The dispute arose from a judgment by the High Court of Delhi, which declared that the land acquisition proceedings under the Land Acquisition Act, 1894 had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Government of NCT of Delhi appealed this decision. The High Court's ruling was based on its interpretation of the lapse provisions, but it failed to consider that the land acquisition proceedings were pending due to challenges from the landowners, which had reached the Supreme Court. The Supreme Court referenced its earlier decision in Pune Municipal Corporation v. Harakchand Misirimal Solanki and the Constitution Bench ruling in Indore Development Authority v. Manoharlal, clarifying that the lapse of proceedings under Section 24(2) occurs only when there has been inaction for five years or more without possession being taken or compensation being paid. The court emphasized that if possession was not taken due to pending proceedings, the landowners could not claim that the acquisition had lapsed. Ultimately, the Supreme Court quashed the High Court's order, allowing the appeal and stating that the land acquisition proceedings were still valid.
Headnote
A) Land Acquisition - Deemed Lapse of Proceedings - Legal Interpretation of Section 24(2) - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - The court held that the land acquisition proceedings do not lapse under Section 24(2) if possession has not been taken or compensation has not been paid due to the inaction of authorities for five years or more prior to the commencement of the 2013 Act. The court quashed the High Court's order declaring the proceedings lapsed, emphasizing that the landowners cannot claim lapse due to non-taking of possession when the acquisition proceedings were pending (Paras 1-3).
Issue of Consideration
Whether the land acquisition proceedings lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
Final Decision
The Supreme Court quashed the High Court's order declaring the land acquisition proceedings lapsed under Section 24(2) of the 2013 Act, allowing the appeal and stating that the proceedings were valid.
Law Points
- Land acquisition
- deemed lapse
- possession
- compensation
- legal interpretation