High Court of Karnataka Hears Commercial Appeal Against Order Upholding Arbitral Award in RMSA Package A-4 Construction Contract Dispute. Arbitral Award Granted Price Adjustment, Overhead Charges, and Loss of Profit; Commercial Court Found No Ground Under Section 34 of Arbitration and Conciliation Act, 1996 to Interfere, Leading to Appeal Under Section 37(1)(c) and Section 13(1A) of Commercial Courts Act, 2015.

High Court: Karnataka High Court Bench: BENGALURU
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The present matter was a commercial appeal before the High Court of Karnataka filed under Section 13(1A) of the Commercial Courts Act, 2015 read with Section 37(1)(c) of the Arbitration and Conciliation Act, 1996, challenging the judgment dated 30.11.2024 passed by the LXXXVI Additional City Civil and Sessions Judge, Commercial Court, Bengaluru in Com.A.P.No.40/2024. In that judgment, the Commercial Court dismissed the appellant's petition under Section 34 of the Arbitration and Conciliation Act, 1996, which had sought setting aside of an arbitral award dated 10.11.2023 rendered by a Sole Arbitrator. The appeal was one of a batch of nine similar appeals arising from separate arbitral awards in respect of nine packages awarded to the respondent contractor. The underlying dispute related to Package A-4 under the Rashtriya Madhyamika Shikshana Abhiyana scheme, involving construction of Adarsha Vidyalayas and girls' hostels in Bidar District. Tenders were invited on 24.09.2012; the respondent contractor was the successful bidder and, after negotiations, offered a revised price on 13.02.2013 on the express condition that a price adjustment clause would be included. The Letter of Acceptance was issued on 18.03.2013 and a Construction Agreement dated 15.05.2013 was executed. The stipulated completion period was twenty months from the notice to proceed dated 17.05.2013, expiring on 16.02.2015. A Supplementary Agreement dated 17.03.2017 provided that all conditions of the original agreement would apply except for the price adjustment clause, for which a decision would be taken after government enquiry. Delays occurred, and the contractor raised claims for price adjustment, alleging delays in handing over sites, supply of drawings, approvals, payments, water and power availability, and sand scarcity. The Government initially ordered an audit and enquiry, and by communication dated 17.07.2018 informed contractors that price adjustment would not be paid. Certain other contractors challenged the Government Order dated 16.11.2016 before the High Court; a Single Judge quashed it on 25.02.2019, and a Division Bench disposed of intra-court appeals on 20.10.2020 observing that parties would be governed by their contract terms. The contractor invoked arbitration on 08.05.2019, and the High Court appointed a Sole Arbitrator on 05.11.2020. Government Order dated 30.09.2020 subsequently allowed price adjustment in packages containing the clause. The Arbitral Tribunal partly allowed the contractor's claims, awarding a total sum of Rs 3,80,58,227 comprising price adjustment, interest, unproductive overhead charges, loss of expected profit, future interest at 9% per annum on Rs 2,75,58,852, and costs of Rs 3,00,000. The State challenged the award under Section 34, contending that the price variation clause was not applicable because the notice inviting tenders expressly provided the clause be read as deleted and was unauthorisedly included in the agreement. The Commercial Court dismissed the Section 34 petition, finding no ground to interfere. The present appeal was heard and reserved for judgment on 21.07.2026 and pronounced on 18.08.2026. The provided judgment text ends before the High Court's analysis and final decision, so the ultimate outcome of the appeal is not included in the extract.

Headnote

A) Arbitration - Setting Aside of Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Limited Judicial Interference - The Commercial Court found no ground to interfere with the arbitral award dated 10.11.2023 which partly allowed the contractor's claims for price adjustment, unproductive overhead charges, loss of expected profit, and interest; the Section 34 petition was dismissed; the present appeal was filed under Section 37(1)(c) read with Section 13(1A) of Commercial Courts Act, 2015 (Paras 1-2).

B) Contract Law - Price Adjustment Clause - Clause 39 of Conditions of Contract - Binding Nature of Incorporated Terms - The contractor made a revised offer on 13.02.2013 expressly stating readiness to execute the project considering inclusion of Price Adjustment Clause; the Letter of Acceptance dated 18.03.2013 accepted the revised offer; the Construction Agreement incorporated the Conditions of Contract including Clause 39; the State contended that the notice inviting tenders provided the clause be read as deleted and the clause was unauthorisedly included; the writ court held that whether Clause 39 was incorporated with approval or inserted unauthorisedly was a disputed question of fact and relegated the parties to arbitration (Paras 5-7, 11-12, 19).

C) Contract Law - Supplementary Agreement - Exclusion of Price Adjustment Clause - Clause 4(i) of the Supplementary Agreement dated 17.03.2017 stipulated that all conditions of the original agreement would apply except for the price adjustment clause, for which a decision would be taken after completion of the government enquiry; the contractor invoked Clause 39 and raised price adjustment bills which remained unpaid (Paras 8-10).

D) Administrative Law - Government Orders - Government Order dated 16.11.2016 and Communication dated 17.07.2018 - A Single Judge quashed the Government Order and restrained the State from acting upon KIPA reports; a Division Bench disposed of intra-court appeals observing that parties would be governed by the terms of the contract; subsequently Government Order dated 30.09.2020 allowed price adjustment in respect of packages whose tender conditions contained the clause (Paras 11-12, 16).

E) Arbitration - Appointment of Arbitrator - Section 11 of Arbitration and Conciliation Act, 1996 - The contractor invoked the arbitration agreement by legal notice dated 08.05.2019; the High Court allowed the Section 11 application on 05.11.2020 and appointed a Sole Arbitrator (Paras 13-15).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Commercial Court erred in dismissing the appellant's petition under Section 34 of the Arbitration and Conciliation Act, 1996; whether the price adjustment clause (Clause 39) of the Conditions of Contract was applicable and binding on the appellant; whether the contractor was entitled to price adjustment, unproductive overhead charges, loss of expected profit, and interest; whether the arbitral award suffered from any ground for setting aside under Section 34

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Commercial Court dismissed the appellant's petition under Section 34 of the Arbitration and Conciliation Act, 1996, declining to set aside the arbitral award dated 10.11.2023. The High Court's final decision on the present appeal is not mentioned in the provided text.

Law Points

  • Arbitral award can be set aside only on limited grounds under Section 34 of Arbitration and Conciliation Act
  • 1996
  • Disputed questions of fact regarding incorporation of contractual clauses are to be resolved by arbitration
  • Parties are governed by terms of the contract entered into by them
  • Price adjustment clause if incorporated in contract is binding and enforceable
  • Supplementary agreement can exclude price adjustment clause pending government enquiry
  • Government orders cannot override contractual terms if clause formed part of contract
  • Section 37(1)(c) appeal against refusal to set aside award under Section 34 requires considering limited grounds
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (KAR) (08) 71

COMAP No. 54 of 2025

2026-08-18

Vibhu Bakhru, Chief Justice; K.S. Hemalekha, Justice

Sri Kiran Vasanth Ron, Additional Advocate General; Sri K.S. Harish, Government Advocate; Sri Zufikir Shafi, Advocate

State Project Director, Rashtriya Madhyamika Shiksha Abhiyan

M/s. KMV Projects and Sri Justice K.N. Keshavanarayana (Sole Arbitrator)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial appeal under Section 13(1A) of Commercial Courts Act, 2015 read with Section 37(1)(c) of Arbitration and Conciliation Act, 1996 against dismissal of Section 34 petition challenging an arbitral award in a construction contract dispute arising from Package A-4 of Rashtriya Madhyamika Shikshana Abhiyana.

Remedy Sought

Appellant sought setting aside of the judgment dated 30.11.2024 passed in Com.A.P.No.40/2024 and consequently setting aside of the arbitral award dated 10.11.2023.

Filing Reason

The Commercial Court dismissed the appellant's Section 34 petition; the appellant contended that the price adjustment clause was not applicable and the award suffered from grounds under Section 34.

Previous Decisions

Arbitral Tribunal partly allowed respondent's claims on 10.11.2023; Commercial Court dismissed Section 34 petition on 30.11.2024; Single Judge of High Court quashed Government Order dated 16.11.2016 on 25.02.2019 and relegated parties to arbitration; Division Bench disposed of writ appeals on 20.10.2020 observing parties are governed by contract terms.

Issues

Whether the Commercial Court erred in dismissing the appellant's petition under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the price adjustment clause (Clause 39) of the Conditions of Contract was applicable and binding on the appellant. Whether the contractor was entitled to price adjustment, unproductive overhead charges, loss of expected profit, and interest. Whether the arbitral award suffered from any ground for setting aside under Section 34.

Submissions/Arguments

Appellant contended that the price variation clause (Clause 39) of the conditions of contract was not applicable as the notice inviting tenders uploaded expressly provided that the said clause be read as deleted; the clause was unauthorisedly included in the Agreement. Respondent contractor contended that after being declared successful bidder, it reduced its rates by factoring in the price escalation clause and economies of scale; the appellant did not hand over the sites within the stipulated period, causing delay; the appellant withheld amounts due, compelling arbitration. Respondent contractor alleged delays in handing over sites, supply of drawings, approval of work slips and EIRL items, release of payments, non-availability of water and power, and scarcity of sand, invoking Clause 39 and raising price adjustment bills. During writ proceedings, the State argued that the price adjustment clause in tender documents was not duly approved and was not binding on the Government, while the contractors argued that the clause formed part of the contract and was binding.

Ratio Decidendi

Disputed questions of fact regarding the incorporation and approval of a price adjustment clause in a construction contract are to be resolved by arbitration; once a contract is entered into, the parties are governed by its terms; an arbitral award can be interfered with only on limited grounds under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

The learned Commercial Court found no ground to interfere with the impugned award and accordingly passed the impugned order dismissing the petition. (Para 1) By its letter dated 13.02.2013 (Ex.C2)... KMV concluded the said letter by stating that it was 'ready to execute the above project considering the inclusion of 'Price Adjustment Clause' at the said price. (Para 6) Clause 4(i) of the Supplementary Agreement stipulates that all conditions of the original agreement (the Agreement) are applicable 'except for the price adjustment clause, for which a decision will be taken after the completion of enquiry ordered by the Government'. (Para 9) The court observed that whether Clause 39 was incorporated with approval or inserted unauthorisedly is a disputed question of fact, and relegated the petitioners to arbitration. (Para 12) The Division Bench ... disposed of ... observing that 'the parties would be governed by the terms of the contract entered into by them in respect of various packages awarded by the State'. (Para 12)

Procedural History

Tenders were invited on 24.09.2012; contractor emerged successful bidder for Package A-4; revised offer was made on 13.02.2013; Letter of Acceptance dated 18.03.2013; Construction Agreement dated 15.05.2013; notice to proceed issued on 17.05.2013; completion period expired on 16.02.2015; Supplementary Agreement dated 17.03.2017; Government Order dated 16.11.2016; communication dated 17.07.2018 informing no price adjustment; Single Judge quashed Government Order on 25.02.2019; contractor invoked arbitration on 08.05.2019; Section 11 application allowed and Sole Arbitrator appointed on 05.11.2020; Division Bench disposed of writ appeals on 20.10.2020; Government Order dated 30.09.2020 allowed price adjustment in packages containing the clause; extension of time order dated 13.01.2021; Arbitral Tribunal passed award on 10.11.2023; Section 34 petition Com.A.P.No.40/2024 dismissed on 30.11.2024; present COMAP No.54/2025 reserved on 21.07.2026 and pronounced on 18.08.2026.

Acts & Sections

  • Commercial Courts Act, 2015: Section 13(1A)
  • Arbitration and Conciliation Act, 1996: Sections 11, 34, 37(1)(c)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows State Appeal in Land Title Dispute Where Lower Courts Relied on Revenue Entry Correction. Revenue Entries Do Not Create or Extinguish Title and Without the Settlement Officer's Order or Other Title Documents, Plaintiffs' Suit for...
Related Judgement
High Court Bombay High Court Dismisses Petitions Challenging Reduction of Superannuation Age from 60 to 58 for Employees of Government Mining Corporation. State as Sole Shareholder Can Amend Service Rules Unilaterally Without Employee Consent.