Madras High Court Dismisses Appeal Against Arbitral Award in Power Supply Agreement Dispute — Abrupt Stoppage of Power Constitutes Breach. The Court upheld the arbitrator's award of damages and interest, finding no patent illegality under Section 34 of the Arbitration and Conciliation Act, 1996.

High Court: Madras High Court
  • 8
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, OPG Power Generation Pvt. Ltd., was the supplier of electricity under a power supply agreement dated 18.04.2018 with the respondent, Shree Karthik Papers Ltd., for a period of three years. The agreement provided for monthly billing from the 28th of one month to the 27th of the next, with payment due within 7 days. The appellant stopped power supply abruptly on 28.09.2018, allegedly due to non-payment of a bill raised on 01.10.2018 for the period 28.08.2018 to 27.09.2018. The respondent contended that the stoppage was a breach of contract and filed a claim under Section 8(1) of the Arbitration and Conciliation Act, 1996, seeking reference to arbitration. The sole arbitrator passed an award on 31.01.2020, granting Rs.40,82,400/- as excess power charges incurred by the respondent from 28.09.2018 to 23.03.2019, along with interest at 12% p.a. from respective due dates, and also interest on additional security deposit paid to TANGEDCO. The appellant challenged the award under Section 34(2)(b)(ii) of the Act before a learned Single Judge, who dismissed the petition by order dated 19.08.2020. The appellant then filed the present appeal under Section 37 of the Act. The Division Bench considered whether the award suffered from patent illegality or was in conflict with public policy. The Court noted that the arbitrator had examined the evidence and found that the appellant had stopped supply without notice, which was a breach. The computation of damages was based on the difference in tariff rates and was supported by evidence. The Court held that the arbitrator's findings were plausible and not perverse, and the award did not violate Section 28(3) of the Act. The Court also upheld the grant of interest at 12% p.a., as it was within the arbitrator's discretion under Section 31(7). Consequently, the appeal was dismissed, and the order of the learned Single Judge was confirmed.

Headnote

A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Setting Aside of Arbitral Award - Patent Illegality - The Court examined whether the arbitral award granting damages for breach of a power supply agreement was patently illegal. The Court held that the arbitrator's interpretation of the agreement and findings on breach were plausible and not perverse, thus not warranting interference under Section 34. (Paras 1-5)

B) Contract - Breach of Contract - Power Supply Agreement - Abrupt Stoppage of Supply - The appellant stopped power supply abruptly without notice, which was held to be a breach of the agreement. The arbitrator awarded damages for the excess power charges incurred by the respondent. The Court upheld this finding as it was based on evidence and not contrary to the terms of the contract. (Paras 2-4)

C) Damages - Computation of Damages - Interest - The arbitrator awarded Rs.40,82,400/- as excess power charges and interest at 12% p.a. from respective due dates. The Court found no patent illegality in the computation or the rate of interest, as the arbitrator had discretion under Section 31(7) of the Act. (Paras 4-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting damages for abrupt stoppage of power supply and interest thereon suffers from patent illegality or is in conflict with public policy under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is dismissed. The order of the learned Single Judge dated 19.08.2020 in O.P.No. 353 of 2020 is confirmed. No costs.

Law Points

  • Arbitration
  • Breach of Contract
  • Damages
  • Interest
  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Patent Illegality
  • Public Policy
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:MHC:938

OSA.No. 301 of 2020

2026-03-06

C.V.KARTHIKEYAN, K.KUMARESH BABU

2026:MHC:938

Mr. P.Vinod Kumar for M/s. J.Sagar Associates (Appellant), Mr. M.Krishnappan, Senior Counsel for Ms. R.Swarnalatha (Respondent)

OPG Power Generation Pvt. Ltd.

Shree Karthik Papers Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against dismissal of petition under Section 34 to set aside arbitral award.

Remedy Sought

Appellant sought to set aside the arbitral award dated 31.01.2020 and the order of the learned Single Judge dated 19.08.2020 dismissing its petition.

Filing Reason

Appellant aggrieved by the arbitral award granting damages and interest for alleged breach of power supply agreement.

Previous Decisions

Learned Single Judge dismissed O.P.No. 353 of 2020 filed under Section 34 of the Act on 19.08.2020.

Issues

Whether the arbitral award suffers from patent illegality or is in conflict with public policy under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996. Whether the arbitrator's findings on breach of contract and computation of damages are perverse or contrary to the terms of the agreement.

Submissions/Arguments

Appellant argued that the stoppage of power was justified due to non-payment of bills and that the award was patently illegal. Respondent contended that the abrupt stoppage was a breach and the award was based on evidence and within the arbitrator's jurisdiction.

Ratio Decidendi

The court held that the arbitrator's findings on breach and damages were plausible and based on evidence, and did not suffer from patent illegality or conflict with public policy. The court also held that the grant of interest at 12% p.a. was within the arbitrator's discretion under Section 31(7) of the Act.

Judgment Excerpts

The sole arbitrator passed an award on 31.01.2020 granting a sum of Rs.40,82,400/- as the amount incurred by the respondent towards excess power charges... Challenging this award, the appellant had filed O.P.No. 353 of 2020 under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996 to set aside the arbitral award.

Procedural History

The respondent filed a claim under Section 8(1) of the Arbitration and Conciliation Act, 1996, which was referred to arbitration. The sole arbitrator passed an award on 31.01.2020. The appellant filed O.P.No. 353 of 2020 under Section 34 to set aside the award, which was dismissed by a learned Single Judge on 19.08.2020. The appellant then filed the present appeal under Section 37 of the Act.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 8(1), Section 34, Section 34(2)(b)(ii), Section 37, Section 31(7), Section 28(3)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Sales Tax Notices Against Axis Bank in Liquidation Proceeding — No Liability for Tax Deducted at Source Under MVAT Act After Company's Winding Up. The Court held that the State cannot recover tax from a secured creditor wh...
Related Judgement
High Court Madras High Court Dismisses Appeal Against Arbitral Award in Power Supply Agreement Dispute — Abrupt Stoppage of Power Constitutes Breach. The Court upheld the arbitrator's award of damages and interest, finding no patent illegality under Section 3...