Bombay High Court Dismisses Employer's Challenge to Arbitral Award in Construction Contract Dispute; Upholds Legal Successor's Right to Enforce Arbitration Agreement. Non-Consent to Assignment by Employer Does Not Extinguish Original Contractor's Rights; Limitation Period Held Not Barred Due to Continuing Proceedings Under Contract's Dispute Resolution Mechanism.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a construction contract for the Bombay Sewage Project awarded by the Municipal Corporation of Greater Mumbai (MCGM) to a German contractor, Dyckerhoff & Widmann AG (D&W), in 1995, with World Bank funding. After work completion in March 2001, D&W merged with Walter BauAG (WB), another German entity, and later filed for insolvency. D&W had earlier transferred its non-European contracts to its subsidiary Dywidag under a contribution agreement contingent on MCGM's consent, which was never given. Consequently, Dywidag acted on behalf of WB in pursuing claims. The contractor submitted a draft final statement in 2009 and initiated arbitration in 2010. The arbitral tribunal passed an award in 2013 in favor of the contractor, awarding INR 20.42 crores and DM 6.71 lakhs plus interest and costs. MCGM challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, on grounds of lack of jurisdiction (no arbitration agreement with WB) and limitation. The High Court held that the arbitration clause was assignable and followed the contract; since the assignment to Dywidag was contingent on MCGM's consent and consent was refused, the assignment failed, leaving D&W bound and entitled, and WB as its legal successor could enforce the arbitration agreement. On limitation, the court upheld the tribunal's finding that the contract's dispute resolution clauses (60.9-60.14) kept all rights and obligations open until resolution of all disputes, which never occurred, and the parties had waived time limits. The court found no ground to interfere under Section 34 and dismissed the petition, confirming the award.

Headnote

A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to Arbitral Award - Jurisdiction of Arbitral Tribunal - Legal Succession and Assignment - Held that where an assignment of a contract is contingent upon consent of the employer and such consent is not given, the assignment fails, and the original contractor remains entitled to enforce the contract and arbitration agreement; its legal successor can invoke arbitration (Paras 4-7).

B) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to Arbitral Award - Limitation - Contractual Dispute Resolution - Held that the arbitral tribunal's finding that the claims were not time-barred due to continuing contractual procedure and waiver of time limits by parties is a plausible interpretation and does not warrant interference under Section 34 (Para 8).

C) Arbitration and Conciliation Act, 1996 - Section 34 - Scope of Interference - Held that under Section 34, the court does not sit as an appellate court over the arbitral tribunal; it cannot reappreciate evidence or substitute its own interpretation of contractual clauses if the tribunal's view is plausible (Paras 6-8).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

1. Whether there was an arbitration agreement between the Petitioner and the Respondent, and hence whether the arbitral tribunal had jurisdiction. 2. Whether the claims in the arbitration were barred by limitation.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Arbitration Petition was dismissed. The court held that the arbitral tribunal correctly found that WB was the legal successor of D&W and entitled to invoke the arbitration clause, as the assignment to Dywidag was ineffective due to lack of consent. On limitation, the court upheld the tribunal's finding that the contractual mechanism kept the claims alive, and the limitation bar did not apply. The impugned award was confirmed.

Law Points

  • An arbitration clause is assignable along with the contract
  • if assignment is contingent on third party consent and consent not given
  • original contractor remains bound and entitled
  • legal succession of a company is determined by law of its domicile
  • contractual dispute resolution mechanism may extend limitation period by agreement of parties
  • limitation is not triggered until final determination of disputes under the contract's procedure
  • under Section 34
  • court does not interfere with plausible findings of the arbitral tribunal
Subscribe to unlock Law Points Subscribe Now

Case Details

2017 LawText (BOM) (10) 51

Arbitration Petition No. 433 of 2014

2017-10-31

S.C. Gupte, J.

2017:BHC-OS:13206

Kevic Setalvad, Anupam Surve, R.Y. Sirsikar, Zal Andhyarujina, Hursh Meghani, Javed Gaya, Vidya Chaudhari

Municipal Corporation of Greater Mumbai

Walter BauAG (IL)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Setting aside of the arbitral award dated 6 August 2013 which awarded the respondent contractor INR 20,42,24,167/- and DM 6,71,465/- with interest and costs.

Filing Reason

Petitioner contended that the arbitral tribunal lacked jurisdiction because there was no arbitration agreement between petitioner and respondent (the legal successor of original contractor) and that the claims were time-barred.

Previous Decisions

The present arbitration reference resulted in the impugned award which was the first decision in this proceeding; an earlier separate arbitration award between the same parties (on other disputes) had been set aside by a Single Judge of this court under Section 34, and that order is under appeal.

Issues

Whether there was an arbitration agreement between Petitioner and Respondent, and consequently, whether the arbitral tribunal had jurisdiction to adjudicate the disputes. Whether the claims raised by the Respondent in the arbitration were barred by limitation.

Submissions/Arguments

The Petitioner argued that the contract originally with D&W was assigned to Dywidag, and therefore WB (as successor of D&W) had no right to invoke the arbitration clause; the tribunal lacked jurisdiction. The Petitioner argued that the claims were time-barred because the taking-over and defects liability certificates were issued in 2001 and 2003, and the draft final statement was submitted only in 2009, well beyond the contractual period.

Ratio Decidendi

An arbitration clause is assignable and follows the contract; if assignment is contingent on consent of a third party and consent is not given, the assignment fails and original contractor remains entitled; legal succession determined by law of domicile grants successor the right to enforce arbitration; limitation is governed by contractual dispute resolution mechanism and can be extended by conduct of parties; under Section 34, court does not interfere with plausible findings of arbitral tribunal.

Judgment Excerpts

Any arbitration clause is in its nature assignable. If the underlying contract can be, and stands, assigned, there is no reason why an arbitration agreement forming part of it cannot or would not. The assignment was, thus, a contingent contract so far as the present contract is concerned. The contingency clearly failed, since the consent of the Employer never came, and the assignment, thus, could not take effect. It is the Petitioner's own case that it never gave its consent to the assignment of the contract by D&W to Dywidag; the legal effect would, therefore, be that the contract remained with D&W and its ownership was never transferred to Dywidag. Subclauses 60.9 to 60.14 of the contract, which bear on the subject, imply that the agreement between the parties was to keep open all rights and obligations under the contract till a stage was reached where all disputes were resolved and settled; the documents produced before the tribunal showed that that stage was never reached.

Procedural History

Contract awarded in 1995; work completed on 30 March 2001; D&W merged with WB on 17 May 2001; disputes arose leading to a first arbitration reference that resulted in an award set aside under Section 34 (appeal pending); second arbitration reference initiated in 2010 after draft final statement in 2009; impugned award passed on 6 August 2013; present petition filed in 2014 and dismissed on 31 October 2017.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Employer's Challenge to Arbitral Award in Construction Contract Dispute; Upholds Legal Successor's Right to Enforce Arbitration Agreement. Non-Consent to Assignment by Employer Does Not Extinguish Original Contractor's Rig...
Related Judgement
High Court Bombay High Court Dismisses Insurance Company's Appeal in Motor Accident Claim. Insurer's Liability to Third Parties Not Affected by Violation of Permit Conditions Under Section 149(2) of Motor Vehicles Act, 1988.