Rajasthan High Court Reviews Appeal Under Section 37 of Arbitration and Conciliation Act, 1996 Challenging Setting Aside of Arbitral Award in Wind Turbine Generation Guarantee Dispute. The Commercial Court held that the generation guarantee was limited to four years under the purchase order and MOU, contrary to the arbitrator's finding that it extended to the entire 20-year turnkey contract.

High Court: Rajasthan High Court Bench: Jaipur
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a wind farm project under the Policy for Promotion of Electricity Generation from Wind, 2003, in which the respondent, Suzlon Energy Limited, acted as developer and the appellant, Navbharat Buildcon Private Limited, invested in a wind turbine generator on a turnkey basis for twenty years. The appellant issued a purchase order dated 14.07.2004 for one SUZLON S-66 – 1.25 MW WTG to be installed at Soda Mada, Jaisalmer, with annexures covering price, terms and conditions, generation and performance guarantee, scope of electrical works, and technical data. A work order and a Memorandum of Understanding dated 16.07.2004 were also executed, along with operation and maintenance agreements and a Power Purchase Agreement. The WTG was commissioned on 29.12.2004. Disputes arose due to shortfall in electricity generation, leading the appellant to invoke arbitration and file a statement of claim seeking compensation for shortfall in generation over twenty years, non-availability of machine below 95% guarantee for certain years, damages for loan repayment burden, and other reliefs. The respondent denied the claims, asserting that the generation guarantee was only for four years, that it had paid compensation of Rs.1,36,93,149/- with interest, and that wind and grid availability were external factors beyond its control. The arbitrator framed seventeen issues and by award dated 20.04.2018 decided Issues 1, 3, 4, 6, 7, 8, 11, 12, 13, 14 and 15 in favor of the appellant, holding that the turnkey project extended the generation guarantee to the entire twenty-year contract period, while other issues were decided against the appellant. The respondent filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 before the Commercial Court, Jaipur, which by order dated 03.01.2019 allowed the petition and set aside the award, holding that a conjoint reading of the purchase order and MOU restricted the generation guarantee to four years. The appellant then filed the present appeal under Section 37 of the Act of 1996 before the High Court of Judicature for Rajasthan, Bench at Jaipur. The provided judgment text ends at paragraph 2.13, before the High Court's reasoning and final decision. Thus, the background, facts, legal issues, and arguments are available, but the court's analysis and operative order are not included in the excerpt.

Headnote

A) Arbitration Law - Appeal Under Section 37 - Appeal against order under Section 34 setting aside arbitral award - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The High Court heard an appeal challenging the Commercial Court's order dated 03.01.2019 which allowed the respondent's Section 34 petition and set aside the arbitral award dated 20.04.2018 - The final adjudication of the appeal is not available in the provided excerpt (Paras 1-2.13).

B) Contract Law - Generation Guarantee Period - Whether the generation guarantee extended to the entire 20-year contract or was restricted to four years - Purchase order dated 14.07.2004 and MOU dated 16.07.2004 - The arbitrator held that the turnkey project meant the generation guarantee extended to the entire 20-year contract; the Commercial Court held that a conjoint reading of the purchase order and MOU restricted the guarantee to four years - The High Court's final view is not mentioned in the excerpt (Paras 2.1-2.13).

C) Contract Law - Turnkey Project Interpretation - Turnkey project imposes obligations for entire contract period - Not mentioned - The dispute pertained to whether the turnkey nature of the project extended the generation guarantee beyond the initial guarantee period - The arbitrator accepted the appellant's contention on this point, but the Commercial Court rejected it; the High Court's final decision is not available (Paras 2.12-2.13).

D) Arbitration Law - Issues Framed by Arbitrator - Issues included guarantee, replacement, compensation, interest, loan damages, short generation, machine availability, and operation and maintenance payments - Arbitration and Conciliation Act, 1996, Sections 31, 34 - The arbitrator framed seventeen issues covering the parties' claims and defenses and decided some in favor of the appellant and some against - The appeal before the High Court concerned the correctness of the Commercial Court's order setting aside that award (Paras 2.11-2.13).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Commercial Court erred in setting aside the arbitral award dated 20.04.2018 under Section 34 of Arbitration and Conciliation Act, 1996 on the ground that the generation guarantee was restricted to four years and not the entire 20-year contract period; whether the generation guarantee under the purchase order dated 14.07.2004 and MOU dated 16.07.2004 extended to the entire contractual period or was limited to four years; whether the turnkey nature of the project imposed a generation guarantee for 20 years; whether the WTG was defective and the appellant entitled to replacement or compensation for shortfall in generation, non-availability of machine, and loan repayment damages.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Appeal under Section 37 of Arbitration and Conciliation Act
  • 1996 against order setting aside arbitral award under Section 34
  • Interpretation of contractual terms regarding generation guarantee period
  • Turnkey project implications on guarantee duration
  • Scope of interference under Section 34 and Section 37
  • Machine availability and grid availability as factors affecting generation
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (RAJ) (08) 45

D.B. Civil Miscellaneous Appeal No. 783/2019

2026-08-17

Arun Monga, Sandeep Taneja

Sudhir Gupta, Sukriti Kasliwal, Shweta Chouhan, Rachit Somani, Sundaram Sharma, Mahendra Singh, Adhiraj Shekhawat, Shruti Jain, Sunil Nath

M/s Navbharat Buildcon Private Limited

M/s Suzlon Energy Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of Arbitration and Conciliation Act, 1996 against order of Commercial Court setting aside arbitral award

Remedy Sought

Appellant sought setting aside of Commercial Court order dated 03.01.2019 and restoration of arbitral award dated 20.04.2018

Filing Reason

Respondent filed Section 34 petition against arbitral award; Commercial Court allowed it; appellant appealed under Section 37

Previous Decisions

Arbitrator passed award dated 20.04.2018 partly in favour of appellant; Commercial Court allowed respondent's Section 34 petition and set aside award on 03.01.2019

Issues

Whether the generation guarantee in the purchase order and MOU extended to the entire 20-year contract period or was limited to four years Whether the turnkey nature of the project imposed a generation guarantee for the whole contract period Whether the WTG was defective and the appellant entitled to replacement Whether the appellant was entitled to compensation for non-availability of machine below 95% for financial years 2012-13 and 2013-14 Whether the appellant was entitled to damages for loan repayment burden Whether the appellant was entitled to compensation for short generation from 01.02.2009 to 31.01.2017 Whether the respondent was liable for compensation after expiry of the generation guarantee period Whether machine availability compensation is governed by the operation and maintenance agreement

Submissions/Arguments

Appellant argued that the respondent guaranteed annual generation of 28 lakh units for the entire 20-year contract period and that the WTG was defective and failed to meet the guarantee Appellant claimed compensation for shortfall in generation, non-availability of machine below 95% in specified years, and damages for loan repayment burden Respondent argued that the generation guarantee was restricted to four years, for which bank guarantee/corporate guarantee was furnished, and that it had fully discharged its obligations by paying Rs.1,36,93,149/- with interest Respondent contended that wind availability and grid availability were external factors beyond its control and only machine availability was within its control Respondent asserted that all contractual obligations had been performed and the claims were liable to be dismissed

Judgment Excerpts

The present appeal has been filed under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the Act of 1996’), assailing the order dated 03.01.2019 passed by the learned Commercial Court No.4, Jaipur (for short, ‘Commercial Court’), whereby the objection petition filed by the respondent under Section 34 of the Act of 1996 was allowed and the arbitral award dated 20.04.2018 passed by the learned arbitrator was set aside. The learned arbitrator, vide arbitral award dated 20.04.2018, decided Issue Nos. 1, 3, 4, 6, 7, 8, 11, 12, 13, 14 and 15 in favour of the appellant. Issue No. 10 was partly decided in favour of the appellant, whereas Issue Nos. 2, 5, 9 and 16 were decided against the appellant. Vide the impugned order, the learned Commercial Court allowed the said objection petition, holding that a conjoint reading of the terms and conditions of the purchase order dated 14.07.2004 and the MOU dated 16.07.2004 established that the generation guarantee was restricted to a period of four years.

Procedural History

Disputes arose due to shortfall in generation from WTG; appellant invoked arbitration and filed statement of claim; respondent filed reply; appellant filed rejoinder; arbitrator framed seventeen issues; arbitrator passed award on 20.04.2018 partly in favour of appellant; respondent filed Section 34 petition before Commercial Court Jaipur; Commercial Court allowed petition on 03.01.2019 and set aside award; appellant filed present appeal under Section 37 before High Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Defendant in Contract Damages Case Due to Failure to Prove Kanpur Market Price. In a sale of goods contract deliverable f.o.r. Kanpur, damages for breach could not be assessed on Calcutta market rate absent evidence of special ci...
Related Judgement
High Court Bombay High Court Upholds Acquittal in PC Act Case Due to Unreliable Complainant and Lack of Corroboration — Demand and Acceptance of Bribe Not Proved Beyond Reasonable Doubt.