Supreme Court Quashes NCLT Approval and NCLAT Judgment in Bhushan Power CIRP, Remands for Fresh Resolution Plan. Approved Plan Set Aside Due to Inordinate Delay, Illegal Extension Clause, Waterfall Violation, and Non-Compliance with IBC Provisions Including Sections 30, 31, and 53.

In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court adjudicated a batch of civil appeals under Section 62 of the Insolvency and Bankruptcy Code, 2016 (IBC) challenging the approval of the Resolution Plan for Bhushan Power and Steel Limited (BPSL), a corporate debtor. The appeals were filed by erstwhile promoters and operational creditors against the judgment of the National Company Law Appellate Tribunal (NCLAT) dated 17 February 2020, which had largely upheld the plan approved by the Committee of Creditors (CoC) and sanctioned by the National Company Law Tribunal (NCLT) on 5 September 2019. JSW Steel Limited (JSW) was the successful resolution applicant (SRA). The Supreme Court quashed both the NCLT's approval order and the NCLAT's judgment, and remanded the matter for fresh resolution proceedings, holding that the plan suffered from multiple legal infirmities and had become unviable due to inordinate delay. The CIRP of BPSL commenced on 26 July 2017 after an application by Punjab National Bank under Section 7 of the IBC, following RBI's identification of BPSL as one of 12 major defaulters. The RP invited claims, and the CoC approved the consolidated resolution plan submitted by JSW on 10 October 2018. The RP filed the plan before the NCLT for approval on 14 February 2019. Several objections were raised by erstwhile promoters and operational creditors. The NCLT approved the plan on 5 September 2019 with certain conditions. JSW appealed some conditions before the NCLAT. Simultaneously, the Enforcement Directorate (ED) attached assets of BPSL under the PMLA. The NCLAT, by its impugned judgment dated 17 February 2020, partially allowed JSW's appeal, modified conditions, and dismissed all other appeals. The ED's appeal regarding attachment was disposed of separately by the Supreme Court on 11 December 2024, permitting JSW to take control of properties as restitution under PMLA. The Supreme Court addressed ten major legal issues. It held that erstwhile promoters have locus standi to challenge a resolution plan as their rights are affected. The CoC does not become functus officio upon plan approval by the NCLT but its role is limited to implementation and cannot include extending the timeline, which power lies exclusively with the NCLT under Section 31(3). The clause in the plan permitting the CoC to extend time was therefore illegal. The Court found that the plan's implementation was delayed by over six years due to litigation, rendering it unviable and against the time-bound objective of the IBC. The upfront payment of Rs. 100 crore by JSW to the CoC before plan approval violated the statutory waterfall mechanism under Section 53. EBITDA generated during CIRP belonged to the corporate debtor and had to be distributed as per priority, but the plan allowed JSW to retain it, which was impermissible. The plan failed to provide for contingent claims of Jaldhi Overseas and gave nil payment to pre-CIRP dues of operational creditors Medi and Darcl, violating Section 30(2)(b) and principles of equity. Consequently, the Court set aside the plan approval and ordered the CoC to return any monies received from JSW, and remanded the matter to the NCLT for fresh resolution process strictly in accordance with the IBC.

Headnote

A) Insolvency Law - Locus Standi - Erstwhile Promoters - Section 62, Insolvency and Bankruptcy Code, 2016 - The Court held that erstwhile promoters, though not creditors or shareholders during CIRP, are aggrieved persons whose rights are affected by the resolution plan and thus have locus standi to appeal. Held that NCLAT erred in denying standing, and promoters were entitled to challenge the plan on merits (Paras not mentioned).

B) Insolvency Law - Role of Committee of Creditors - CoC Post-Plan Approval - Insolvency and Bankruptcy Code, 2016 - The Court held that the CoC does not become functus officio upon NCLT approval but its role is limited to supervision and implementation; it cannot modify the plan or usurp NCLT's powers under Section 31(3) to extend time (Paras not mentioned).

C) Insolvency Law - Resolution Plan Implementation - Extension of Time - Section 31(3), Insolvency and Bankruptcy Code, 2016 - A clause permitting the CoC to extend the implementation period beyond 90 days was held illegal as the power to extend time vests exclusively with the NCLT. The clause was void and vitiated the plan (Paras not mentioned).

D) Insolvency Law - Delay in Implementation - Viability of Resolution Plan - Insolvency and Bankruptcy Code, 2016 - Inordinate delay of over six years in implementing the plan due to litigation rendered it unviable and frustrated the time-bound objective of the IBC, warranting quashing of approval (Paras not mentioned).

E) Insolvency Law - Upfront Payment to CoC - Waterfall Mechanism - Section 53, Insolvency and Bankruptcy Code, 2016 - Upfront payment of Rs. 100 crore by SRA to CoC before plan approval violated the statutory waterfall mechanism and Section 30(2), prejudicing operational creditors. Held that such payment was impermissible and plan approval based on it was illegal (Paras not mentioned).

F) Insolvency Law - Treatment of EBITDA - Asset of Corporate Debtor - Insolvency and Bankruptcy Code, 2016 - EBITDA generated during CIRP belongs to the corporate debtor and must be distributed as per the waterfall. The plan's provision allowing SRA to retain EBITDA was held illegal (Paras not mentioned).

G) Insolvency Law - Contingent Claims - Provision in Resolution Plan - Regulation 38(1)(c), IBBI (CIRP) Regulations, 2016 - Contingent claims must be recognized and provided for in the resolution plan; the failure to do so for Jaldhi's claim rendered the plan non-compliant (Paras not mentioned).

H) Insolvency Law - Pre-CIRP Dues of Operational Creditors - Section 30(2)(b), Insolvency and Bankruptcy Code, 2016 - Operational creditors are entitled to at least liquidation value of their claims. The plan's zero payment to Medi and Darcl while paying similar creditors violated the IBC and principles of equity (Paras not mentioned).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the resolution plan approved by the CoC and NCLT was valid, legal, and implemented in accordance with the Insolvency and Bankruptcy Code, 2016, including issues of locus standi, delay, contravention of statutory provisions, distribution of EBITDA, and treatment of contingent and operational claims

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals. The judgments and orders dated 2019-09-05 by NCLT and 2020-02-17 by NCLAT were quashed and set aside. The approval of the Resolution Plan submitted by JSW Steel Limited was set aside. The Committee of Creditors was directed to return the amount received from the SRA. The matter was remanded to the NCLT for fresh consideration of a resolution plan in accordance with the Insolvency and Bankruptcy Code, 2016.

Law Points

  • erstwhile promoters have locus standi to challenge resolution plan despite not being creditors
  • CoC does not become functus officio after plan approval by NCLT but its role is limited
  • clause in resolution plan allowing CoC to extend implementation period is illegal as it usurps NCLT's power under IBC
  • inordinate delay in implementation of resolution plan vitiates its viability and contravenes objective of IBC
  • upfront payment of Rs. 100 crore by SRA to CoC before plan approval is contrary to IBC's waterfall mechanism
  • EBITDA generated during CIRP must be treated as asset of corporate debtor and distributed as per waterfall
  • contingent claims cannot be rejected outright and must be provided for in resolution plan
  • pre-CIRP dues of operational creditors must be paid as per Section 30(2) of IBC
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (SC) (09) 116

CIVIL APPEAL NO. 1808 OF 2020, CIVIL APPEAL NO. 2192-2193 OF 2020, CIVIL APPEAL NO. 2225 OF 2020, CIVIL APPEAL NO. 3020 OF 2020, CIVIL APPEAL NO. 6390 OF 2021

2025-05-02

B.R. Gavai, CJI

2025 INSC 1165

Kalyani Transco, Jaldhi Overseas Pte. Limited, M/s. Medi Carrier Private Limited, CJ Darcl Logistics Limited

M/S Bhushan Power and Steel Limited and Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals under Section 62 of Insolvency and Bankruptcy Code, 2016 against NCLAT judgment approving resolution plan of corporate debtor Bhushan Power and Steel Limited

Remedy Sought

Appellants sought quashing of resolution plan approval and direction for fresh corporate insolvency resolution process

Filing Reason

Allegations of illegality in plan approval, inordinate delay, violation of statutory provisions, and adverse impact on creditors' rights

Previous Decisions

NCLT approved resolution plan with conditions on 2019-09-05; NCLAT modified conditions and dismissed appeals on 2020-02-17

Issues

Locus standi of erstwhile promoters to challenge resolution plan Existence and role of Committee of Creditors after plan approval by NCLT Legality of clause permitting CoC to extend implementation period Effect of inordinate delay on viability of resolution plan Contravention of law through upfront payment and EBITDA retention Treatment of contingent claims of Jaldhi Overseas Pre-CIRP dues of operational creditors Medi and Darcl

Submissions/Arguments

Erstwhile promoters argued they had locus standi as aggrieved persons; that CoC became functus officio after NCLT approval; plan clause allowing CoC to extend time was illegal; delay rendered plan unviable; upfront payment and EBITDA retention violated IBC waterfall; contingent claims ignored; operational creditors denied statutory minimum. Jaldhi Overseas contended its contingent claim was wrongly rejected and plan failed to provide for it, rendering plan non-compliant. Medi Carrier and CJ Darcl argued their pre-CIRP dues were not provided for in plan, violating Section 30(2)(b) and equitable treatment principle. Respondents including SRA-JSW and CoC defended plan approval, contending that erstwhile promoters had no locus; CoC retained limited role; extension clause was mere enabling provision; delay was due to litigation; upfront payment was in accordance with plan; EBITDA was part of SRA's upfront commitment; contingent claims not crystallized; operational creditors properly classified.

Ratio Decidendi

A resolution plan under the IBC must be implemented in a time-bound manner; inordinate delay renders it unviable. The CoC cannot exercise powers beyond those conferred by the Code, such as extending the implementation period, which is the NCLT's prerogative under Section 31(3). Upfront payments to creditors outside the statutory waterfall mechanism are impermissible. EBITDA generated during CIRP is an asset of the corporate debtor and must be distributed as per priority. Contingent claims cannot be ignored and must be provided for in the plan. Pre-CIRP dues of operational creditors must be paid at least the liquidation value as per Section 30(2)(b). Any plan that contravenes these principles is illegal and cannot be approved.

Judgment Excerpts

Section 32A of the IBC was inserted w.e.f. 28th December 2019 and it did not have retrospective effect. the Committee of Creditors would return the amount received by it from the SRA – JSW in case the appeals succeed

Procedural History

CIRP commenced on 2017-07-26 under Section 7 IBC. RP invited claims; JSW submitted resolution plan. CoC approved plan on 2018-10-10. RP filed for NCLT approval on 2019-02-14. NCLT approved plan with conditions on 2019-09-05. SRA-JSW and others filed appeals before NCLAT. NCLAT partly allowed SRA appeal and dismissed other appeals on 2020-02-17. Appellants filed civil appeals in Supreme Court. Supreme Court admitted appeals on 2020-03-06 and recorded CoC's undertaking to return SRA payment if appeals succeed. ED's appeal regarding attachment disposed of on 2024-12-11 permitting SRA to take control as restitution. Final judgment delivered on 2025-05-02 by Chief Justice B.R. Gavai quashing NCLT and NCLAT orders and remanding for fresh resolution.

Acts & Sections

  • Insolvency and Bankruptcy Code, 2016: 7, 30(2), 30(4), 30(6), 31(1), 31(3), 53, 61, 62, 32A
  • Indian Penal Code, 1860: 420, 468, 471, 477A, 120B
  • Prevention of Corruption Act, 1988: 13(1)(d), 13(2)
  • Prevention of Money Laundering Act, 2002: 5, 8(8)
  • Banking Regulation Act, 1949:
  • Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016: 38(1)(c), 39(4)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Quashes NCLT Approval and NCLAT Judgment in Bhushan Power CIRP, Remands for Fresh Resolution Plan. Approved Plan Set Aside Due to Inordinate Delay, Illegal Extension Clause, Waterfall Violation, and Non-Compliance with IBC Provisions In...
Related Judgement
High Court High Court of Bombay at Goa Dismisses Appeals in Succession Dispute Over Property of Deceased — Upholds Trial Court's Order for Status Quo and Appointment of Administrator. The court held that the trial court had jurisdiction to appoint an administ...