Case Note & Summary
The petitioner, M/s. Acer India (Pvt.) Ltd., a private limited company engaged in supplying computer software and hardware, challenged its blacklisting by respondent No. 1, Central Bank of India, and the consequential blacklisting by respondent No. 2. In March 2011, respondent No. 1 invited bids for a Rate Contract for desktops, laptops, printers, scanners, etc. The petitioner participated and was empanelled by a letter dated 28 June 2011. Pursuant to this, various purchase orders were placed, and the supply process ran smoothly until 30 November 2011. In December 2011, unprecedented floods in Thailand, a key supplier of components to the IT industry, disrupted the global supply chain. The petitioner informed respondent No. 1 about the force majeure situation and its inability to supply goods at the same rates. A meeting was held on 15 December 2011, and the petitioner submitted a proposal for revised rates on 20 December 2011. However, by a communication dated 24 December 2011, respondent No. 1 rejected the request, threatened to cancel the purchase order, and blacklist the petitioner if it did not confirm delivery within 24 hours. The petitioner could not comply, and respondent No. 1 blacklisted the petitioner without any prior notice or opportunity of hearing. The petitioner filed a writ petition challenging the blacklisting. The court framed the issues of whether the blacklisting without hearing violated natural justice and whether the floods constituted force majeure. The petitioner argued that the blacklisting was arbitrary and without jurisdiction, while the respondents contended that the petitioner had failed to perform its contractual obligations. The court analyzed that blacklisting has serious civil consequences and must be preceded by a notice and hearing. It also held that the floods in Thailand were a force majeure event beyond the petitioner's control, excusing its non-performance. The court quashed the blacklisting orders, holding them violative of natural justice and disproportionate.
Headnote
A) Administrative Law - Blacklisting - Natural Justice - Blacklisting of a contractor without prior notice or opportunity of hearing is arbitrary and violative of principles of natural justice - The court held that blacklisting has serious civil consequences and cannot be imposed without giving the affected party a chance to be heard (Paras 10-12). B) Contract Law - Force Majeure - Excuse for Non-Performance - Unprecedented floods in Thailand disrupting global supply chain of IT hardware constitute a force majeure event - The court held that the petitioner's inability to supply goods at the contracted rates due to the floods was beyond its control and thus excusable (Paras 5-7). C) Administrative Law - Proportionality - Doctrine of Proportionality - Blacklisting must be proportionate to the alleged default - The court held that even if there was a breach, blacklisting the petitioner without considering the force majeure circumstances was disproportionate (Para 13).
Issue of Consideration
Whether the blacklisting of the petitioner by respondent No. 1 without affording an opportunity of hearing is sustainable in law, and whether the floods in Thailand constitute a force majeure event excusing the petitioner's failure to supply goods at the contracted rates.
Final Decision
The court allowed the writ petition, quashed the blacklisting orders, and directed the respondents to restore the petitioner's empanelment status. Rule made absolute.
Law Points
- Blacklisting without hearing violates natural justice
- Force majeure excuses non-performance
- Doctrine of proportionality in administrative action





