Madras High Court Allows State's Appeal in Contract Dispute Over Canal Excavation Work — Contractor's Claim for Payment for Work Done Partly Allowed. The court held that the contractor is entitled to payment for work actually done and measured, but the quantum must be proved by proper evidence.

High Court: Madras High Court
  • 56
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a second appeal filed by the State of Tamil Nadu and the Executive Engineer, P.W.D., Krishna Water Supply Project, against the judgment of the First Appellate Court confirming the trial court's decree in favor of the plaintiff, P.V. Murthy, a contractor. The plaintiff had submitted tenders for three works of excavation and lining of canal from Tamil Nadu border to Poondi Reservoir reach under the Krishna Water Supply Project. The tenders were accepted, and agreements were entered into. The plaintiff claimed to have completed part of the work and sought payment for the same. The defendants contended that the plaintiff abandoned the work and did not complete it within the stipulated time, and that the plaintiff was not entitled to any payment as per the contract terms. The trial court decreed the suit for a sum of Rs. 1,50,000 with interest, which was confirmed by the First Appellate Court. The High Court, in the second appeal, examined the substantial question of law regarding the correctness of the decree in light of the alleged breach of contract. The court noted that the plaintiff had completed some work and the defendants had measured the work but did not pay the full amount. The court held that the plaintiff was entitled to payment for work done on quantum meruit basis, but the plaintiff failed to prove the exact amount due. The court set aside the decree and remanded the matter to the trial court for fresh determination of the quantum of payment based on the measurement books and other evidence. The appeal was allowed in part.

Headnote

A) Contract Law - Government Contracts - Breach of Contract - Quantum Meruit - The plaintiff contractor completed part of the work under three separate agreements with the Public Works Department for excavation and lining of canal. The State defendants contended that the plaintiff abandoned the work and failed to complete within time. The courts below decreed the suit for recovery of amounts due for work done. The High Court held that the plaintiff is entitled to payment for work actually done and measured, even if the contract was not fully performed, as the State accepted the work and did not terminate the contract. (Paras 1-10)

B) Civil Procedure - Second Appeal - Substantial Question of Law - Section 100 CPC - The appeal was admitted on the substantial question of law whether the courts below erred in decreeing the suit without considering the breach of contract by the plaintiff. The High Court found that the findings of fact by the lower courts were not perverse and no substantial question of law arose, but allowed the appeal on the ground that the plaintiff failed to prove the exact amount due. (Paras 11-15)

C) Evidence - Burden of Proof - Quantum of Damages - The plaintiff claimed a specific amount for work done but did not produce proper measurement books or vouchers. The High Court held that the burden was on the plaintiff to prove the quantum of work done and the amount payable. Since the plaintiff failed to discharge this burden, the decree for a specific sum was set aside. (Paras 16-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the courts below erred in decreeing the suit for recovery of money for work done under a contract when the plaintiff allegedly failed to complete the work within the stipulated time and whether the State is liable to pay for work done beyond the contract terms.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court allowed the appeal in part, set aside the decrees of the lower courts, and remanded the matter to the trial court for fresh determination of the quantum of payment due to the plaintiff based on the measurement books and other evidence. The court directed the trial court to dispose of the suit within six months.

Law Points

  • Contract law
  • Breach of contract
  • Quantum meruit
  • Earnest money deposit
  • Government contracts
  • Public Works Department
  • Specific performance
  • Section 100 CPC
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:MHC:1949

S.A. NO.1839 OF 2003

2026-04-20

R.SAKTHIVEL

2026:MHC:1949

Mr.R.Siddharath, Government Advocate for Appellants; No appearance for Respondent

1. The State rep. by The Secretary, P.W.D., Tamilnadu Government, Chennai – 600 009. 2. The Executive Engineer, P.W.D., Krishna Water Supply Project, Division No.3, Thiruvallur, Chengai Anna District.

P.V.Murthy S/o.P.Viswanathan residing at No.7, Paramanandha 1st Street, Chennai – 600 001.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Second appeal against concurrent decrees in a suit for recovery of money for work done under a contract.

Remedy Sought

The appellants (defendants) sought to set aside the judgment and decree of the First Appellate Court confirming the trial court's decree in favor of the respondent (plaintiff) for recovery of a sum of Rs. 1,50,000 with interest.

Filing Reason

The appellants contended that the plaintiff failed to complete the contract within the stipulated time and abandoned the work, and therefore was not entitled to any payment.

Previous Decisions

The trial court decreed the suit on September 29, 1997 in O.S. No.6231 of 1991. The First Appellate Court confirmed the decree on January 23, 2002 in A.S. No.31 of 2000.

Issues

Whether the courts below erred in decreeing the suit without considering the breach of contract by the plaintiff? Whether the plaintiff is entitled to payment for work done under the contract despite alleged abandonment? Whether the quantum of payment was properly proved by the plaintiff?

Submissions/Arguments

Appellants argued that the plaintiff abandoned the work and did not complete within time, and as per contract terms, no payment is due. Respondent argued that he completed part of the work and the defendants measured the work but did not pay the full amount.

Ratio Decidendi

A contractor who has performed part of the work under a contract is entitled to payment for the work actually done and accepted by the employer, even if the contract is not fully performed, on the principle of quantum meruit. However, the burden is on the contractor to prove the quantum of work done and the amount payable. In this case, the plaintiff failed to prove the exact amount due, necessitating a remand for fresh determination.

Judgment Excerpts

Feeling aggrieved by the Judgment and Decree dated January 23, 2002 made in A.S. No.31 of 2000 by 'the V Additional City Civil Court, Chennai' ['First Appellate Court' for brevity], confirming the Judgment and Decree dated September 29, 1997 made in O.S. No.6231 of 1991 by 'the V Assistant City Civil Court, Chennai' ['Trial Court' for short], the defendants therein have preferred this Second Appeal. The plaintiff is a contractor registered with the Public Works Department, Madras. The plaintiff submitted his tenders and made earnest money deposits for the following three works: ... As regards the first work ... the plaintiff completed 1350 cubic meters of earth work including 350 cubic meters in medium rock, 450 cubic meters ...

Procedural History

The plaintiff filed O.S. No.6231 of 1991 in the V Assistant City Civil Court, Chennai, for recovery of money for work done. The trial court decreed the suit on September 29, 1997. The defendants appealed to the V Additional City Civil Court, Chennai, in A.S. No.31 of 2000, which confirmed the decree on January 23, 2002. The defendants then filed the present second appeal under Section 100 CPC in the Madras High Court.

Acts & Sections

  • Code of Civil Procedure, 1908: Section 100
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Madras High Court Allows State's Appeal in Contract Dispute Over Canal Excavation Work — Contractor's Claim for Payment for Work Done Partly Allowed. The court held that the contractor is entitled to payment for work actually done and measured, but...
Related Judgement
High Court Bombay High Court Upholds Removal of Directors of Maharashtra State Road Transport Corporation Under Section 8 of Road Transport Corporation Act, 1950 — No Prior Hearing Required for Removal in Public Interest. The court held that the power of remo...