Bombay High Court Allows Arbitration Petition Challenging Arbitral Award in Excise Duty Reimbursement Dispute. Contractual interpretation of purchase order clause for reimbursement of excise duty paid by contractor to Railways.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 201
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, M/s Creative Engineers, filed an arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award passed by a Sole Arbitrator (Deputy Chief Engineer, Planning, Western Railway) in a dispute arising from a contract for manufacture and supply of Glued Insulated Rail Joints to the Respondent, Union of India through the General Manager, Western Railway. The purchase order placed by the Respondent on the Petitioner stated that no excise duty was payable at the time of the order, but if any duty became applicable by the time of dispatch, it would be reimbursed by the Respondent subject to production of documentary evidence of payment. The purchase order also specified that excise duty would be considered as 16% and any variation due to increase in turnover was not applicable. The Petitioner supplied the rail joints and paid excise duty of Rs.8,07,340/-, producing a certificate dated 16 October 2003 from the Superintendent, Central Excise, Range III, Kota (Rajasthan) as documentary proof. The Respondent reimbursed Rs.3,66,336/- in March 2003, leaving a balance of Rs.4,41,004/-. The Respondent contested the claim for the balance, leading to disputes referred to arbitration. The Arbitrator rejected the Petitioner's claim, holding that the certificate produced was not a proper document as required under the purchase order. The High Court examined the purchase order clause and found that the certificate from the Superintendent of Central Excise was sufficient documentary evidence of payment of excise duty. The Court held that the Arbitrator's interpretation was patently illegal and contrary to the terms of the contract, as the purchase order did not specify any particular form of documentary evidence. The Court set aside the impugned award and directed the Respondent to pay the balance amount of Rs.4,41,004/- to the Petitioner with interest at 9% per annum from the date of the award until payment.

Headnote

A) Arbitration - Section 34 Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Reimbursement of Excise Duty - The dispute pertained to reimbursement of excise duty paid by the contractor for supply of rail joints to the Railways. The purchase order provided for reimbursement subject to production of documentary evidence of payment. The Arbitrator rejected the claim holding that the certificate from the Superintendent of Central Excise was not a proper document. The High Court held that the certificate was sufficient documentary evidence and the Arbitrator's interpretation was patently illegal and contrary to the terms of the contract. The award was set aside and the claim for balance excise duty was allowed. (Paras 1-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitrator erred in rejecting the Petitioner's claim for reimbursement of excise duty paid on the ground that the certificate produced was not a proper document as required under the purchase order.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court allowed the arbitration petition, set aside the impugned award, and directed the Respondent to pay the Petitioner the balance amount of Rs.4,41,004/- with interest at 9% per annum from the date of the award until payment.

Law Points

  • Contractual interpretation
  • Reimbursement of excise duty
  • Arbitral award
  • Section 34 Arbitration and Conciliation Act
  • 1996
  • Purchase order terms
  • Documentary evidence
Subscribe to unlock Law Points Subscribe Now

Case Details

2018 LawText (BOM) (11) 103

Arbitration Petition No.610 of 2016

2018-11-29

S.C. Gupte, J.

2018:BHC-OS:17797

Mr. Kamlesh Sukhwani a/w Mr. Paras Sukhwani I/b Ms. Suvarna Joshi for the Petitioner, Mr. Suresh Kumar a/w Ms. Mohinee Chougule for the Respondent

M/s Creative Engineers

Union of India through The General Manager, Western Railway

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

The Petitioner sought setting aside of the arbitral award and reimbursement of balance excise duty of Rs.4,41,004/-.

Filing Reason

The Arbitrator rejected the Petitioner's claim for reimbursement of excise duty paid, holding that the certificate produced was not a proper document as required under the purchase order.

Previous Decisions

The Arbitrator passed an award rejecting the Petitioner's claim for balance excise duty.

Issues

Whether the certificate from the Superintendent of Central Excise constituted sufficient documentary evidence of payment of excise duty under the purchase order. Whether the Arbitrator's interpretation of the purchase order clause was patently illegal and contrary to the terms of the contract.

Submissions/Arguments

The Petitioner argued that the certificate from the Superintendent of Central Excise was proper documentary evidence of payment of excise duty and the Arbitrator erred in rejecting it. The Respondent contended that the certificate was not a proper document as required under the purchase order and the Arbitrator's award was correct.

Ratio Decidendi

The purchase order did not specify any particular form of documentary evidence for reimbursement of excise duty. The certificate from the Superintendent of Central Excise was sufficient documentary evidence of payment. The Arbitrator's interpretation that the certificate was not a proper document was patently illegal and contrary to the terms of the contract, warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

The purchase order provided that, as of that date, no excise duty was payable on the goods, but if any duty became applicable by the time of the dispatch, the same would be reimbursed by the Respondent, subject to production of documentary evidence of payment of such duty. The certificate issued by the Superintendent, Central Excise, Range III, Kota (Rajasthan) dated 16 October 2003 was sufficient documentary evidence of payment of excise duty.

Procedural History

The Petitioner supplied rail joints and paid excise duty. The Respondent reimbursed part of the duty. Disputes arose regarding the balance. The matter was referred to a Sole Arbitrator (Deputy Chief Engineer, Planning, Western Railway) who rejected the claim. The Petitioner then filed Arbitration Petition No.610 of 2016 under Section 34 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Writ Petition Challenging Sub-Divisional Officer's Revision Order for Lack of Jurisdiction Under Mamlatdars' Courts Act, 1906. Sub-Divisional Officer Not Authorized to Exercise Revisional Powers Under Section 23(2) of the Act...
Related Judgement
Supreme Court Supreme Court Upholds Detention in Jammu and Kashmir Preventive Detention Act Case Due to Valid Non-Disclosure of Grounds in State Security Interest. Article 35(c) Modification Did Not Affect Detenu's Right to Move Supreme Court Under Article 32, and...