Case Note & Summary
The petitioner, M/s DDL Excavation Pvt. Ltd., and the respondent, Union of India (UOI), entered into an agreement for execution of works in Goa. Disputes arose and were referred to an arbitrator, Mr. T. P. Vetayudhan, who submitted an award dated 7.4.2004. Both parties were dissatisfied with the award. The UOI challenged the award before the Bikaner Court, while the petitioner challenged it before the Margao Court. To avoid conflicting decisions, both parties filed transfer petitions before the Supreme Court, which by consent transferred the Bikaner proceedings to the Margao Court, noting that the Margao proceedings were instituted earlier. Before the Margao Court, the UOI filed an application under Section 14 of the Limitation Act, 1963, seeking exclusion of 467 days spent in prosecuting the challenge before the Bikaner Court. The learned District Judge, South Goa, Margao, allowed the application by order dated 17.12.2016, permitting exclusion of 467 days for computing limitation for filing a Section 34 application under the Arbitration and Conciliation Act, 1996. The petitioner challenged this order by way of a writ petition before the High Court of Bombay at Goa. The High Court held that Section 14 of the Limitation Act applies only to suits or applications under the Code of Civil Procedure, 1908, and not to applications under Section 34 of the Arbitration Act, which is a special statute with its own limitation regime. The court further held that the UOI failed to demonstrate due diligence and bona fides in pursuing the Bikaner proceedings, as the Bikaner Court had no jurisdiction. The High Court allowed the writ petition, set aside the order of the District Judge, and dismissed the UOI's application under Section 14 of the Limitation Act.
Headnote
A) Limitation Act - Section 14 - Exclusion of time for proceeding bona fide in court without jurisdiction - The court considered whether the period spent by the Union of India in pursuing a challenge to an arbitral award before the Bikaner Court (which lacked jurisdiction) could be excluded under Section 14 of the Limitation Act, 1963, for filing a Section 34 application under the Arbitration and Conciliation Act, 1996 before the Margao Court. The High Court held that Section 14 applies only to suits or applications under the Code of Civil Procedure, 1908, and not to applications under Section 34 of the Arbitration Act, which is a special statute with its own limitation regime. The exclusion was not permissible as the proceedings before the Bikaner Court were not bona fide and the UOI failed to demonstrate due diligence. (Paras 5-10) B) Arbitration Act - Section 34 - Limitation for challenging award - The court examined whether the period of limitation for filing a Section 34 application can be extended by applying Section 14 of the Limitation Act. The High Court held that Section 34(3) of the Arbitration Act provides a strict limitation period of three months, extendable by a further 30 days on sufficient cause, but no further. The application of Section 14 of the Limitation Act would defeat the legislative intent of speedy resolution under the Arbitration Act. The court set aside the order of the District Judge allowing exclusion of 467 days. (Paras 11-15)
Issue of Consideration
Whether the District Judge was correct in allowing the Union of India the benefit of Section 14 of the Limitation Act, 1963 to exclude 467 days for filing an application under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award.
Final Decision
The High Court allowed the writ petition, set aside the order dated 17.12.2016 passed by the learned District Judge, South Goa, Margao, and dismissed the application filed by the Union of India under Section 14 of the Limitation Act, 1963.
Law Points
- Section 14 of Limitation Act
- 1963
- Section 34 of Arbitration and Conciliation Act
- 1996
- Exclusion of time for proceeding bona fide in court without jurisdiction
- Limitation for challenging arbitral award





