Case Note & Summary
The State of Maharashtra filed a Civil Application seeking modification of a final judgment dated 17 July 2012 passed by a Division Bench of the Bombay High Court in a batch of writ petitions concerning the acquisition of agricultural lands for the Bhama Askhed Project. The Division Bench had directed the Collector, Pune, to issue notices under Section 16(2)(a) of the Maharashtra Resettlement of Project Affected Persons Act, 1999 to the petitioners (project affected persons) within one month, allowing them to communicate willingness to accept alternate land within 45 days and deposit 65% of compensation. The State sought modification on the ground that some affected persons had given up their right to claim alternate land and that 315 statements to that effect were found in the records. The State also sought an extension of time for issuing the notices. The court, consisting of Dr. D.Y. Chandrachud and Mrs. Mridula Bhatkar, JJ., dismissed the application, holding that a final judgment cannot be modified as the court becomes functus officio. The court further found no sufficient cause for extension of time, noting that the State had ample opportunity to comply with the order and the application was filed after the deadline. The court observed that the State's grounds did not justify modification or extension, and the application was dismissed.
Headnote
A) Civil Procedure - Modification of Final Judgment - Final Judgment Cannot Be Modified - The court held that a final judgment cannot be modified after it has been pronounced, as the court becomes functus officio. The application for modification was dismissed as the judgment dated 17 July 2012 was a final order disposing of the writ petitions. (Paras 5-6) B) Land Acquisition - Project Affected Persons - Extension of Time for Compliance - Section 16(2)(a) of Maharashtra Resettlement of Project Affected Persons Act, 1999 - The State sought extension of time for issuing notices under Section 16(2)(a) on the ground that some affected persons had given up their right to claim alternate land. The court found no sufficient cause for extension as the State had ample time to comply and the application was filed after the deadline. (Paras 3-6) C) Land Acquisition - Project Affected Persons - Right to Alternate Land - Section 16(2)(a) of Maharashtra Resettlement of Project Affected Persons Act, 1999 - The Division Bench had directed the Collector to issue notices under Section 16(2)(a) within one month. The State's failure to comply and subsequent application for modification was rejected. (Paras 2-6)
Issue of Consideration
Whether the State's application for modification of the final judgment and extension of time for issuance of notice under Section 16(2)(a) of the Maharashtra Resettlement of Project Affected Persons Act, 1999 should be allowed.
Final Decision
The Civil Application is dismissed. The court held that the judgment dated 17 July 2012 was a final order and cannot be modified. No sufficient cause was shown for extension of time.
Law Points
- Modification of final judgment not permissible
- extension of time for compliance not warranted without sufficient cause
- Section 16(2)(a) of Maharashtra Resettlement of Project Affected Persons Act
- 1999




