Case Note & Summary
The appellant, M/s.X-Press Container Lines (UK) Ltd., entered into a Berth Reservation Agreement with the respondent, the Board of Trustees of the Port of Chennai, on 18.01.1995 for a period of two years. The respondent alleged breach of agreement and demanded payment of Rs.62,48,950.32 as penal levy for shortfall and Rs.1,00,13,000/- as advance payment for the second year. The appellant disputed the claims, leading to arbitration. The Arbitral Tribunal passed an award on 17.01.2009 directing the respondent to refund Rs.1,21,91,869/- with interest. The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, and the learned Single Judge set aside the award on 17.09.2020, holding that the claim was barred by limitation and that the Tribunal erred on merits. The appellant appealed under Section 37 of the Act. The Division Bench examined the issues of limitation and the merits of the award. On limitation, the Tribunal had applied Section 14 of the Limitation Act to exclude the time spent in pursuing the writ petition and appeal filed by the respondent, which had stayed the arbitration proceedings. The Division Bench held that the Tribunal's application of Section 14 was correct as the respondent had obtained a stay, and the appellant had acted in good faith. On merits, the Division Bench found that the Tribunal's findings on the calculation of penal levy and the refund of advance payments were based on evidence and were not perverse. The court held that the Single Judge had exceeded the scope of Section 34 by reappreciating evidence. Consequently, the appeal was allowed, the Single Judge's order was set aside, and the Arbitral Award was restored.
Headnote
A) Arbitration Law - Setting Aside of Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - The Single Judge set aside the award on grounds of limitation and merits, but the Division Bench held that the Arbitral Tribunal's findings were not perverse and did not warrant interference under Section 34, as the Tribunal had correctly applied Section 14 of the Limitation Act and considered the evidence. (Paras 1-44) B) Limitation Act - Exclusion of Time - Section 14 of the Limitation Act, 1963 - The Arbitral Tribunal held that the time spent in pursuing the writ petition (W.P.No.7692 of 2005) and the appeal (W.A.No.1459 of 2005) in good faith was liable to be excluded under Section 14, and the Division Bench affirmed this view, noting that the respondent had obtained a stay of arbitration proceedings. (Paras 20-30) C) Contract Law - Berth Reservation Agreement - Penal Levy for Shortfall - The dispute pertained to the calculation of penal levy for shortfall in throughput under the Berth Reservation Agreement dated 18.01.1995. The Arbitral Tribunal found that the respondent's calculation was erroneous and that the appellant was entitled to refund of advance payments. The Division Bench upheld this finding as reasonable. (Paras 3-10, 31-40)
Issue of Consideration
Whether the learned Single Judge was justified in setting aside the Arbitral Award dated 17.01.2009 under Section 34 of the Arbitration and Conciliation Act, 1996, on the grounds of limitation and merits, and whether the appellant is entitled to refund of Rs.1,21,91,869/- with interest.
Final Decision
The appeal is allowed. The order dated 17.09.2020 in OP No.511 of 2009 is set aside. The Arbitral Award dated 17.01.2009 is restored. No costs. Consequently, CMP No.11337 of 2021 is closed.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 34
- Section 37
- Section 43
- Limitation Act
- 1963
- Section 14
- Berth Reservation Agreement
- Penal Levy
- Shortfall in Throughput
- Refund of Advance Payment
- Interest



