.08.2004; Division Bench permitted clarification on 03.01.2005; arbitrator clarified on 15.03.2005; Single Judge set aside clarification on 19.02.2008; Division Bench dismissed appeal on 23.02.2012 relying on S.L. Arora; Supreme Court on 12.03.2015 overruled S.L. Arora and remanded; Division Bench on 01.07.2019 set aside Single Judge's calculations and directed fresh determination; appellant filed SLP which was converted to Civil Appeal No. 1878 of 2024; Supreme Court dismissed appeal on 13.12.2024.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7), Section 31(7)(a), Section 31(7)(b), Section 32, Section 34, Section 36, Section 37
  • Arbitration Act, 1940: Section 20
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal in Arbitration Execution Matter — Post-Award Interest Calculation Must Follow Hyder Consulting Principle. Court holds that post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 is payab...
Related Judgement
High Court Bombay High Court Allows Revision Against Dismissal of Land Acquisition Reference for Want of Evidence - Principles of Natural Justice Violated. Court sets aside order dismissing reference due to advocate's absence and remands for fresh hearing on me...