Case Note & Summary
The present first appeal arises from a judgment and decree dated 8th March 2000 passed by the learned Second Joint Civil Judge (SD), Kachchh at Bhuj, in Special Civil Suit No.210 of 1991. The appellant, the Executive Engineer of the Gujarat Water Supply and Sewerage Board (plaintiff), had filed the suit against the respondent, Kataria Construction Company (defendant), seeking recovery of damages amounting to Rs.17,28,855.65 with 18% interest per annum. The plaintiff alleged that it had awarded a contract to the defendant for construction of an ESR (Elevated Storage Reservoir) and underground sump at a cost of Rs.23,08,712.50, with a condition to complete the work within 12 months from the receipt of the work order. The defendant failed to complete the work within the stipulated time, raised various disputes, and was issued legal notices on 3rd March 1999, 18th July 1990, and 28th September 1990. The contract was terminated, and the remaining work was carried out through another agency at risk and cost of the defendant. The plaintiff claimed damages for the additional expenditure incurred. The defendant appeared and filed a written statement-cum-counterclaim at Exh.28, disputing the allegations and claiming that the delay was caused by the plaintiff's own actions, including late sanction of designs (by four months), hard rock cutting that was not anticipated, obstruction by landowners, and unilateral increase in the quantity of reinforcement (steel). The defendant sought recovery of Rs.6,52,050/- with interest. The trial court dismissed the plaintiff's suit and allowed the defendant's counterclaim, directing the plaintiff to pay Rs.6,52,050/- with 12% interest per annum from the date of suit till realization. Aggrieved, the plaintiff filed the present appeal. The High Court examined the record and found that the trial court had failed to frame proper issues arising from the pleadings, particularly regarding the delay attributable to the plaintiff and the alleged unilateral increase in steel quantity. The court also noted that the trial court did not properly appreciate the evidence on record. Consequently, the High Court allowed the appeal, set aside the impugned judgment and decree, and remanded the matter back to the trial court for fresh consideration, directing the trial court to frame proper issues and decide the suit and counterclaim afresh in accordance with law.
Headnote
A) Civil Procedure - Issue Framing - Order 14 Rule 1 CPC - Duty of Court - The trial court failed to frame proper issues arising from the pleadings, especially regarding the delay caused by the plaintiff in sanctioning designs and the alleged unilateral increase in steel quantity, which vitiated the trial. Held that proper framing of issues is essential for a fair trial and the absence thereof warrants remand (Paras 5-7). B) Contract Law - Breach of Contract - Delay in Performance - Evidence - The trial court did not properly appreciate the evidence regarding the delay in completion of the construction contract, including the late sanction of designs and hard rock cutting, which were pleaded by the defendant as reasons for delay. Held that the court must consider all relevant evidence before concluding breach (Paras 8-10). C) Civil Procedure - Counterclaim - Order 8 Rule 6A CPC - The trial court allowed the counterclaim without adequate reasoning and without considering the plaintiff's objections. Held that a counterclaim must be adjudicated on merits with proper findings (Paras 11-12).
Issue of Consideration
Whether the trial court erred in dismissing the plaintiff's suit and allowing the defendant's counterclaim without properly framing issues and considering the evidence on record, particularly regarding the delay attributable to the plaintiff.
Final Decision
The High Court allowed the appeal, set aside the impugned judgment and decree dated 8th March 2000, and remanded the matter back to the trial court for fresh consideration. The trial court is directed to frame proper issues and decide the suit and counterclaim afresh in accordance with law.
Law Points
- Contract law
- Breach of contract
- Delay in performance
- Counterclaim
- Remand
- Issue framing
- Evidence appreciation





