Madras High Court Allows Appeal in RERA Case for Delay in Possession — Promoter Liable for Interest Under Section 18 of RERA Act, 2016. The court restored the order of TN RERA directing the promoter to pay interest for delay in handing over possession of flat and club house facilities.

High Court: Madras High Court In Favour of Accused
  • 133
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, a retired General Manager of Bharat Petroleum Corporation Limited, entered into a Memorandum of Agreement on 30.07.2011 with the respondent promoter, M/s. Akshaya Pvt. Ltd., for the purchase of a residential flat in the project 'January' at Thaiyur Village, Chengalpet Taluk. The total cost was Rs.46,38,000/-. As per the agreement, possession was to be delivered within 30 months with a 90-day grace period from the date of sanction, i.e., by 30.04.2014. However, the promoter handed over possession of the flat only on 24.02.2018, a delay of nearly 4 years, and the club house facilities were handed over on 26.01.2021, a delay of 7 years. Aggrieved by the delay, the appellant filed a complaint before the Tamil Nadu Real Estate Regulatory Authority (TN RERA) in CCP No.30 of 2020. TN RERA, by order dated 30.03.2020, directed the promoter to pay interest for the delay. The promoter appealed to the Tamil Nadu Real Estate Appellate Tribunal (TNREAT), which reversed the order on 07.03.2022. The appellant then filed the present Civil Miscellaneous Second Appeal under Section 58 of the TNRERA Act read with Section 100 CPC. The High Court framed substantial questions of law regarding the liability of the promoter for delay under Section 18 of the RERA Act and the correctness of the Appellate Tribunal's order. The court analyzed the provisions of the RERA Act, particularly Section 18 which imposes liability on the promoter for delay in possession, and Section 19(4) which allows the allottee to withdraw. The court noted that the promoter did not provide any valid reason for the delay, such as force majeure. The court held that the Appellate Tribunal erred in reversing the TN RERA order, as the promoter was clearly liable for the delay. The court restored the TN RERA order, directing the promoter to pay interest at the prescribed rate for the period of delay. The appeal was allowed with costs.

Headnote

A) Real Estate Law - Delay in Possession - Interest Liability - Section 18 of Real Estate (Regulation and Development) Act, 2016 - The appellant allottee entered into an agreement with the respondent promoter for purchase of a flat, with possession to be delivered by 30.04.2014. The promoter handed over possession of the flat on 24.02.2018 and club house facilities on 26.01.2021, causing delays of nearly 4 years and 7 years respectively. The Tamil Nadu Real Estate Regulatory Authority (TN RERA) directed the promoter to pay interest for the delay. The Appellate Tribunal reversed this order. The High Court held that the promoter is liable to pay interest under Section 18 of the RERA Act for the delay in handing over possession, as the delay was not due to force majeure or any valid reason. The court restored the order of TN RERA. (Paras 2-10, 15-20)

B) Real Estate Law - Withdrawal by Allottee - Right to Interest - Section 19(4) of Real Estate (Regulation and Development) Act, 2016 - The allottee had the option to withdraw from the project due to the delay and claim interest. The court noted that the allottee did not withdraw but continued with the agreement. However, the promoter's liability for delay remains under Section 18. The court clarified that the allottee is entitled to interest for the period of delay even if he did not withdraw. (Paras 12-14)

C) Civil Procedure - Appeal under RERA - Scope of Second Appeal - Section 58 of Tamil Nadu Real Estate (Regulation and Development) Act, 2017 read with Section 100 of Code of Civil Procedure, 1908 - The appeal before the High Court is a second appeal under Section 58 of the TNRERA Act, which is akin to a second appeal under Section 100 CPC. The court can interfere only if there is a substantial question of law. The court found that the Appellate Tribunal's order was perverse and raised substantial questions of law regarding the interpretation of Section 18 and the liability for delay. (Paras 1, 15-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Tamil Nadu Real Estate Appellate Tribunal erred in reversing the order of the Tamil Nadu Real Estate Regulatory Authority which had directed the promoter to pay interest for delay in handing over possession of the flat and club house facilities.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is allowed. The order of the Tamil Nadu Real Estate Appellate Tribunal dated 07.03.2022 in Appeal No.103 of 2021 is set aside. The order of the Tamil Nadu Real Estate Regulatory Authority dated 30.03.2020 in CCP No.30 of 2020 is restored. The respondent promoter is directed to pay interest for the delay in handing over possession as per the TN RERA order. No costs. Connected miscellaneous petitions are closed.

Law Points

  • Section 18 of RERA Act
  • 2016 imposes liability on promoter for delay in possession
  • Section 19(4) of RERA Act
  • 2016 allows allottee to withdraw without interest
  • Section 38 of RERA Act
  • 2016 provides for interest on delayed payments
  • Section 100 CPC applicability to appeals under Section 58 of TNRERA Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (MAD) (01) 246

C.M.S.A.No.41 of 2022 and C.M.P.Nos.9256 of 2022

2025-01-10

J.Nisha Banu, R.Sakthivel

Mr.C.K.Chandrasekar for Mrs.W.R.Subhashini (for appellant), Mr.Mani Sundaragopal (for respondent)

P.Anandasundaresan

M/s.Akshaya Pvt. Ltd. Rep. by its Director, Mr.J.Ravi

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil Miscellaneous Second Appeal under Section 58 of TNRERA Act, 2017 read with Section 100 CPC against order of Tamil Nadu Real Estate Appellate Tribunal

Remedy Sought

Appellant sought restoration of TN RERA order directing respondent promoter to pay interest for delay in handing over possession of flat and club house facilities

Filing Reason

Delay of nearly 4 years in handing over possession of flat and 7 years in handing over club house facilities by the promoter

Previous Decisions

TN RERA (CCP No.30 of 2020) directed promoter to pay interest on 30.03.2020; TNREAT (Appeal No.103 of 2021) reversed that order on 07.03.2022

Issues

Whether the promoter is liable to pay interest under Section 18 of RERA Act for delay in handing over possession of the flat and club house facilities? Whether the Tamil Nadu Real Estate Appellate Tribunal erred in reversing the order of TN RERA?

Submissions/Arguments

Appellant argued that the promoter delayed possession by 4 years for flat and 7 years for club house, and is liable for interest under Section 18 of RERA Act. Respondent argued that the delay was due to various reasons and that the allottee did not withdraw from the project, so no interest is payable.

Ratio Decidendi

Under Section 18 of the Real Estate (Regulation and Development) Act, 2016, a promoter is liable to pay interest to the allottee for any delay in handing over possession of the property, unless the delay is due to force majeure or other valid reasons. The allottee's option to withdraw under Section 19(4) does not absolve the promoter of liability for delay. The Appellate Tribunal's reversal of the TN RERA order was erroneous as the promoter failed to justify the delay.

Judgment Excerpts

The appellant has approached this Court under Section 58 of the Real Estate (Regulation and Development) Act, read with Section 100 of the Civil Procedure Code against the order of the Tamil Nadu Real Estate Appellate Tribunal... The respondent/ Promoter has to complete the construction and deliver the flat at least, on or before 30th April 2014. But the respondent / Promoter handed over the keys of the flat only on 24.02.2018... Therefore, the respondent/ Promoter has handed over the possession of the flat with a long delay of nearly 4 years...

Procedural History

The appellant filed a complaint before TN RERA (CCP No.30 of 2020) which was allowed on 30.03.2020 directing the promoter to pay interest. The promoter appealed to TNREAT (Appeal No.103 of 2021) which reversed the order on 07.03.2022. The appellant then filed the present Civil Miscellaneous Second Appeal before the Madras High Court under Section 58 of TNRERA Act read with Section 100 CPC.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18, Section 19(4), Section 38
  • Tamil Nadu Real Estate (Regulation and Development) Act, 2017: Section 58
  • Code of Civil Procedure, 1908: Section 100
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Parole to Life Convict Despite Police Objection Based on Past Good Conduct. The court held that parole is a statutory right and rejection based on vague apprehension of absconding without material is unsustainable under Rule ...
Related Judgement
Supreme Court Supreme Court Allows Appeal in Family Settlement Dispute — Upholds Validity of Pre-Emptive Right Clause. Clause requiring written concurrence of all co-sharers before sale to third party is valid and binding; High Court erred in holding it vague an...