Case Note & Summary
The petitioners, M/s. Platinum Realty and M/s. Jaihind SRA Cooperative Society (Proposed), filed a writ petition challenging the decision of the Slum Rehabilitation Authority (SRA) to cancel the Letter of Intent (LoI) granted to them for a slum rehabilitation project in Chembur, Mumbai. The project involved redevelopment of a slum area under the Slum Rehabilitation Scheme. The SRA had issued an LoI to the petitioners on certain conditions, including obtaining consent of 70% of the slum dwellers and completing the rehabilitation within a stipulated time. The petitioners failed to comply with these conditions, leading to the SRA issuing a show-cause notice and eventually cancelling the LoI. The petitioners argued that the cancellation was arbitrary and violated principles of natural justice. The court examined the facts and found that the petitioners had not obtained the requisite consent and had not completed the rehabilitation within the extended time. The court held that the SRA's decision was based on valid grounds and was not arbitrary. The court also noted that the petitioners had been given adequate opportunity to be heard before the cancellation. The writ petition was dismissed, and the SRA's decision to cancel the LoI was upheld.
Headnote
A) Slum Rehabilitation - Cancellation of Letter of Intent - Power of SRA - Slum Rehabilitation Authority has the power to cancel a Letter of Intent if the developer fails to comply with the conditions, including obtaining consent of 70% of slum dwellers and completing rehabilitation within the stipulated time. The court held that the SRA's decision was based on valid grounds and did not violate principles of natural justice (Paras 10-15). B) Slum Rehabilitation - Consent of Slum Dwellers - Requirement of 70% Consent - Under the Slum Rehabilitation Scheme, a developer must obtain consent of at least 70% of the eligible slum dwellers before proceeding with the project. The court held that the petitioners failed to demonstrate that they had obtained the requisite consent, and the SRA was justified in cancelling the LoI on this ground (Paras 16-20). C) Slum Rehabilitation - Time Limit for Completion - Extension of Time - The Slum Rehabilitation Authority may grant extension of time for completion of rehabilitation, but the developer must show sufficient cause. The court held that the petitioners did not provide adequate justification for the delay, and the SRA's refusal to extend time was reasonable (Paras 21-25).
Issue of Consideration
Whether the Slum Rehabilitation Authority was justified in cancelling the Letter of Intent granted to the petitioners for a slum rehabilitation project due to non-compliance with conditions, including failure to obtain consent of 70% of slum dwellers and failure to complete rehabilitation within the stipulated time.
Final Decision
The High Court dismissed the writ petition, upholding the Slum Rehabilitation Authority's decision to cancel the Letter of Intent. The court found that the petitioners failed to comply with the conditions of the LoI, including obtaining 70% consent and completing rehabilitation within the stipulated time, and that the SRA's decision was not arbitrary.
Law Points
- Slum Rehabilitation Authority's power to cancel Letter of Intent for non-compliance
- requirement of consent of 70% of slum dwellers
- time limit for completion of rehabilitation
- principles of natural justice in cancellation proceedings





