Case Note & Summary
The dispute arose from a wind farm project under the Policy for Promotion of Electricity Generation from Wind, 2003, in which the respondent, Suzlon Energy Limited, acted as developer and the appellant, Navbharat Buildcon Private Limited, invested in a wind turbine generator on a turnkey basis for twenty years. The appellant issued a purchase order dated 14.07.2004 for one SUZLON S-66 – 1.25 MW WTG to be installed at Soda Mada, Jaisalmer, with annexures covering price, terms and conditions, generation and performance guarantee, scope of electrical works, and technical data. A work order and a Memorandum of Understanding dated 16.07.2004 were also executed, along with operation and maintenance agreements and a Power Purchase Agreement. The WTG was commissioned on 29.12.2004. Disputes arose due to shortfall in electricity generation, leading the appellant to invoke arbitration and file a statement of claim seeking compensation for shortfall in generation over twenty years, non-availability of machine below 95% guarantee for certain years, damages for loan repayment burden, and other reliefs. The respondent denied the claims, asserting that the generation guarantee was only for four years, that it had paid compensation of Rs.1,36,93,149/- with interest, and that wind and grid availability were external factors beyond its control. The arbitrator framed seventeen issues and by award dated 20.04.2018 decided Issues 1, 3, 4, 6, 7, 8, 11, 12, 13, 14 and 15 in favor of the appellant, holding that the turnkey project extended the generation guarantee to the entire twenty-year contract period, while other issues were decided against the appellant. The respondent filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 before the Commercial Court, Jaipur, which by order dated 03.01.2019 allowed the petition and set aside the award, holding that a conjoint reading of the purchase order and MOU restricted the generation guarantee to four years. The appellant then filed the present appeal under Section 37 of the Act of 1996 before the High Court of Judicature for Rajasthan, Bench at Jaipur. The provided judgment text ends at paragraph 2.13, before the High Court's reasoning and final decision. Thus, the background, facts, legal issues, and arguments are available, but the court's analysis and operative order are not included in the excerpt.
Headnote
A) Arbitration Law - Appeal Under Section 37 - Appeal against order under Section 34 setting aside arbitral award - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The High Court heard an appeal challenging the Commercial Court's order dated 03.01.2019 which allowed the respondent's Section 34 petition and set aside the arbitral award dated 20.04.2018 - The final adjudication of the appeal is not available in the provided excerpt (Paras 1-2.13). B) Contract Law - Generation Guarantee Period - Whether the generation guarantee extended to the entire 20-year contract or was restricted to four years - Purchase order dated 14.07.2004 and MOU dated 16.07.2004 - The arbitrator held that the turnkey project meant the generation guarantee extended to the entire 20-year contract; the Commercial Court held that a conjoint reading of the purchase order and MOU restricted the guarantee to four years - The High Court's final view is not mentioned in the excerpt (Paras 2.1-2.13). C) Contract Law - Turnkey Project Interpretation - Turnkey project imposes obligations for entire contract period - Not mentioned - The dispute pertained to whether the turnkey nature of the project extended the generation guarantee beyond the initial guarantee period - The arbitrator accepted the appellant's contention on this point, but the Commercial Court rejected it; the High Court's final decision is not available (Paras 2.12-2.13). D) Arbitration Law - Issues Framed by Arbitrator - Issues included guarantee, replacement, compensation, interest, loan damages, short generation, machine availability, and operation and maintenance payments - Arbitration and Conciliation Act, 1996, Sections 31, 34 - The arbitrator framed seventeen issues covering the parties' claims and defenses and decided some in favor of the appellant and some against - The appeal before the High Court concerned the correctness of the Commercial Court's order setting aside that award (Paras 2.11-2.13).
Issue of Consideration
Whether the learned Commercial Court erred in setting aside the arbitral award dated 20.04.2018 under Section 34 of Arbitration and Conciliation Act, 1996 on the ground that the generation guarantee was restricted to four years and not the entire 20-year contract period; whether the generation guarantee under the purchase order dated 14.07.2004 and MOU dated 16.07.2004 extended to the entire contractual period or was limited to four years; whether the turnkey nature of the project imposed a generation guarantee for 20 years; whether the WTG was defective and the appellant entitled to replacement or compensation for shortfall in generation, non-availability of machine, and loan repayment damages.
Law Points
- Appeal under Section 37 of Arbitration and Conciliation Act
- 1996 against order setting aside arbitral award under Section 34
- Interpretation of contractual terms regarding generation guarantee period
- Turnkey project implications on guarantee duration
- Scope of interference under Section 34 and Section 37
- Machine availability and grid availability as factors affecting generation


