High Court of Judicature for Rajasthan at Jaipur Hears Appeal Against Dismissal of Section 34 Objection to Arbitral Award in BOT Tunnel Project. Dispute Centers on Arbitral Tribunal's Award of Cost Escalation and Toll Losses, and Validity of Corrigendum Adding Compound IRR, Under Arbitration and Conciliation Act, 1996 Sections 33, 34, and 37.

High Court: Rajasthan High Court Bench: Jaipur
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a tripartite concession agreement dated 27.11.2009 executed between the Government of Rajasthan, Jaipur Development Authority, and Rohan Rajdeep Rajasthan Infra Project Limited, a special purpose vehicle, for construction, operation, and maintenance of an alternate route to Ghat Ki Guni through a tunnel in Jhalana Hills, Jaipur on Build-Operate-Transfer basis. The project was awarded pursuant to Notice Inviting Tender dated 04.08.2009, amended on 17.08.2009, with a pre-bid meeting on 08.09.2009 and letter of agreement of award dated 13.10.2009. The approved project cost was Rs.150 crores with IRR of 20.33%, concession period of 13 years 05 months 20 days. The actual commencement date was 15.12.2010 against proposed 01.12.2009, and actual completion date was 31.01.2013 against stipulated date 14.06.2013. The respondent claimed that the Detailed Project Report supplied by the department was fundamentally defective, leading to inadequate natural overburden over tunnel tubes, necessitating revised alignment and cost escalation. It relied on surveys conducted in December 2009 and February 2010, communications dated 28.04.2010 and 12.05.2010, and approval of revised alignment on 20.10.2010. It also cited the debarment of the consultant associated with the earlier DPR and termination of the Project Head as administrative recognition of defects. Further, the presence of Baba Balaknath Samadhi at chainage 0+650 allegedly compelled additional revisions. The respondent filed statement of claim dated 15.02.2019 seeking Claim No.1 of Rs.175.67 crores for increase in project cost, Claim No.2 of Rs.188.02 crores for loss of toll, Claim No.3 of Rs.40.71 crores for compensation of toll loss due to delay in achieving COD, and Claim No.4 of Rs.8.49 crores for revenue loss from denial of right of way for advertisements. The arbitral tribunal allowed Claim No.1 in toto, partly allowed Claim No.2 (Rs.12.20 crores for traffic leakage through old GKG road and Rs.1.68 crores for demonetization), allowed Claim No.4, and rejected Claim No.3, resulting in total award of Rs.198.04 crores plus costs of Rs.23,66,061, with pre-award IRR @20.33% per annum and post-award interest @12% per annum after 90 days. A corrigendum award dated 31.07.2023 under Section 33 deleted the total award amount and made the award without an upper cap by adding compounded IRR @20.33%. Execution proceedings sought recovery of Rs.544.43 crores, and the executing court directed issuance of warrant of recovery under Order XXI Rule 30 CPC on 09.01.2026; execution was stayed by the High Court on 22.01.2026. The appellants challenged the arbitral award and the Commercial Court's dismissal of their Section 34 petition dated 27.01.2025. The High Court's final decision is not available in the provided excerpt.

Headnote

A) Arbitration - Section 34 Challenge - Scope of Interference - Arbitration and Conciliation Act, 1996, Sections 34, 37 - Appeal directed against dismissal of objections to arbitral award; Court to examine whether Commercial Court properly applied limited grounds for setting aside award and whether arbitral findings on cost escalation were perverse (Paras 1-8).

B) Arbitration - Corrigendum Award - Correction of Clerical Errors - Arbitration and Conciliation Act, 1996, Section 33 - Corrigendum deleted total award amount and made award without upper cap by adding compound IRR; issue whether this exceeded Section 33 power (Paras 6-7).

C) Contract Law - Concession Agreement - Interpretation and Risk Allocation - Tripartite Concession Agreement dated 27.11.2009 - Dispute regarding defective DPR, revised alignment, and cost escalation; respondent claimed DPR defects necessitated redesign; question whether risk allocated to concessionaire or authority (Paras 8.1-11).

D) Execution - Recovery Proceedings - Order XXI Rule 30 of Code of Civil Procedure, 1908 - Execution sought Rs.544.43 crores based on award; High Court stayed execution (Paras 7-8).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Commercial Court erred in dismissing the Section 34 objection petition; whether the corrigendum award dated 31.07.2023 exceeded the scope of Section 33 of the Arbitration and Conciliation Act, 1996; whether the arbitral award granting cost escalation, toll loss compensation, and compounded IRR is sustainable

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Limited grounds for setting aside arbitral award under Sections 34 and 37 of Arbitration and Conciliation Act
  • 1996
  • correction of clerical errors under Section 33 of Arbitration and Conciliation Act
  • scope of judicial interference with arbitral award
  • interpretation of tripartite concession agreement
  • risk allocation in public-private partnership BOT project
  • execution proceedings under Order XXI Rule 30 of Code of Civil Procedure
  • 1908
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (RAJ) (08) 47

D.B. Civil Miscellaneous Appeal No. 1560/2025

2026-08-17

Arun Monga, Sandeep Taneja

Rajendra Prasad, Tanay Goyal, Sheetanshu Sharma, Harshita Thakar, Dhriti Sharma, Sudhir Gupta, Sweta Chauhan, Tarak Ahuja, Ishan Khanna, Aditya Shandilya, Rachit Somani

Jaipur Development Authority; Urban Development And Housing Department (UDH), Government Of Rajasthan

Rohan Rajdeep Rajasthan Infra Project Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of Arbitration and Conciliation Act, 1996 against dismissal of Section 34 objection petition by Commercial Court challenging arbitral award and corrigendum award.

Remedy Sought

Appellants sought to set aside the order dated 27.01.2025 of the District Judge, Commercial Court, Jaipur and consequently the arbitral award dated 25.06.2023 and corrigendum award dated 31.07.2023.

Filing Reason

Disputes arising out of a Tripartite Concession Agreement dated 27.11.2009 concerning construction, operation, and maintenance of a tunnel on BOT basis; respondent claimed cost escalation and loss of toll; arbitral award partly allowed claims; Section 34 petition dismissed.

Previous Decisions

Arbitral award dated 25.06.2023 allowed Claim No.1 in toto, partly allowed Claim No.2, allowed Claim No.4, rejected Claim No.3, with total award Rs.198.04 crores, costs, and IRR; corrigendum award dated 31.07.2023 under Section 33 removed upper cap and applied compound IRR; District Judge, Commercial Court, Jaipur dismissed Section 34 objection petition on 27.01.2025; Executing Court order dated 09.01.2026 directed recovery warrant under Order XXI Rule 30 CPC; High Court stayed execution on 22.01.2026.

Issues

Whether the Commercial Court erred in dismissing the Section 34 objection petition without adequately examining the arbitral award Whether the corrigendum award dated 31.07.2023 under Section 33 of the Arbitration and Conciliation Act, 1996 exceeded the scope of correction of clerical errors Whether the arbitral award granting cost escalation, toll loss compensation, and compounded IRR is sustainable in law

Submissions/Arguments

Respondent asserted that the Detailed Project Report supplied by the department was fundamentally defective in material particulars affecting structural and engineering feasibility of tunnel alignment. Respondent claimed that surveys in December 2009 and February 2010 revealed inadequate natural overburden over tunnel tubes, necessitating redesign and cost escalation. Respondent relied upon communications dated 28.04.2010 and 12.05.2010 and subsequent approvals to show that revised alignment was approved on 20.10.2010. Respondent contended that presence of Baba Balaknath Samadhi at chainage 0+650 compelled further revision on instructions of authority, causing repeated redesign.

Judgment Excerpts

Appeal herein is directed against the order dated 27.01.2025 passed by the learned District Judge, Commercial Court, Jaipur, whereby the objection petition preferred by the appellants under Section 34 of the Arbitration and Conciliation Act, 1996... was dismissed. The Corrigendum, inter alia, deleted the words 'amounting to Rs. 198.04 Crores', ... and made the original Award dated 25.06.2023 without any upper cap, by adding IRR @20.33% on compounding basis per annum.

Procedural History

Arbitral proceedings initiated by respondent's statement of claim dated 15.02.2019 before sole arbitrator. Arbitral award dated 25.06.2023 allowed Claim No.1 in toto, Claim No.2 partly, Claim No.4 allowed, Claim No.3 rejected; total award Rs.198.04 crores plus costs and IRR @20.33%. Corrigendum award dated 31.07.2023 under Section 33 deleted upper cap and allowed compounded IRR. Appellants filed Section 34 objection petition before District Judge, Commercial Court, Jaipur; dismissed on 27.01.2025. Execution proceedings instituted seeking Rs.544.43 crores; Executing Court order dated 09.01.2026 directed warrant of recovery under Order XXI Rule 30 CPC. High Court stayed execution by order dated 22.01.2026. Present appeal filed against dismissal of Section 34 petition.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 33, Section 34, Section 37
  • Code of Civil Procedure, 1908: Order XXI Rule 30
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature for Rajasthan Examines Challenge to Land Acquisition Lapse and Encroachment Proceedings. Petition Challenges Whether Acquisition Lapsed Under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisitio...
Related Judgement
High Court High Court of Karnataka Hears Intra-Court Appeal Against Quashing of Survey Notices in Land Dispute. Appeal Challenges Single Judge's Ruling That Survey Authorities Cannot Adjudicate Disputed Title and Must Leave Validity of Excess Sale Deeds to Civi...