Supreme Court Hears Civil Appeals Concerning Applicability of Interest on Delayed Payments Act to Prior Contracts. The appeals arise from a common question of law regarding the retrospective application of the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993.

  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The appeals before the Supreme Court arose from a common question of law regarding the applicability of the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 ('the Act') to supply contracts concluded before the Act's commencement on 23 September 1992. The appellants, M/s Shanti Conductors (P) Ltd. and others, were small-scale industrial undertakings that had supplied aluminium electrical conductors to the respondent Assam State Electricity Board pursuant to purchase orders dated 31 March 1992 and 13 May 1992. The supplies were completed by 4 October 1993, and the Board made full payment of the principal amount on 5 March 1994. Alleging delay in payment, the appellants filed a suit on 10 January 1997 for recovery of interest under the Act. The trial court decreed the suit on 2 February 2000, awarding compound interest. The Board appealed, and the Gauhati High Court after a reference to a Full Bench, ultimately allowed the appeal on 20 November 2012, relying on the Supreme Court's decision in Purbanchal Cables & Conductors Pvt. Ltd. v. Assam State Electricity Board, (2012) 7 SCC 462, which held that the Act applies only to sale agreements entered into after the date of commencement of the Act. The Full Bench had earlier on 5 March 2002 held that the Act applies to pre-commencement contracts and that a suit for interest alone is maintainable, but the Division Bench felt bound by the later Supreme Court ruling. The legal issues before the Supreme Court were: (i) whether the Act applies to contracts entered into prior to 23 September 1992; (ii) whether the test of 'sale agreement' adopted in Purbanchal Cables is the correct criterion for determining the applicability of the Act; (iii) whether a suit for mere interest under the Act is maintainable; and (iv) whether acceptance of delayed payment without reserving the right to claim interest extinguishes the claim. The appellants argued that the Act, being a welfare legislation aimed at protecting small-scale industries, should be given retroactive operation so as to cover all outstanding payments irrespective of the date of contract. They contended that the expression 'sale agreement' used in Purbanchal Cables was not defined in the Act and was inconsistent with the earlier decisions of this Court in Assam Small Scale Industries Development Corporation Ltd. v. J.D. Pharmaceuticals, (2005) 13 SCC 19 and Modern Industries v. Steel Authority of India Ltd., (2010) 5 SCC 44, which had applied the 'transaction' and 'supply order' test. It was also submitted that the Act does not create a new right but only provides a higher rate of interest, and thus could apply to existing contracts. The respondents relied on Purbanchal Cables and argued that the right to statutory interest accrues only in respect of agreements entered into after the Act's commencement. The Supreme Court heard the arguments of learned senior counsel for both sides. The judgment extract is incomplete and does not contain the final decision.

Headnote

A) Civil Law - Applicability of Statute - Retroactive Operation - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 - The High Court Full Bench held that the Act applies to contracts entered into prior to 23.09.1992 and interest is payable from that date. The Supreme Court in Purbanchal Cables held that the Act applies only to sale agreements after its commencement. The present appeals challenge the correctness of Purbanchal Cables. (Paras 7-8, 13)

B) Civil Procedure - Maintainability of Suit - Suit for Interest Alone - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 - The High Court Full Bench answered in the affirmative that a suit for recovery of mere interest under the Act is maintainable. This position was not disturbed by the Division Bench. (Para 7)

C) Interpretation of Statutes - Beneficial Legislation - Purpose of Act - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 - The object of the Act is to ensure prompt payment to small scale industries and to provide for statutory interest on delayed payments. The appellants argued that the Act, being a beneficial legislation, should be given retroactive operation to cover existing transactions. (Paras 12, 14)

D) Precedent - Binding Effect - Conflicting Decisions - The appellants contended that the term 'sale agreement' used in Purbanchal Cables is inconsistent with earlier decisions in Assam Small Scale Industries Development Corporation Ltd. and Modern Industries, which applied the 'transaction' and 'supply order' test. It was urged that the legal test for applicability of the Act should be reconsidered. (Paras 11, 13-14)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 is applicable to supply contracts entered into prior to its enforcement date of 23.09.1992; Whether the test of 'sale agreement' adopted in Purbanchal Cables is correct; Whether a suit for recovery of mere interest under the Act is maintainable; Whether acceptance of belated payment without reservation extinguishes the right to claim interest under the Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Decision not clearly stated

Law Points

  • Legal points not extracted
  • Beneficial legislation
  • Retroactive operation
  • Supply order test
  • Sale agreement test
  • Maintainability of suit for interest alone
  • Pre-commencement contracts not covered as per Purbanchal Cables
Subscribe to unlock Law Points Subscribe Now

Case Details

2016 LawText (SC) (08) 303

CIVIL APPEAL NOS.8442-8443 OF 2016 (Arising out of SLP (C) Nos.9924-9925 of 2013) with C.A. No.8445/2016, C.A. No.8448/2016, C.A. No.8450/2016

2026-08-01

V. Gopala Gowda, J.

Citation not available

M.H. Baig, Basava Prabhu S. Patil, Ajit Kumar Sinha, Vijay Hansaria

M/s Shanti Conductors (P) Ltd. & Anr.

Assam State Electricity Board & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for recovery of interest under the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993

Remedy Sought

The appellants sought recovery of interest on delayed payments from the respondent Board

Filing Reason

The Board delayed payment for supplies made, and the appellants claimed statutory interest under the Act

Previous Decisions

Trial court decreed suit; High Court initially referred to Full Bench, which held Act applicable; but Division Bench reversed based on Purbanchal Cables

Issues

Whether the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 applies to contracts entered into prior to its enforcement on 23.09.1992 Whether the test of 'sale agreement' adopted in Purbanchal Cables is correct Whether a suit for recovery of mere interest under the Act is maintainable Whether acceptance of belated payment without reservation extinguishes the right to claim interest under the Act

Submissions/Arguments

Appellants argued that the Act is a beneficial legislation and should have retroactive operation to cover all outstanding payments irrespective of contract date; the 'sale agreement' test is inconsistent with earlier Supreme Court decisions that applied the 'transaction' and 'supply order' test; the Act only provides a higher rate of interest and does not create a new right Respondents relied on Purbanchal Cables and argued that the right to statutory interest accrues only in respect of agreements entered into after the Act's commencement

Ratio Decidendi

Ratio not explicitly mentioned

Judgment Excerpts

Whether the suit for recovery of mere interest under the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 is maintainable? Whether in the present case the suit for recovery of Interest under the Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 would not be maintainable as the contract for supply of goods between the parties was entered into prior to enforcement of the Act, i.e. on 23.09.1992? Whether the suit for recovery of interest under the Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 would not be maintainable if no reservation is made by the supplier retaining to it the right to recovery interest under the Act when the payment(s) of the principal sum is/are accepted, though these may be made beyond the prescribed period? Since the Act envisages that the supplier has an accrued right to claim a higher rate of interest in terms of the Act, the same can only be said to accrue for sale agreements after the date of commencement of the Act i.e. 23-9-1992 and not any time prior. The wholesome purpose and object behind the 1993 Act as amended in 1998 is to ensure that the buyer promptly pays the amount due towards the goods supplied or the services rendered by the supplier. It also provides for payment of interest statutorily on the outstanding money in case of default.

Procedural History

On 31.03.1992 and 13.05.1992, supply orders were placed by the respondent Board. The Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 came into force on 23.09.1992. Supplies were completed on 04.10.1993, and full payment was received on 05.03.1994. The appellants filed a suit for interest on 10.01.1997. The trial court decreed the suit on 02.02.2000. The Board appealed, and the High Court Division Bench on 18.10.2001 referred the matter to a Full Bench. The Full Bench on 05.03.2002 held that the Act applies to pre-commencement contracts and a suit for interest alone is maintainable. Subsequently, the Division Bench on 20.11.2012 set aside the trial court decree, relying on the Supreme Court's decision in Purbanchal Cables. The appellants then filed SLPs, which were converted to the present civil appeals.

Acts & Sections

  • Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993: 2(b)(ii)
  • Code of Civil Procedure, 1908: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Hears Civil Appeals Concerning Applicability of Interest on Delayed Payments Act to Prior Contracts. The appeals arise from a common question of law regarding the retrospective application of the Interest on Delayed Payment to Small Sca...
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Demolition Notice for Unauthorized Floors Constructed Without Approval. Court holds that occupants of illegally constructed floors cannot claim violation of natural justice when notices were served on ...