Supreme Court Upholds Award of Contract to Successful Bidder in Tender Dispute, Setting Aside High Court's Interference. Judicial Review in Tender Matters is Limited to Examining Arbitrariness and Procedural Fairness, Not Re-evaluating Merits, Especially After Contract Execution Under the Tender Terms.

The dispute arose from a tender floated by Respondent for operation and maintenance of a gas-based power plant. The tender used a Quality and Cost Bas...

© Image Copyrights Juris Services & Technology

Supreme Court Allows Appeal in Part and Refers Question of Law to Larger Bench in MSMED Act Dispute. Registration Under Section 8 of MSMED Act, 2006 Not a Precondition for Reference Under Section 18, but Issue Requires Authoritative Determination by Three-Judge Bench.

The Supreme Court of India heard an appeal by NBCC (India) Ltd. against the State of West Bengal and others, concerning a dispute with M/s Saket Infra...

© Image Copyrights Juris Services & Technology

Supreme Court Upholds Farmers' Insurance Claim in Cold Storage Fire — Insurer Liable Despite No Privity of Contract. Farmers are Consumers Under Consumer Protection Act, 1986, and Insurance Company Must Pay for Loss of Stored Agricultural Produce.

The case involves multiple appeals arising from a common order of the National Consumer Disputes Redressal Commission regarding a fire that occurred o...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Petition Challenging Disqualification in Tender for Pumping Machinery at MIDC Water Treatment Plant. Court holds that disqualification based on alleged non-submission of required documents was arbitrary and contrary to tender conditions.

The petitioner, M/s Yogiraj Powertech Pvt. Ltd., participated in a tender process issued by the Maharashtra Industrial Development Corporation (MIDC) ...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Insurance Company's Challenge to Arbitral Award on Fire Insurance Claim. Reinstatement Value Claim Allowed Despite Delay in Replacement; Acceptance Under Protest Not Full Settlement; Interest at 18% Upheld.

The New India Assurance Company Limited (Petitioner) issued two fire and special perils insurance policies to M/s. Alan Scott Industries Limited (Resp...

© Image Copyrights Juris Services & Technology

Bombay High Court Upholds Labour Court's Finding that Senior Engineer and Engineering Assistant are Not Workmen under Industrial Disputes Act, 1947. Petitioners' Complaints under MRTU & PULP Act Dismissed as Not Maintainable Due to Lack of Workman Status.

The Bombay High Court dismissed two writ petitions challenging the Labour Court's orders dated 23rd July 1999, which held that the Petitioners were no...