High Court Considers Appeal Against Dismissal of Section 34 Objection in Arbitration Dispute Over BOT Tunnel Project. Dispute involved claims for increased project cost, loss of toll, and advertisement revenue under Tripartite Concession Agreement, with Arbitral Tribunal awarding Rs. 198.04 crores plus IRR.

High Court: Rajasthan High Court Bench: Jaipur
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appeal before the High Court of Judicature for Rajasthan, Bench at Jaipur, arose from the dismissal of an objection petition under Section 34 of the Arbitration and Conciliation Act, 1996 by the learned District Judge, Commercial Court, Jaipur, vide order dated 27.01.2025. The appellants, Jaipur Development Authority and Urban Development and Housing Department, Government of Rajasthan, challenged the arbitral award dated 25.06.2023 and corrigendum award dated 31.07.2023. The underlying dispute stemmed from a Tripartite Concession Agreement dated 27.11.2009 executed between the Government of Rajasthan, Jaipur Development Authority, and the respondent concessionaire, Rohan Rajdeep Rajasthan Infra Project Limited, for the construction, operation and maintenance of an alternate route to Ghat Ki Guni through a tunnel in the Jhalana Hills, connecting to NH-11 (Agra Road), Jaipur, on a Build Operate Transfer basis. The project cost as per bid documents was Rs. 150 crores, with a concession period of 13 years 05 months 20 days. The actual commencement date was 15.12.2010, against a proposed commencement date of 01.12.2009, and the actual completion date was 31.01.2013, earlier than the stipulated date of 14.06.2013. The respondent filed a statement of claim on 15.02.2019, seeking Claim No. 1 for increase in project cost of Rs. 175.67 crores, Claim No. 2 for loss of toll of Rs. 188.02 crores, Claim No. 3 for compensation of toll loss due to delay in achieving Commercial Operations Date of Rs. 40.71 crores, and Claim No. 4 for revenue loss on account of denial of right of way for displaying advertisements of Rs. 8.49 crores, along with declaratory reliefs, Internal Rate of Return at 20.33%, and arbitral costs. The Arbitral Tribunal allowed Claim No. 1 in toto, partly allowed Claim No. 2 by awarding Rs. 12.20 crores for leakage of traffic through old GKG road and Rs. 1.68 crores for demonetization while disallowing other sub-claims, disallowed Claim No. 3, and allowed Claim No. 4. The total award was Rs. 198.04 crores, plus IRR at 20.33% per annum up to the date of the award, and post-award interest at 12% per annum if not paid within 90 days. Subsequently, the arbitrator passed a corrigendum award dated 31.07.2023 under Section 33 of the Act, deleting the total cap and making the award without any upper limit by adding IRR on a compounding basis. Execution proceedings were instituted seeking recovery of Rs. 544.43 crores, calculated as Rs. 198.04 crore plus IRR at 20.33% with effect from 31.01.2019, plus additional 12% with effect from 01.08.2023. The executing court directed issuance of a warrant of recovery under Order XXI Rule 30 of the Code of Civil Procedure, 1908, on 09.01.2026, but the High Court stayed the execution proceedings on 22.01.2026. The present appeal challenged the order dismissing the Section 34 objections and the approach of the Commercial Court in refusing interference. The available extracted text contains the introduction, factual background, and details of the claims and award, but does not include the parties' detailed arguments, the court's analysis, or the final decision, as the judgment text is truncated after paragraph 11. Therefore, the final holding cannot be determined from the provided material.

Headnote

A) Arbitration and Conciliation - Appeal under Section 37 - Sections 34 and 37 of Arbitration and Conciliation Act, 1996 - Appeal directed against order dated 27.01.2025 dismissing Section 34 objection challenging arbitral award dated 25.06.2023 and corrigendum dated 31.07.2023 - Arbitral Tribunal allowed Claim No. 1 in toto, partly allowed Claim No. 2, rejected Claim No. 3, and allowed Claim No. 4, awarding Rs. 198.04 crores plus IRR @20.33% and post-award interest @12% - High Court examined scope of interference; final outcome not available in extracted text (Paras 1-8).

B) Arbitration and Conciliation - Corrigendum under Section 33 - Section 33 of Arbitration and Conciliation Act, 1996 - Corrigendum dated 31.07.2023 deleted words amounting to Rs. 198.04 crores and made award without any upper cap by adding IRR @20.33% on compounding basis per annum - This corrigendum was also assailed before Commercial Court and in appeal (Paras 5-6).

C) Civil Procedure - Execution of Arbitral Award - Order XXI Rule 30 of Code of Civil Procedure, 1908 - Executing court directed issuance of warrant of recovery for Rs. 544.43 crore calculated as Rs. 198.04 crore plus IRR @20.33% w.e.f. 31.01.2019 plus additional 12% w.e.f. 01.08.2023 - High Court stayed execution proceedings on 22.01.2026 (Paras 7-8).

D) Contract - Concession Agreement - Tripartite Concession Agreement dated 27.11.2009 - Project for construction, operation and maintenance of alternate route to Ghat Ki Guni through tunnel in Jhalana Hills on Build Operate Transfer basis - Disputes arose over alleged DPR deficiencies, revised alignment, cost escalation, toll loss and advertisement revenue loss - Arbitral Tribunal awarded total Rs. 198.04 crores plus IRR (Paras 2-11).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Commercial Court erred in dismissing the appellants' objections under Section 34 of the Arbitration and Conciliation Act, 1996 against the arbitral award dated 25.06.2023 and corrigendum dated 31.07.2023; and whether the scope of interference under Sections 34 and 37 warranted setting aside of the award.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Arbitration and Conciliation Act 1996 Section 34 scope of interference
  • Arbitration and Conciliation Act 1996 Section 33 correction of clerical errors
  • Code of Civil Procedure 1908 Order XXI Rule 30 execution of arbitral award
  • Arbitral award finality unless grounds under Section 34 established
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (RAJ) (08) 48

D.B. Civil Miscellaneous Appeal No. 1560/2025

2026-08-17

Arun Monga, Sandeep Taneja

Rajendra Prasad, Tanay Goyal, Sheetanshu Sharma, Harshita Thakar, Dhriti Sharma, Sudhir Gupta, Sweta Chauhan, Tarak Ahuja, Ishan Khanna, Aditya Shandilya, Rachit Somani

Jaipur Development Authority and Urban Development And Housing Department (UDH), Government of Rajasthan

Rohan Rajdeep Rajasthan Infra Project Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of Arbitration and Conciliation Act, 1996 against dismissal of Section 34 objection

Remedy Sought

Appellants sought setting aside of arbitral award dated 25.06.2023 and corrigendum dated 31.07.2023 by challenging order dated 27.01.2025 of Commercial Court dismissing Section 34 petition

Filing Reason

Disputes arising out of Tripartite Concession Agreement dated 27.11.2009 regarding construction, operation and maintenance of alternate route to Ghat Ki Guni through tunnel on BOT basis; appellants aggrieved by arbitral award allowing claims totaling Rs. 198.04 crores plus IRR

Previous Decisions

Arbitral award dated 25.06.2023 and corrigendum award dated 31.07.2023; Section 34 objection dismissed by District Judge, Commercial Court, Jaipur on 27.01.2025; executing court directed warrant of recovery on 09.01.2026 for Rs. 544.43 crore; High Court stayed execution on 22.01.2026

Issues

Whether the Commercial Court erred in dismissing the objections under Section 34 of the Arbitration and Conciliation Act, 1996 Whether the arbitral award and corrigendum dated 31.07.2023 were liable to be set aside within the scope of Sections 34 and 37 of the Act

Judgment Excerpts

Appeal herein is directed against the order dated 27.01.2025 passed by the learned District Judge, Commercial Court, Jaipur, whereby the objection petition preferred by the appellants under Section 34 of the Arbitration and Conciliation Act, 1996 ... assailing the arbitral award dated 25.06.2023 and the corrigendum award dated 31.07.2023, was dismissed. The arbitral proceedings culminated in an award, whereby Claim No. 1 and Claim No. 4 were allowed, Claim No. 2 was partly allowed, and Claim No. 3 was rejected. The learned Executing Court, vide its order dated 09.01.2026, had directed issuance of a warrant of recovery under Order XXI Rule 30 of the Code of Civil Procedure, 1908, for recovery of Rs. 544.43 crore. However, pursuant to an order dated 22.01.2026 passed by this Court, the execution proceedings were stayed.

Procedural History

Notice Inviting Tender dated 04.08.2009, amended 17.08.2009; pre-bid meeting held 08.09.2009; minutes circulated 14.09.2009; Letter for agreement of Award dated 13.10.2009; Tripartite Concession Agreement executed 27.11.2009; actual commencement 15.12.2010; actual completion 31.01.2013; statement of claim filed 15.02.2019; arbitral award passed 25.06.2023; corrigendum award passed 31.07.2023; Section 34 objection dismissed by Commercial Court on 27.01.2025; executing court directed warrant of recovery on 09.01.2026 for Rs. 544.43 crore; High Court stayed execution on 22.01.2026; present appeal pronounced on 17.08.2026.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 33
  • Code of Civil Procedure, 1908: Order XXI Rule 30
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Dismisses Revenue's Appeal in Income Tax Penalty Limitation Case — Tribunal's Order Setting Aside Penalty Under Section 271D Upheld. The Court Held That the Penalty Order Passed by the Range Head Was Barred by Limitation Und...
Related Judgement
Supreme Court Supreme Court Quashes Preventive Detention Order in Telangana Act Case Due to Non-Application of Mind and Stale Material. Detenu Granted Bail Months Before Detention Order, Conditions Fulfilled, No Breach of Public Order Established.