High Court of Karnataka Dismisses Appeal of Bidder in Tender Rejection for Battery Energy Storage Project — Appellant's Bid Properly Rejected as Non-Responsive. Non-Furnishing of Affiliate Undertaking as Required by Clause 37.3 of RfS Justified Rejection and No Violation of Natural Justice Found.

High Court: Karnataka High Court Bench: BENGALURU In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appeal arose from a writ petition challenging the rejection of a bid submitted in response to a Request for Selection (RfS) for a Battery Energy Storage System project. The appellant, a private energy company, had submitted its bid for a 150 MW/300 MWh standalone battery storage system. The bid was declared non-responsive, and the appellant filed a writ petition alleging violation of natural justice and erroneous rejection. The learned Single Judge dismissed the petition, finding no error in the Tender Evaluation Committee's decision and no breach of natural justice. On appeal, the appellant contended that its bid was wrongly rejected without communicating reasons, and that the same documents were accepted in a similar tender in Tamil Nadu. It also argued that the observation of the Single Judge regarding its unwillingness to commit to a rate was incorrect. The respondent authorities, led by the Karnataka Power Transmission Corporation Limited, submitted that the principal ground for rejection was the appellant's failure to furnish an undertaking from its affiliates as required under Clause 37.3 of the RfS. The court examined the tender conditions and noted that Clause 37.3 expressly required such an undertaking when financial qualification is based on affiliate capability. The appellant had relied on two affiliates but did not provide the mandated board resolutions or CEO/MD letters. The court held that non-compliance with this essential condition justified the declaration of the bid as non-responsive. Regarding natural justice, the court observed that the rejection was communicated through the e-tender portal, and the reasons were later made known; therefore, no violation had occurred. The court rejected the appellant's other contentions and upheld the Tender Evaluation Committee's decision. Consequently, the writ appeal was dismissed, affirming the rejection of the bid as non-responsive.

Headnote

A) Tender Law - Bid Responsiveness - Compliance with Tender Conditions - Karnataka High Court Act, 1961, Section 4 - The appellant failed to submit an undertaking from its affiliates as mandated by Clause 37.3 of the RfS, which required board resolutions or CEO/MD letters undertaking to contribute equity and performance guarantees if qualification was sought on the basis of affiliate financial capability. Held that the Tender Evaluation Committee's decision to declare the bid non-responsive was justified and not erroneous. (Paras 16-19)

B) Administrative Law - Natural Justice - Communication of Reasons in E-Tendering - Not mentioned - The appellant contended that non-communication of reasons for rejection violated principles of natural justice. Held that since the rejection was reflected on the e-tender portal and reasons were subsequently disclosed, there was no violation of natural justice vitiating the process. (Paras 8-9, 17-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge erred in dismissing the writ petition challenging the rejection of the appellant's bid as non-responsive; Whether there was violation of principles of natural justice in not communicating reasons for rejection; Whether the appellant's bid was correctly rejected for non-compliance with Clause 37.3 of the RfS.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The writ appeal is dismissed. The court upheld the rejection of the appellant's bid as non-responsive due to non-compliance with Clause 37.3 of the RfS and found no violation of natural justice.

Law Points

  • compliance with tender conditions
  • no violation of natural justice
  • bid responsiveness determined by Tender Evaluation Committee
  • non-furnishing of affiliate undertaking renders bid non-responsive
  • clause 37.3 of RfS
  • no requirement to communicate detailed reasons for rejection in e-tender process
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (KAR) (07) 102

Writ Appeal No. 545 of 2026 (GM-TEN)

2026-07-20

Vibhu Bakhru, K.S. Hemalekha

Sahil Sood, Shruti Shivkumar, Mohsin Khan Pathan, K. Shashi Kiran Shetty, Rakshitha D.J., Adoorya Harish, K.S. Harish, B.S. Venkatanarayana, C.K. Nandakumar, Shahnawaz Mamadapur

Forceone SD Private Limited

Karnataka Power Transmission Corporation Limited and Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ appeal against dismissal of writ petition challenging rejection of bid in tender process.

Remedy Sought

The appellant sought to set aside the order rejecting its bid as non-responsive and to declare the successful bidder's bid as invalid.

Filing Reason

The appellant's bid was rejected as non-responsive, and it claimed the rejection was erroneous and without communication of reasons, violating natural justice.

Previous Decisions

The learned Single Judge dismissed the writ petition, holding that there was no error in the Tender Evaluation Committee's decision and no violation of natural justice.

Issues

Whether the appellant's bid was correctly rejected as non-responsive for failure to furnish affiliate undertaking under Clause 37.3 of the RfS? Whether non-communication of reasons for rejection amounted to violation of natural justice?

Submissions/Arguments

Appellant: The bid was wrongly rejected as non-responsive; no reasons communicated; the same documents were accepted in a similar tender in Tamil Nadu; the appellant was willing to commit to its competitive rate; the TEC sought an opinion but still rejected; no deficiency existed. Respondents: The principal ground was non-furnishing of affiliate undertaking as required by Clause 37.3; the rejection was justified.

Ratio Decidendi

The rejection of a bid as non-responsive for non-compliance with the express requirement of an affiliate undertaking under Clause 37.3 of the RfS is justified; no violation of natural justice occurs if the rejection is communicated via the e-tender portal and reasons are subsequently made known.

Judgment Excerpts

we are unable to accept that the same would vitiate the bidding process or the decision of the authority to reject the appellant’s proposal as non-responsive. the central dispute is whether the decision of the TEC can be faulted. the appellant had not furnished an undertaking of its affiliates as required in terms of clause 37.3 of the RfS.

Procedural History

The appellant filed writ petition W.P.No.26719/2025 challenging the rejection of its bid dated 19.08.2025. The learned Single Judge dismissed the petition on 27.01.2026. The appellant filed the present writ appeal under Section 4 of the Karnataka High Court Act.

Acts & Sections

  • Karnataka High Court Act, 1961: Section 4
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Dismisses Appeal of Bidder in Tender Rejection for Battery Energy Storage Project — Appellant's Bid Properly Rejected as Non-Responsive. Non-Furnishing of Affiliate Undertaking as Required by Clause 37.3 of RfS Justified Rej...
Related Judgement
High Court Karnataka High Court Quashes FIR Against Government Engineers in Corruption Case Due to Invalid Police Station Notification. Anti-Corruption Bureau Koppal Lacked Notification Under Section 2(s) of Cr.P.C., Rendering FIR Void.