High Court Upholds Plaintiff's Claims for Extra Work in Construction Contract Dispute — Validity of Claims Affirmed.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The judgment addressed two appeals concerning a construction contract dispute between Maharashtra State Police Housing and Welfare Corporation Ltd. and Ajay Deep Construction Pvt. Ltd. The appeals challenged a judgment from June 28, 2021, which decreed the Plaintiff's claims for extra work and interest on delayed payments. The Defendant had invited tenders for constructing quarters for policemen, and the Plaintiff's bid was accepted, leading to a work order issued in November 1996. The Plaintiff completed the work by December 1999 but faced delays in payment for various running account bills. The Plaintiff claimed additional payments for extra work, including depth of foundation and excess quantities of materials, which the Defendant contested. The court analyzed the contractual obligations, particularly clauses regarding extra work and the authority of the project management consultant. It found that the Defendant had waived certain conditions regarding the claims for extra work and that the Plaintiff had executed the work as per the contract. The court upheld the Plaintiff's claims for payment and interest, concluding that the Defendant's objections were unfounded and that the Plaintiff had adequately demonstrated its entitlement to the decreed amounts. The judgment reinforced the principle that contractual stipulations regarding claims should not act as a bar to legitimate claims for work actually performed.

Headnote

A) Contract Law - Extra Work Claims - Entitlement to Payment - Contractual obligations, waiver of conditions - The court held that the Plaintiff was entitled to payment for extra work executed beyond the contractual specifications, as the Defendant had waived the requirement for prior written approval for such work. The evidence supported that the work was executed as per the contract terms and the Defendant's project management consultant had recommended payment (Paras 54-59).

B) Contract Law - Interest on Delayed Payments - Entitlement to Interest - The court found that the Plaintiff was entitled to interest on delayed payments as the Defendant had failed to adhere to the stipulated timelines for payment, thus affirming the Plaintiff's claims for interest (Paras 1-3).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Plaintiff was entitled to payment for extra work and interest on delayed payments under the construction contract.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court upheld the Plaintiff's claims for payment of Rs. 9,32,544 for extra work and Rs. 2,82,484 for additional items, along with interest on delayed payments as decreed by the Learned Single Judge.

Law Points

  • Contractual obligations
  • waiver of conditions
  • authority of project management consultant
  • extra work claims
  • interest on delayed payments
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (10) 24

Appeal No. 9 of 2022 and Appeal No. 29 of 2022

2026-10-19

B. P. Colabawalla, P. P. Pooniwalla

Mr. Narayan Sahu, Mr. Sagar Kothari, Mr. Sahil Narvekar, Mr. Hasmit Trivedi, Mr. Indra Kumar Lahoti, Ms. Niharika Ahirekar

Maharashtra State Police Housing and Welfare Corporation Ltd.

Ajay Deep Construction Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Dispute over payment for extra work and interest on delayed payments under a construction contract.

Remedy Sought

Plaintiff sought payment for extra work and interest on delayed payments.

Filing Reason

The Plaintiff filed the suit due to non-payment for extra work and delayed payments.

Previous Decisions

The Learned Single Judge had decreed the Plaintiff's claims in the earlier judgment.

Issues

Entitlement to payment for extra work executed beyond contractual specifications Entitlement to interest on delayed payments

Submissions/Arguments

Defendant argued that the Plaintiff did not comply with contractual terms for claiming extra work. Plaintiff contended that the Defendant waived the requirement for prior approval for extra work.

Ratio Decidendi

The court affirmed that contractual stipulations regarding claims should not bar legitimate claims for work performed, and that waiver of conditions can occur through conduct.

Judgment Excerpts

The court held that the Plaintiff was entitled to payment for extra work executed beyond the contractual specifications. The evidence supported that the work was executed as per the contract terms and the Defendant's project management consultant had recommended payment.

Procedural History

The Plaintiff filed Suit No. 1418 of 2003 on April 22, 2003. The Defendant filed its Written Statement on January 11, 2008. The Learned Single Judge passed the impugned judgment on June 28, 2021. The Defendant filed Appeal No. 9 of 2022 and the Plaintiff filed Appeal No. 29 of 2022, both admitted on January 9, 2023.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court Quashes Tax Refund Adjustment Order for Violation of Settlement Scheme and Natural Justice. Adjustment of refund for one tax period against demand for another under proviso to Section 50(1) of Maharashtra Value Added Tax Act, 2002 held inv...
Related Judgement
Supreme Court Supreme Court Upholds Employer's Decision in Service Matter Due to Established Misconduct. Misinterpretation of Findings by High Court Led to Erroneous Conclusion on Legality of Removal.