NATIONAL COMPANY LAW APPELLATE TRIBUNAL Dismisses Application for Payment Confirmation Due to Conditional Form Submission. Tribunal Directed Operational Creditor to Submit Unconditional Form FA with Guarantee as per Previous Order.

Tribunals: National Company Law Appellate Tribunal Bench: NEW DELHI
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The matter involved an application filed by Mohd. Zaheer, the ex-promoter of AL-Dua Food Processing Pvt. Ltd, against Ashu Agencies and another party. The application was in response to a previous judgment of the Tribunal dated 12.03.2026, concerning the payment of Rs. 2,48,46,299 by the Operational Creditor. The Tribunal noted that while the payment had been made within the stipulated time, the required Form FA had not been submitted. The Operational Creditor's counsel claimed that Form FA had been sent, but the IRP's counsel pointed out that it was conditional and lacked the necessary guarantee. The Tribunal directed the Operational Creditor to submit a fresh unconditional Form FA along with the guarantee within three working days. Additionally, it was noted that if any fee of the IRP was not paid, the Appellant would bear that fee. The application was ultimately disposed of with these directions.

Headnote

A) Company Law - Operational Creditor Compliance - Submission of Form FA - Insolvency and Bankruptcy Code, 2016 - The Tribunal addressed the compliance of the Operational Creditor with the payment and Form FA submission as per its previous order. The Operational Creditor was directed to submit an unconditional Form FA along with a guarantee within three working days, and the IRP was permitted to file an application thereafter. Held that the application was disposed of with these directions (Paras Not mentioned).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Operational Creditor has complied with the Tribunal's order regarding payment and Form FA submission.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Tribunal directed the Operational Creditor to submit a fresh unconditional Form FA along with a guarantee within three working days and allowed the IRP to file an application thereafter. The Appellant agreed to bear the IRP's fee if not paid.

Law Points

  • Operational Creditor compliance
  • Form FA submission
  • IRP fee responsibility
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (NCLAT) (05) 159

I.A. No. 2923 of 2026 in Comp. App. (AT) (Ins) No. 1526 of 2025

2026-05-08

Justice Ashok Bhushan, Mr. Barun Mitra

Mr. Abhijeet Sinha, Shivam Shukla, Heena Kochar, Syed Saud, Anjali Upadhyay, Mr. Abhinav Prakash, Mr. Rishi Singhal, Pawan Kr. Goyal

Mohd. Zaheer

Ashu Agencies & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application regarding compliance with Tribunal's payment order

Remedy Sought

Confirmation of payment and submission of Form FA

Filing Reason

Non-submission of required Form FA by the Operational Creditor

Previous Decisions

Tribunal's order dated 12.03.2026 regarding payment

Issues

Compliance with Tribunal's order regarding payment and Form FA submission

Submissions/Arguments

Operational Creditor claimed Form FA was sent IRP counsel argued Form FA was conditional and lacked guarantee

Ratio Decidendi

The Tribunal emphasized the necessity of compliance with procedural requirements for the submission of Form FA and the implications of conditional submissions.

Judgment Excerpts

This application has been filed claiming that in pursuance of the judgment of this Tribunal dated 12.03.2026, the Operational Creditor has made the payment of amount of Rs. 2,48,46,299/- within time as allowed by the Court. Ld. Counsel for the Operational Creditor submits that he shall submit a fresh unconditional Form FA alongwith guarantee within three working days.

Procedural History

Application filed on 08.05.2026 regarding compliance with previous Tribunal order.

Acts & Sections

  • Insolvency and Bankruptcy Code:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses State's Application to Modify Final Judgment in Bhama Askhed Project Land Acquisition Case. No Ground Made Out for Extension of Time for Issuance of Notice Under Section 16(2)(a) of Maharashtra Resettlement of Project Affe...
Related Judgement
Supreme Court Supreme Court Allows Appeal in Property Dispute Over Compromise Decree Validity — Oral Statements Not Sufficient to Transfer Ownership Under Order XXIII Rule 3 CPC. Sale Deed Executed During Pendency of Appeal Remains Valid and Not Affected by Subs...