Madras High Court Partially Sets Aside Arbitral Award in Construction Contract Dispute — Upholds Refund of Withheld EPF/ESI Amounts but Remits Liquidated Damages Issue for Reconsideration. The court held that the rejection of liquidated damages claim was patently illegal under Section 34 of the Arbitration and Conciliation Act, 1996, while the award of refund of EPF/ESI deductions was not against public policy.

High Court: Madras High Court
  • 11
Judgement Image
Font size:
Print

Case Note & Summary

The judgment concerns two petitions under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 01.07.2019. The dispute arose from a construction contract between M/s.NRP Projects Pvt. Ltd. (contractor) and M/s.Chennai Petroleum Corporation Ltd. (employer). The contractor claimed various amounts for work done, refund of EPF/ESI deductions, and challenged liquidated damages imposed by the employer. The arbitrator awarded certain claims in favor of the contractor, including refund of EPF/ESI withheld amounts and part of liquidated damages deducted. Both parties filed petitions: the contractor sought to set aside the award regarding rejection of certain claims and liquidated damages, while the employer sought to set aside the award directing refund of EPF/ESI amounts and part of liquidated damages. The court examined the grounds of patent illegality and public policy. It held that the award of refund of EPF/ESI amounts was based on evidence and not patently illegal. However, the rejection of the employer's claim for liquidated damages on change order No.1 was found to be perverse and without proper reasoning, amounting to patent illegality. The court set aside that part of the award and remitted it to the arbitrator for fresh consideration. The court also upheld the interest rates awarded. The petitions were disposed of accordingly, with the employer's petition partly allowed and the contractor's petition dismissed.

Headnote

A) Arbitration - Section 34 Challenge - Public Policy - Patent Illegality - The court examined whether the arbitral award was liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality or being against public policy. The court held that the award of refund of EPF/ESI withheld amounts was not patently illegal as the arbitrator had considered the evidence. However, the rejection of liquidated damages was found to be perverse and remitted for reconsideration. (Paras 1-43)

B) Contract Law - Liquidated Damages - Change Order - The court considered the claim for liquidated damages on change order No.1. The arbitrator rejected the claim without proper reasoning. The court held that the rejection was patently illegal and remitted the issue to the arbitrator for fresh consideration. (Paras 20-30)

C) Interest - Rate of Interest - Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 - The court upheld the arbitrator's award of interest at 12.35% p.a. on the principal amount from the date of cause of action till the date of award and future interest at 14.35% p.a., finding no patent illegality. (Paras 31-35)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award suffers from patent illegality or is against public policy under Section 34 of the Arbitration and Conciliation Act, 1996, particularly regarding the award of refund of EPF/ESI withheld amounts and the rejection of liquidated damages claim.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court partly allowed O.P.No.110 of 2021 (employer's petition) by setting aside the part of the award rejecting the liquidated damages claim on change order No.1 and remitted it to the arbitrator for fresh consideration. The court dismissed O.P.No.810 of 2019 (contractor's petition). The interim application was disposed of.

Law Points

  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Public Policy
  • Patent Illegality
  • Liquidated Damages
  • EPF/ESI Deductions
  • Interest Rate
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:MHC:2

O.P.Nos.810 of 2019 & 110 of 2021 and A.No.399 of 2021

2026-01-02

N.ANAND VENKATESH

2026:MHC:2

M/s.NRP Projects Pvt. Ltd. (in O.P.No.810 of 2019) and Chennai Petroleum Corporation Ltd. (in O.P.No.110 of 2021)

M/s.Chennai Petroleum Corporation Ltd. (in O.P.No.810 of 2019) and M/s.NRP Projects Pvt. Ltd. (in O.P.No.110 of 2021)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petitions under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award.

Remedy Sought

The contractor sought to set aside the award rejecting certain claims and liquidated damages; the employer sought to set aside the award directing refund of EPF/ESI withheld amounts and part of liquidated damages.

Filing Reason

Dissatisfaction with the arbitral award dated 01.07.2019.

Previous Decisions

Arbitral award dated 01.07.2019 passed by the arbitral tribunal.

Issues

Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality or being against public policy. Whether the rejection of liquidated damages claim by the arbitrator was patently illegal. Whether the award of refund of EPF/ESI withheld amounts was against public policy.

Submissions/Arguments

The employer argued that the award of refund of EPF/ESI amounts was patently illegal as the contractor had not actually deposited the amounts. The contractor argued that the rejection of liquidated damages was perverse and without evidence.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, an award can be set aside if it is patently illegal or against public policy. The rejection of a claim without proper reasoning or ignoring material evidence amounts to patent illegality. However, the court should not reappreciate evidence unless the findings are perverse.

Judgment Excerpts

The rejection of the liquidated damages claim by the arbitrator is patently illegal and is set aside. The award of refund of EPF/ESI amounts is based on evidence and does not suffer from patent illegality.

Procedural History

The dispute was referred to arbitration. The arbitral tribunal passed an award on 01.07.2019. Both parties filed petitions under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award. The court heard the petitions and delivered judgment on 02.01.2026.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Madras High Court Partially Sets Aside Arbitral Award in Construction Contract Dispute — Upholds Refund of Withheld EPF/ESI Amounts but Remits Liquidated Damages Issue for Reconsideration. The court held that the rejection of liquidated damages cla...
Related Judgement
High Court Bombay High Court Dismisses Revenue's Appeal in Income Tax TDS Case — Wheeling and Transmission Charges Not Rent Under Section 194I. Payments for Use of Transmission Lines Held Not Rent as No Transfer of Possession or Right to Use Occurs.