Bombay High Court Allows Deemed Conveyance to Co-operative Society Despite Pending Layout Development — MOFA Obligation to Convey Land to Flat Purchasers Is Not Contingent on Completion of Entire Layout. The Court held that the developer's obligation under Section 11 of MOFA, 1963 to convey the land to the society is absolute once occupation certificate is granted, and the Competent Authority cannot reject an application for deemed conveyance on the ground that the developer has not completed the entire layout.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 296
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Upvan Woodlands Co-operative Housing Society Limited, filed a writ petition under Article 227 of the Constitution of India challenging an order dated 20 May 2025 passed by the District Deputy Registrar, Co-operative Societies, Mumbai City-4 and Competent Authority (Competent Authority) rejecting its Application No.222 of 2024 for deemed conveyance. The background of the case is that Respondent No.3 was the original owner of a larger property comprising five plots. By an Agreement for Sale dated 18 April 1978, Respondent No.3 transferred its rights to Respondent No.2, which later entered into a partnership with Respondent No.1 under a Deed of Partnership dated 18 July 1989. Respondent No.1 became the developer of the land. A mini layout was approved on 6 July 2007, and Respondent No.1 constructed a building named 'Upvan Woodlands' on an undivided portion of the land admeasuring 2799.90 sq. mtrs. Occupation Certificate was granted on 6 May 2017. Respondent No.1 sold units to flat purchasers under agreements under Section 4 of the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963 (MOFA). The flat purchasers formed the Petitioner-Society, registered on 11 July 2018. The Society demanded conveyance of the land from Respondent No.1. By letter dated 1 September 2023, Respondent No.1 shared a draft Deed of Conveyance but indicated willingness to execute conveyance only after completion of the entire layout development. The Society then filed Application No.222 of 2024 before the Competent Authority seeking deemed conveyance under Section 11 of MOFA. The Competent Authority rejected the application on the ground that the developer had not completed the development of the remaining plots in the layout. The Society challenged this order. The legal issues considered were whether the Competent Authority could reject the application for deemed conveyance on the ground that the developer had not completed the entire layout development. The Society argued that the developer's obligation to convey the land under Section 11 of MOFA is absolute once the building is completed and occupation certificate granted, and is not contingent on completion of the entire layout. The developer contended that conveyance could only be executed after completion of the entire layout to avoid complications. The Court analyzed the provisions of MOFA, particularly Sections 4 and 11, and held that the developer's obligation to convey the land to the society is independent and must be performed without waiting for completion of the entire layout. The Court observed that the Competent Authority has jurisdiction to order deemed conveyance even if the developer has not completed development of other plots. The Court set aside the order of the Competent Authority and directed it to allow the society's application for deemed conveyance. The Court further directed that the conveyance deed be executed within a specified period. The decision primarily favors the petitioner-society.

Headnote

A) MOFA - Deemed Conveyance - Section 11 of MOFA, 1963 - Obligation to Convey - The developer's obligation to convey the land to the co-operative society under Section 11 of MOFA is not contingent upon completion of the entire layout development. Once the building is completed and occupation certificate granted, the developer must convey the proportionate land to the society. The Competent Authority erred in rejecting the society's application for deemed conveyance on the ground that the developer had not completed development of the remaining plots. Held that the developer's obligation under Section 11 is independent and must be performed without waiting for completion of the entire layout (Paras 10-15).

B) MOFA - Jurisdiction of Competent Authority - Section 11 of MOFA, 1963 - Deemed Conveyance - The Competent Authority under MOFA has jurisdiction to order deemed conveyance of the land on which the building is constructed, even if the developer has not completed development of other parts of the layout. The authority cannot refuse to exercise its power on the ground that the developer's overall development plan is incomplete. Held that the Competent Authority must consider the application on its merits and cannot defer conveyance indefinitely (Paras 16-20).

C) MOFA - Rights of Flat Purchasers - Sections 4 and 11 of MOFA, 1963 - Conveyance of Land - Flat purchasers who have paid full consideration are entitled to conveyance of the proportionate land under Section 11 of MOFA. The developer cannot withhold conveyance by citing pending development of other plots. The society, as representative of flat purchasers, has a right to seek deemed conveyance. Held that the society's application for deemed conveyance ought to have been allowed (Paras 21-25).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Competent Authority under the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963 (MOFA) can reject an application for deemed conveyance on the ground that the developer has not completed the development of the entire layout, even though the building in question has been completed and occupation certificate granted.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court allowed the writ petition, set aside the order dated 20 May 2025 passed by the Competent Authority, and directed the Competent Authority to allow Application No.222 of 2024 for deemed conveyance. The Court further directed that the conveyance deed be executed within a specified period.

Law Points

  • Deemed conveyance under Section 11 of MOFA
  • 1963 is not dependent on completion of entire layout development
  • Developer's obligation to convey land to society is absolute once occupation certificate is granted
  • Competent Authority under MOFA has jurisdiction to order deemed conveyance even if developer has not completed development of remaining plots
  • Section 4 and Section 11 of MOFA
  • 1963 impose independent obligations on developer
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (06) 52

WRIT PETITION NO.11551 OF 2025

2026-06-15

SANDEEP V. MARNE, J.

Ms. Tanaya Patankar with Mr. Devang Shah and Mr. Aditya Kanchan i/b Lakshyavedhi Legal for the Petitioners, Mr. Karl Tamboly with Mr. Samit Shukla, Ms. Delnavaz Patel and Ms. Sayali Diwadkar i/b Trilegal for Respondent No.1, Mr. Nimesh Bhatt for Respondent No.2, Mr. P.G. Sawant, AGP for Respondent Nos.4 and 5/State

Upvan Woodlands Co-operative Housing Society Limited

M/s. Upvan Developers, M/s. Govindram Brothers Pvt. Ltd., M/s. Balrampur Chini Mills Limited, The Competent Authority & District Deputy Registrar, Co-operative Societies, Mumbai City, The State of Maharashtra through Secretary, Housing Department

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 227 of Constitution of India challenging order of Competent Authority rejecting application for deemed conveyance under MOFA.

Remedy Sought

Petitioner-Society sought quashing of order dated 20 May 2025 and direction to Competent Authority to allow its application for deemed conveyance.

Filing Reason

Competent Authority rejected the society's application for deemed conveyance on the ground that the developer had not completed development of the entire layout.

Previous Decisions

Competent Authority rejected Application No.222 of 2024 by order dated 20 May 2025.

Issues

Whether the Competent Authority under MOFA can reject an application for deemed conveyance on the ground that the developer has not completed the entire layout development. Whether the developer's obligation to convey land under Section 11 of MOFA is contingent upon completion of the entire layout.

Submissions/Arguments

Petitioner-Society argued that the developer's obligation to convey the land under Section 11 of MOFA is absolute once the building is completed and occupation certificate granted, and is not contingent on completion of the entire layout. Respondent No.1 argued that conveyance could only be executed after completion of the entire layout to avoid complications and that the Competent Authority correctly rejected the application.

Ratio Decidendi

The developer's obligation under Section 11 of MOFA to convey the land to the co-operative society is absolute and not contingent upon completion of the entire layout development. The Competent Authority has jurisdiction to order deemed conveyance even if the developer has not completed development of other plots. The flat purchasers are entitled to conveyance of the proportionate land once the building is completed and occupation certificate granted.

Judgment Excerpts

The developer's obligation to convey the land to the society under Section 11 of MOFA is not contingent upon completion of the entire layout development. Once the building is completed and occupation certificate granted, the developer must convey the proportionate land to the society. The Competent Authority has jurisdiction to order deemed conveyance even if the developer has not completed development of other plots.

Procedural History

The Petitioner-Society filed Application No.222 of 2024 before the Competent Authority under MOFA seeking deemed conveyance. The Competent Authority rejected the application by order dated 20 May 2025. The Society then filed the present writ petition under Article 227 of the Constitution of India before the Bombay High Court, which was reserved on 9 June 2026 and pronounced on 15 June 2026.

Acts & Sections

  • Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963: Section 4, Section 11
  • Constitution of India: Article 227
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Deemed Conveyance to Co-operative Society Despite Pending Layout Development — MOFA Obligation to Convey Land to Flat Purchasers Is Not Contingent on Completion of Entire Layout. The Court held that the developer's obligati...
Related Judgement
High Court Bombay High Court Upholds Revenue's View that BEST Undertaking is a Dealer Under Bombay Sales Tax Act, 1959 — Transport Service for Hire Constitutes Business Even Without Profit Motive. The court held that the definition of 'dealer' under section 2...