Gujarat High Court Allows Petition by Distribution Company Challenging Appellate Authority's Order Quashing Supplementary Bill for Unauthorized Use of Electricity. Extension of Supply to Adjacent Plots Without Permission Constitutes Unauthorized Use Under Section 126 of Electricity Act, 2003.

High Court: Gujarat High Court In Favour of Prosecution
  • 54
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Madhya Gujarat Vij Company Limited, a distribution licensee, filed a petition under Articles 14, 19(1)(g), 226, and 227 of the Constitution of India read with the Electricity Act, 2003, challenging an order dated 7.9.2022 passed by the Chief Electrical Inspector (Appellate Authority) in Appeal No.2153 of 2022. The respondent No.1, Panoli Intermediates (India) Pvt. Ltd., had an HT electricity connection with a contracted load of 1500 KVA. On 26.04.2018, representatives of the petitioner inspected the installation and found that respondent No.1 was utilizing electricity supply in adjacent Plot Nos.156A and 156B, which were owned by respondent No.1, without any prior intimation or permission. Consequently, a provisional assessment under Section 126 of the Electricity Act, 2003 was issued on 03.05.2018. After granting an opportunity of hearing to respondent No.1, a final supplementary bill was raised. Respondent No.1 filed an appeal under Section 127 before the Chief Electrical Inspector, who quashed the supplementary bill. The petitioner challenged this order. The High Court analyzed the provisions of Sections 126 and 127 of the Electricity Act, 2003, and held that the extension of electricity supply to adjacent plots without prior permission constitutes unauthorized use. The appellate authority's order was found to be perverse and without proper reasoning, as it failed to consider the evidence on record. The court set aside the appellate authority's order and restored the supplementary bill. The petition was allowed.

Headnote

A) Electricity Law - Unauthorized Use of Electricity - Section 126 Electricity Act, 2003 - Extension of supply to adjacent plots without permission - The petitioner, a distribution company, inspected the respondent's premises and found that electricity was being utilized in adjacent plots without prior intimation. A provisional assessment under Section 126 was issued, and after hearing, a final supplementary bill was raised. The appellate authority quashed the bill. The High Court held that the extension of supply to adjacent plots without permission constitutes unauthorized use, and the appellate authority's order was set aside. (Paras 3-10)

B) Electricity Law - Appellate Authority's Jurisdiction - Section 127 Electricity Act, 2003 - Scope of appeal - The appellate authority under Section 127 has limited jurisdiction and cannot re-appreciate evidence or substitute its own findings without proper reasoning. The High Court found that the appellate authority's order was perverse and not based on evidence. (Paras 8-12)

C) Electricity Law - Natural Justice - Opportunity of hearing - The petitioner granted an opportunity of hearing to the respondent before finalizing the assessment. The appellate authority's order was set aside as it failed to consider the evidence on record. (Paras 5-7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the extension of electricity supply to adjacent plots without prior intimation or permission constitutes unauthorized use under Section 126 of the Electricity Act, 2003, and whether the appellate authority erred in quashing the supplementary bill.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court allowed the petition, set aside the order dated 7.9.2022 passed by the Chief Electrical Inspector (Appellate Authority) in Appeal No.2153 of 2022, and restored the supplementary bill issued by the petitioner.

Law Points

  • Unauthorized use of electricity
  • Section 126 Electricity Act 2003
  • Supplementary bill
  • Appellate authority's jurisdiction
  • Natural justice
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (GUJ) (03) 228

R/SPECIAL CIVIL APPLICATION NO. 23464 of 2022

2026-03-17

Hemant M. Prachchhak

Mr. Dipak R Dave for Petitioner, Mr. Ashish Jha for Respondent No.1, Ms. Nirali Sarda AGP for Respondent No.2

Madhya Gujarat Vij Company Limited

Panoli Intermediates (India) Pvt. Ltd. & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil writ petition challenging appellate authority's order under Section 127 of Electricity Act, 2003

Remedy Sought

Petitioner sought quashing of appellate authority's order dated 7.9.2022 and restoration of supplementary bill

Filing Reason

Appellate authority quashed supplementary bill for unauthorized use of electricity

Previous Decisions

Appellate authority (Chief Electrical Inspector) in Appeal No.2153 of 2022 quashed supplementary bill

Issues

Whether extension of electricity supply to adjacent plots without permission constitutes unauthorized use under Section 126 of Electricity Act, 2003 Whether appellate authority under Section 127 acted within its jurisdiction in quashing the supplementary bill

Submissions/Arguments

Petitioner argued that respondent No.1 utilized electricity in adjacent plots without prior intimation, amounting to unauthorized use under Section 126 Respondent No.1 contended that the plots were owned by them and the use was not unauthorized

Ratio Decidendi

Extension of electricity supply to adjacent premises without prior intimation or permission from the distribution licensee constitutes unauthorized use under Section 126 of the Electricity Act, 2003. The appellate authority under Section 127 has limited jurisdiction and cannot quash a supplementary bill without proper reasoning or evidence.

Judgment Excerpts

The facts giving rise to present petition are that respondent No.1 was having an HT electricity connection... During the inspection, it was found that respondent No.1 was utilizing electricity supply in adjacent Plot Nos.156A and 156B... without any prior intimation or permission from the petitioner. In view of the above facts, a provisional assessment under Section 126 of the Electricity Act, 2003 was issued on 03.05.2018.

Procedural History

On 26.04.2018, inspection revealed unauthorized use. Provisional assessment under Section 126 on 03.05.2018. After hearing, final supplementary bill issued. Respondent No.1 appealed under Section 127 before Chief Electrical Inspector, who quashed the bill on 7.9.2022. Petitioner filed present writ petition on 23.12.2022.

Acts & Sections

  • Electricity Act, 2003: 126, 127
  • Constitution of India: 14, 19(1)(g), 226, 227
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Gujarat High Court Allows Petition by Distribution Company Challenging Appellate Authority's Order Quashing Supplementary Bill for Unauthorized Use of Electricity. Extension of Supply to Adjacent Plots Without Permission Constitutes Unauthorized Use ...
Related Judgement
High Court High Court of Bombay at Goa Dismisses Second Appeal in Permanent Injunction Suit — Concurrent Findings of Fact Not Interfered With. Suit for Injunction Simpliciter Dismissed as Plaintiffs Failed to Prove Possession Over Disputed Strip of Land.