Case Note & Summary
The appellant, Municipal Corporation of Greater Bombay, had invited tenders for re-construction of Zakariya Bunder road in May 1989. Respondent no.1 submitted a percentage rate tender on 12.05.1989, which was accepted on 23.09.1989. The work was to commence from 11.10.1989 with a contract period of eight months. Some delay occurred in commencing the work. Disputes arose between the parties regarding the delay and compensation, which were referred to arbitration. The sole arbitrator passed an award on 22.06.1993. The appellant filed a petition under Section 30 of the Arbitration Act, 1940 before the learned Single Judge seeking to set aside the award. The Single Judge dismissed the petition. Aggrieved, the appellant filed the present appeal. The main legal issue was whether the Single Judge erred in dismissing the petition. The appellant argued that the award suffered from errors apparent on the face of it and that the arbitrator had misconducted himself. The respondents contended that the award was final and binding and that the challenge was without merit. The Court analyzed the scope of Section 30 of the Arbitration Act, 1940 and held that the arbitrator's findings on factual issues and contractual interpretation are final and cannot be interfered with unless they are perverse or contrary to law. The Court found that the award did not suffer from any legal infirmity and that the Single Judge had correctly dismissed the petition. Consequently, the appeal was dismissed with no order as to costs.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 30 of Arbitration Act, 1940 - Scope of Interference - The appellant-corporation challenged the arbitral award on grounds of errors apparent on the face of the award and misconduct of the arbitrator. The Court held that the arbitrator's findings on factual issues and contractual interpretation are final and cannot be interfered with unless they are perverse or contrary to law. The Single Judge had correctly dismissed the petition as the award did not suffer from any legal infirmity. (Paras 1-10) B) Contract Law - Interpretation of Contract Terms - Finality of Arbitrator's Decision - The dispute arose from a contract for re-construction of a road. The arbitrator interpreted the contract terms regarding delay and compensation. The Court held that the arbitrator's interpretation, being a possible view, is binding and not open to challenge under Section 30 of the Arbitration Act, 1940. (Paras 2-8)
Issue of Consideration
Whether the learned Single Judge erred in dismissing the appellant's petition under Section 30 of the Arbitration Act, 1940 for setting aside the arbitral award dated 22.06.1993.
Final Decision
Appeal dismissed with no order as to costs.
Law Points
- Arbitration Act
- 1940
- Section 30
- Scope of challenge to arbitral award
- Finality of arbitrator's findings on facts and contract interpretation
- Perversity as ground for setting aside award




