Case Note & Summary
The judgment concerns two arbitration petitions filed under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 15th October 2011 passed under Section 84 of the Multi-State Co-operative Societies Act, 2002. The dispute arose from a loan advanced by The Memon Co-operative Bank Ltd. (respondent no.1) to Mr. Amarlal Ramchand Gera (since deceased, represented by his wife Smt. Prema Amarlal Gera) and guaranteed by Mr. Rajan Ramchand Gera. The bank claimed that the loan was not repaid, leading to arbitration. The arbitrator awarded the bank a sum of Rs. 12,00,000 with interest at 24% per annum with quarterly rests from the date of the award until realization, and costs of Rs. 50,000. Both the borrower's legal heir (Smt. Prema Amarlal Gera) and the guarantor (Rajan Ramchand Gera) filed separate petitions challenging the award. The main legal issues were whether the arbitrator exceeded his jurisdiction by awarding interest at a rate higher than the contractual rate of 16.5% per annum, whether the award of costs was justified, and whether the guarantor was liable. The court analyzed the loan agreement and found that the contractual rate was 16.5% per annum with quarterly rests. The court held that the arbitrator could not award interest exceeding the contractual rate, as doing so would be patently illegal and against public policy. The court also set aside the award of costs of Rs. 50,000 as the arbitrator gave no reasons for the quantum. However, the court upheld the liability of the guarantor, finding that the guarantee deed was valid and the guarantor was liable for the principal amount. The court partially allowed both petitions, modifying the award to reduce the interest rate to 16.5% per annum with quarterly rests from the date of the award until realization, and deleting the costs. The rest of the award was confirmed.
Headnote
A) Arbitration - Challenge to Arbitral Award - Section 34 Arbitration and Conciliation Act, 1996 - Section 84 Multi-State Co-operative Societies Act, 2002 - The court considered petitions challenging an arbitral award on grounds of excess of jurisdiction and patent illegality. The arbitrator had awarded interest at 24% per annum with quarterly rests, which was contrary to the contractual rate of 16.5% per annum. The court held that the arbitrator could not award interest exceeding the contractual rate and set aside the interest portion. (Paras 1-10) B) Arbitration - Interest Rate - Contractual Rate vs. Awarded Rate - The loan agreement provided for interest at 16.5% per annum with quarterly rests. The arbitrator awarded 24% per annum with quarterly rests. The court held that the arbitrator exceeded his jurisdiction by awarding a rate higher than the contractual rate, and such award was patently illegal and against public policy. (Paras 11-20) C) Arbitration - Costs - Award of Costs Without Reasons - The arbitrator awarded costs of Rs. 50,000 without providing any reasons. The court held that the award of costs was arbitrary and set it aside, as the arbitrator failed to give any justification for the quantum. (Paras 21-25) D) Arbitration - Guarantor Liability - The court upheld the liability of the guarantor (petitioner in ARBP 207/2012) as the guarantor had signed the guarantee deed and was liable for the principal amount. The court found no infirmity in the award regarding the guarantor's liability. (Paras 26-30)
Issue of Consideration
Whether the arbitral award dated 15th October, 2011 under Section 84 of the Multi-State Co-operative Societies Act, 2002 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of the arbitrator exceeding jurisdiction, patent illegality, and conflict with public policy, particularly regarding the rate of interest, costs, and liability of the guarantor.
Final Decision
Both arbitration petitions are partly allowed. The impugned arbitral award is modified to the extent that the rate of interest awarded at 24% per annum with quarterly rests is reduced to 16.5% per annum with quarterly rests from the date of the award until realization. The award of costs of Rs. 50,000 is set aside. The rest of the award is confirmed. No order as to costs.
Law Points
- Arbitration
- Multi-State Co-operative Societies Act
- 2002
- Section 34 of Arbitration and Conciliation Act
- 1996
- Section 84 of Multi-State Co-operative Societies Act
- Interest rate
- Guarantor liability
- Costs
- Jurisdiction of arbitrator
- Public policy





