Bombay High Court Quashes Blacklisting of Supplier by Central Bank of India for Non-Supply Due to Force Majeure. Natural Calamity in Thailand Constitutes Force Majeure Excusing Performance Under Contract Law Principles.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s. Acer India (Pvt.) Ltd., a private limited company engaged in supplying computer software and hardware, challenged its blacklisting by respondent No. 1, Central Bank of India, and the consequential blacklisting by respondent No. 2. In March 2011, respondent No. 1 invited bids for a Rate Contract for desktops, laptops, printers, scanners, etc. The petitioner participated and was empanelled by a letter dated 28 June 2011. Pursuant to this, various purchase orders were placed, and the supply process ran smoothly until 30 November 2011. In December 2011, unprecedented floods in Thailand, a key supplier of components to the IT industry, disrupted the global supply chain. The petitioner informed respondent No. 1 about the force majeure situation and its inability to supply goods at the same rates. A meeting was held on 15 December 2011, and the petitioner submitted a proposal for revised rates on 20 December 2011. However, by a communication dated 24 December 2011, respondent No. 1 rejected the request, threatened to cancel the purchase order, and blacklist the petitioner if it did not confirm delivery within 24 hours. The petitioner could not comply, and respondent No. 1 blacklisted the petitioner without any prior notice or opportunity of hearing. The petitioner filed a writ petition challenging the blacklisting. The court framed the issues of whether the blacklisting without hearing violated natural justice and whether the floods constituted force majeure. The petitioner argued that the blacklisting was arbitrary and without jurisdiction, while the respondents contended that the petitioner had failed to perform its contractual obligations. The court analyzed that blacklisting has serious civil consequences and must be preceded by a notice and hearing. It also held that the floods in Thailand were a force majeure event beyond the petitioner's control, excusing its non-performance. The court quashed the blacklisting orders, holding them violative of natural justice and disproportionate.

Headnote

A) Administrative Law - Blacklisting - Natural Justice - Blacklisting of a contractor without prior notice or opportunity of hearing is arbitrary and violative of principles of natural justice - The court held that blacklisting has serious civil consequences and cannot be imposed without giving the affected party a chance to be heard (Paras 10-12).

B) Contract Law - Force Majeure - Excuse for Non-Performance - Unprecedented floods in Thailand disrupting global supply chain of IT hardware constitute a force majeure event - The court held that the petitioner's inability to supply goods at the contracted rates due to the floods was beyond its control and thus excusable (Paras 5-7).

C) Administrative Law - Proportionality - Doctrine of Proportionality - Blacklisting must be proportionate to the alleged default - The court held that even if there was a breach, blacklisting the petitioner without considering the force majeure circumstances was disproportionate (Para 13).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the blacklisting of the petitioner by respondent No. 1 without affording an opportunity of hearing is sustainable in law, and whether the floods in Thailand constitute a force majeure event excusing the petitioner's failure to supply goods at the contracted rates.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the writ petition, quashed the blacklisting orders, and directed the respondents to restore the petitioner's empanelment status. Rule made absolute.

Law Points

  • Blacklisting without hearing violates natural justice
  • Force majeure excuses non-performance
  • Doctrine of proportionality in administrative action
Subscribe to unlock Law Points Subscribe Now

Case Details

2018 LawText (BOM) (07) 105

WRIT PETITION NO. 2909 OF 2017

2018-07-06

RANJIT MORE, SMT. SADHANA S. JADHAV

Mr. Janak Dwarkadas, Senior counsel a/w. Ms. Rishika Harish I/b. Mr. Nilesh Prataprai Parekh for petitioner; Mrs. Rathina Maravarman for respondent No. 1; Mr. Vakul Sharma I/b. Rajlaxmi Punjabi for respondent No. 2; Mr. Prashant Pandurang Jadhav for respondent No. 3

M/s. Acer India (Pvt.) Ltd.

Central Bank of India & ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging blacklisting of petitioner by respondent bank and consequential blacklisting by another respondent.

Remedy Sought

Petitioner sought quashing of blacklisting orders and restoration of its empanelment status.

Filing Reason

Petitioner was blacklisted without prior notice or opportunity of hearing after it failed to supply goods at contracted rates due to floods in Thailand (force majeure).

Issues

Whether the blacklisting of the petitioner without affording an opportunity of hearing is sustainable in law? Whether the floods in Thailand constitute a force majeure event excusing the petitioner's failure to supply goods at the contracted rates?

Submissions/Arguments

Petitioner argued that blacklisting without hearing violates principles of natural justice and that the floods in Thailand were a force majeure event beyond its control. Respondents argued that the petitioner failed to perform its contractual obligations and that the blacklisting was justified.

Ratio Decidendi

Blacklisting of a contractor without affording an opportunity of hearing is arbitrary and violative of principles of natural justice. Additionally, unprecedented floods in Thailand disrupting the global supply chain constitute a force majeure event excusing the petitioner's non-performance. The blacklisting was also disproportionate to the alleged default.

Judgment Excerpts

The Petitioner has approached this Court by way of writ jurisdiction, thereby challenging the blacklisting of the petitioner's company by respondent No. 1 and as consequence of the same, by respondent No. 2. In December, 2011, there were unprecedented floods in Thailand, thereby disturbing the economic infrastructure of the company. The petitioner had informed respondent No. 1 about the effect of force majeure and had further informed that in the given circumstances it was not possible to supply goods at the same rate as per the Rate Contract.

Procedural History

The petitioner filed Writ Petition No. 2909 of 2017 before the Bombay High Court challenging the blacklisting. The court heard the parties and reserved judgment on May 3, 2018, pronouncing it on July 6, 2018.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Upholds Reinstatement of Employee in Retrenchment Case for Non-Compliance with Section 25F of Industrial Disputes Act. Finding of 240 days continuous service based on salary vouchers and attendance register held to be a question of ...
Related Judgement
High Court Bombay High Court Quashes Blacklisting of Supplier by Central Bank of India for Non-Supply Due to Force Majeure. Natural Calamity in Thailand Constitutes Force Majeure Excusing Performance Under Contract Law Principles.