Case Note & Summary
The Petitioner, M/s Creative Engineers, filed an arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award passed by a Sole Arbitrator (Deputy Chief Engineer, Planning, Western Railway) in a dispute arising from a contract for manufacture and supply of Glued Insulated Rail Joints to the Respondent, Union of India through the General Manager, Western Railway. The purchase order placed by the Respondent on the Petitioner stated that no excise duty was payable at the time of the order, but if any duty became applicable by the time of dispatch, it would be reimbursed by the Respondent subject to production of documentary evidence of payment. The purchase order also specified that excise duty would be considered as 16% and any variation due to increase in turnover was not applicable. The Petitioner supplied the rail joints and paid excise duty of Rs.8,07,340/-, producing a certificate dated 16 October 2003 from the Superintendent, Central Excise, Range III, Kota (Rajasthan) as documentary proof. The Respondent reimbursed Rs.3,66,336/- in March 2003, leaving a balance of Rs.4,41,004/-. The Respondent contested the claim for the balance, leading to disputes referred to arbitration. The Arbitrator rejected the Petitioner's claim, holding that the certificate produced was not a proper document as required under the purchase order. The High Court examined the purchase order clause and found that the certificate from the Superintendent of Central Excise was sufficient documentary evidence of payment of excise duty. The Court held that the Arbitrator's interpretation was patently illegal and contrary to the terms of the contract, as the purchase order did not specify any particular form of documentary evidence. The Court set aside the impugned award and directed the Respondent to pay the balance amount of Rs.4,41,004/- to the Petitioner with interest at 9% per annum from the date of the award until payment.
Headnote
A) Arbitration - Section 34 Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Reimbursement of Excise Duty - The dispute pertained to reimbursement of excise duty paid by the contractor for supply of rail joints to the Railways. The purchase order provided for reimbursement subject to production of documentary evidence of payment. The Arbitrator rejected the claim holding that the certificate from the Superintendent of Central Excise was not a proper document. The High Court held that the certificate was sufficient documentary evidence and the Arbitrator's interpretation was patently illegal and contrary to the terms of the contract. The award was set aside and the claim for balance excise duty was allowed. (Paras 1-6)
Issue of Consideration
Whether the Arbitrator erred in rejecting the Petitioner's claim for reimbursement of excise duty paid on the ground that the certificate produced was not a proper document as required under the purchase order.
Final Decision
The High Court allowed the arbitration petition, set aside the impugned award, and directed the Respondent to pay the Petitioner the balance amount of Rs.4,41,004/- with interest at 9% per annum from the date of the award until payment.
Law Points
- Contractual interpretation
- Reimbursement of excise duty
- Arbitral award
- Section 34 Arbitration and Conciliation Act
- 1996
- Purchase order terms
- Documentary evidence


