National Company Law Appellate Tribunal Allows Financial Creditor's Appeal for PIRP Extension Due to Required Approvals. Tribunal Found Justification for Extension as Repayment Plan Was Approved in Principle.

Tribunals: National Company Law Appellate Tribunal Bench: NEW DELHI
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from the rejection of the Indian Bank's request for an extension of the Personal Insolvency Resolution Process (PIRP) period concerning the guarantors, Mrs. Sneha Dharmendra Shah and Dharmendra Shah. The Indian Bank filed two appeals against the orders of the National Company Law Tribunal (NCLT) dated 08.07.2026, which denied the extension requests. The PIRP was initiated under Section 95 of the Code of Personal Insolvency, 2019, on 20.02.2026, and a public announcement was made on 27.02.2026, with claims submitted by 19.03.2026. The first meeting of creditors occurred on 02.04.2026, and after several meetings, a repayment plan of Rs. 3,27,50,000 was proposed by the guarantors. The fifth meeting on 26.06.2026 led to a resolution to extend the PIRP period by 60 days, but the NCLT ultimately rejected the applications for extension. The Appellant argued that the rejection was unjustified as the repayment plan had been approved in principle and only required further approvals from the financial creditor's authority. The Respondents contended that they were willing to settle and had made a repayment offer. The Tribunal, after reviewing the circumstances, found that the NCLT should have granted a reasonable extension for the completion of the PIRP process, given the approval status of the repayment plan. Consequently, the Tribunal allowed the appeals, set aside the NCLT's orders, and extended the PIRP period by 45 days to facilitate the completion of the process. No costs were awarded, and any pending applications were disposed of.

Headnote

A) Insolvency Law - Personal Insolvency Resolution Process - Extension of Time - Code of Personal Insolvency, 2019, Section 95 - The Appellant sought an extension of the PIRP period after the repayment plan was in principle approved by the financial creditor but required further approvals. The Tribunal found merit in the appeal and allowed the extension for 45 days to complete the PIRP process (Paras 14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the National Company Law Tribunal erred in rejecting the request for extension of the Personal Insolvency Resolution Process (PIRP) period.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Tribunal allowed the appeals, set aside the NCLT's orders, and extended the PIRP period by 45 days for completion of the process.

Law Points

  • Personal Insolvency Resolution Process
  • extension of time
  • approval of repayment plan
  • financial creditor's authority
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (NCLAT) (08) 28

Comp. App. (AT) (Ins) No. 1454 of 2026 and Comp. App. (AT) (Ins) No. 1457 of 2026

2026-08-19

Mohd. Faiz Alam Khan, Naresh Salecha

Mr. Ritesh D. Patadia, Mr. Sumit Parikh

Indian Bank

Mrs. Sneha Dharmendra Shah, Dharmendra Shah

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against the rejection of extension requests for Personal Insolvency Resolution Process.

Remedy Sought

Indian Bank sought an extension of the PIRP period.

Filing Reason

The NCLT rejected the request for extension of time for the PIRP process.

Previous Decisions

The NCLT had denied the extension requests on 08.07.2026.

Issues

Whether the NCLT erred in rejecting the extension request for the PIRP period.

Submissions/Arguments

The Appellant argued that the repayment plan was approved in principle and required further approvals. The Respondents contended that they were willing to settle and had made a repayment offer.

Ratio Decidendi

The Tribunal emphasized the necessity of granting reasonable time for the completion of the PIRP process when the repayment plan had been approved in principle, highlighting the importance of procedural fairness and the need for appropriate authority approvals.

Judgment Excerpts

The PIRP period with regard to the aforesaid PIRP’s proceedings is extended for further 45 days, from today. The purpose of the PIRP is for repayment of loan to the financial creditor.

Procedural History

The Appellant filed two appeals against the NCLT's orders rejecting the extension requests for the PIRP period.

Acts & Sections

  • Code of Personal Insolvency: 95
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal Regarding Resignation Acceptance in Banking Service Regulations — Employee's Right to Withdraw Resignation Affirmed.
Related Judgement
High Court Bombay High Court Quashes Blacklisting Order Against Contractor in Pipeline Contract Dispute — Mere Breach of Contract Without Deviant Conduct Insufficient for Blacklisting. Clause 4.1.1(g)-(h) of BPCL's Holiday Listing Policy Struck Down as Arbitr...