Supreme Court Allows Appeal in Electricity Act Arbitration Dispute — Holds That Captive Generating Plant Wheeling Power to Own Units Is a Generating Company, Not Open Access Consumer, Under Section 86(1)(f). The Court Clarifies That Section 86(1)(f) Covers Disputes Between Licensees and Generating Companies, and the Appellant's Captive Power Plant Qualifies as a Generating Company.

  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court allowed the appeal filed by Hindustan Zinc Limited (HZL) against the judgment of the Rajasthan High Court, which had set aside an arbitral award in a dispute concerning unscheduled interchange (UI) charges under the Electricity Act, 2003. The background of the case involves HZL, which operates four high-tension electricity connections for its units at Chanderiya, Debari, Aghucha, and Dariba, and had set up a captive power plant of 154 MW at Chanderiya. HZL entered into three open access agreements with Ajmer Vidyut Vitran Nigam Limited (AVVNL) on March 10, 2005, for wheeling power from its captive plant to three of its units. Disputes arose regarding UI charges under Clauses 8 and 9 of these agreements. The Rajasthan Electricity Regulatory Commission initially decided to resolve the dispute itself but later appointed an arbitrator under Section 86(1)(f) read with Section 158 of the Electricity Act. The arbitrator struck down Clauses 8(c) and 9, leading to a challenge by AVVNL. The Commercial Court dismissed the challenge under Section 34 of the Arbitration and Conciliation Act, 1996, but the High Court, in a Section 37 appeal, set aside the award, holding that HZL was an open access consumer, not a generating company, and thus the Commission lacked jurisdiction under Section 86(1)(f). The Supreme Court reversed this decision, holding that a captive generating plant wheeling power to its own units is a 'generating company' under the Electricity Act, and the dispute falls within the ambit of Section 86(1)(f). The Court emphasized that the proviso to Section 42(2) exempts captive generating plants from surcharge, indicating they are not ordinary consumers. The Court also noted that the High Court erred in delving into the merits of the award after finding lack of jurisdiction. Consequently, the Supreme Court set aside the High Court's judgment and restored the award of the arbitrator, allowing the appeal.

Headnote

A) Electricity Law - Arbitration - Section 86(1)(f) read with Section 158 of the Electricity Act, 2003 - Jurisdiction of State Commission to appoint arbitrator - Dispute between a captive generating plant and a distribution licensee regarding unscheduled interchange charges - Held that a captive generating plant wheeling power to its own units is a 'generating company' and not an 'open access consumer', thus the dispute falls within Section 86(1)(f) - The High Court erred in holding that the appellant was an open access consumer and that the Commission lacked jurisdiction (Paras 1-20).

B) Electricity Law - Open Access - Section 42 of the Electricity Act, 2003 - Duties of distribution licensee - Open access for captive generating plants - The proviso to Section 42(2) exempts surcharge for captive generating plants, indicating they are treated differently from ordinary consumers - The appellant's captive power plant qualifies for such exemption (Paras 7-10).

C) Arbitration Law - Challenge to Arbitral Award - Sections 34 and 37 of the Arbitration and Conciliation Act, 1996 - Jurisdictional issue - The High Court, while hearing an appeal under Section 37, can examine the issue of inherent lack of jurisdiction of the arbitrator - However, in this case, the arbitrator had jurisdiction as the dispute was covered under Section 86(1)(f) - The High Court's finding of lack of jurisdiction was erroneous (Paras 15-20).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the dispute between Hindustan Zinc Limited (HZL) and Ajmer Vidyut Vitran Nigam Limited regarding unscheduled interchange charges falls within the scope of Section 86(1)(f) of the Electricity Act, 2003, and whether the Rajasthan Electricity Regulatory Commission had jurisdiction to appoint an arbitrator under that provision.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeal, set aside the High Court judgment dated 05.04.2018, and restored the arbitral award dated 25.08.2007. The Court held that the dispute falls within Section 86(1)(f) of the Electricity Act, 2003, and the arbitrator had jurisdiction.

Law Points

  • Interpretation of Section 86(1)(f) of the Electricity Act
  • 2003
  • Scope of arbitration under Electricity Act
  • Distinction between generating company and open access consumer
  • Captive generating plant's status under Electricity Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (12) 26

Civil Appeal No. 9212 of 2019 (Arising out of SLP (C) No. 9750 of 2018)

2019-12-04

R. F. Nariman

Shri C.S. Vaidyanathan (for appellant), Shri Puneet Jain (for respondent)

Hindustan Zinc Limited (H.Z.L.)

Ajmer Vidyut Vitran Nigam Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court judgment setting aside arbitral award in dispute over unscheduled interchange charges under Electricity Act.

Remedy Sought

Appellant sought restoration of arbitral award and setting aside of High Court judgment.

Filing Reason

High Court held that appellant was an open access consumer, not a generating company, and thus the dispute was outside Section 86(1)(f) of the Electricity Act, leading to lack of jurisdiction of the arbitrator.

Previous Decisions

Rajasthan Electricity Regulatory Commission appointed arbitrator on 12.02.2007; Arbitrator passed award on 25.08.2007; Commercial Court dismissed Section 34 petition on 25.02.2017; High Court allowed Section 37 appeal on 05.04.2018.

Issues

Whether the dispute between HZL and AVVNL falls within the scope of Section 86(1)(f) of the Electricity Act, 2003. Whether HZL, in the context of the open access agreements, is a generating company or an open access consumer. Whether the High Court erred in setting aside the arbitral award on jurisdictional grounds and on merits.

Submissions/Arguments

Appellant argued that its captive power plant is a generating company and the dispute is covered under Section 86(1)(f). Respondent argued that HZL acted as an open access consumer and thus the Commission lacked jurisdiction.

Ratio Decidendi

A captive generating plant wheeling power to its own units is a 'generating company' under the Electricity Act, 2003, and not an 'open access consumer'. Therefore, disputes between such a generating company and a distribution licensee regarding unscheduled interchange charges fall within the ambit of Section 86(1)(f) of the Electricity Act, and the State Commission has jurisdiction to appoint an arbitrator under that provision.

Judgment Excerpts

The present appeal raises an important question as to the scope of arbitration proceedings under the Electricity Act, 2003, in particular, Section 86(1)(f) thereto read with Section 158. The High Court held that, in the peculiar facts of this case, the captive generating plant of the company situated at Chanderiya was to use, through open access, the distribution system of the respondent to wheel power to three of its own units... the hat worn by the appellant-company... was that of an open access consumer and not that of a generating company. Section 42 of the Electricity Act, 2003, is relevant for the purpose of discussion...

Procedural History

The Rajasthan Electricity Regulatory Commission initially decided to resolve the dispute itself on 22.05.2006 and 23.06.2006, but later appointed an arbitrator on 12.02.2007 under Section 86(1)(f) read with Section 158 of the Electricity Act. The arbitrator passed an award on 25.08.2007. The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, before the Commercial Court, which dismissed the petition on 25.02.2017. The respondent then appealed under Section 37 to the Rajasthan High Court, which set aside the award on 05.04.2018. The appellant appealed to the Supreme Court by way of SLP (C) No. 9750 of 2018, which was converted into Civil Appeal No. 9212 of 2019.

Acts & Sections

  • Electricity Act, 2003: 86(1)(f), 158, 42
  • Arbitration and Conciliation Act, 1996: 34, 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal in Electricity Act Arbitration Dispute — Holds That Captive Generating Plant Wheeling Power to Own Units Is a Generating Company, Not Open Access Consumer, Under Section 86(1)(f). The Court Clarifies That Section 86(1)(f...
Related Judgement
Supreme Court Supreme Court Acquits Accused in Gang Rape Case Due to Unreliable Sole Testimony and Unexplained Delay. Conviction Under Sections 376(2)(g) and 506 IPC Set Aside as Prosecutrix's Statements Contained Material Inconsistencies and Prior Enmity Defence ...