Case Note & Summary
The Supreme Court dismissed two appeals filed by the Union of India (Railways) against the judgments of the Delhi High Court appointing independent arbitrators in disputes with contractors. The background involves two separate contracts: one with Pradeep Vinod Construction Company for civil works on the Rewari-Rohtak New Line, and another with BM Construction Company for construction of a road over bridge near Muradnagar. In both cases, the contractors completed the work and received final payments, but later claimed that additional amounts were due and that they had signed 'No Claim' certificates and supplementary agreements under duress. The contractors invoked the arbitration clause under Clause 64 of the General Conditions of Contract (GCC), but the Railways rejected their claims, asserting that the matters were settled and that the disputes were 'excepted matters' not referable to arbitration. The contractors then filed petitions under Section 11 of the Arbitration and Conciliation Act, 1996 before the Delhi High Court, which appointed independent arbitrators. The legal issues considered were: (1) whether the High Court could appoint an independent arbitrator despite the contractual mechanism under Clause 64; (2) whether the pre-amendment or post-amendment Act of 1996 applied; and (3) whether the disputes were 'excepted matters'. The Railways argued that the High Court should have directed appointment as per Clause 64, which requires appointment of Railway officers, and that the claims were 'excepted matters'. The contractors contended that the Railways forfeited its right to appoint by failing to appoint within 60 days, and that the validity of the 'No Claim' certificates should be examined by the arbitrator. The Supreme Court held that since the Railways failed to appoint an arbitrator within 60 days of the demand, it forfeited its right under the contract, and the High Court was justified in appointing an independent arbitrator under Section 11(6). The Court also held that the pre-amendment Act of 1996 applied as the requests were made before 23.10.2015. Regarding 'excepted matters', the Court found that the issue required evidence and could be examined by the arbitrator. The Court dismissed both appeals, upholding the High Court's orders appointing independent arbitrators.
Headnote
A) Arbitration Law - Appointment of Arbitrator - Section 11(6) of Arbitration and Conciliation Act, 1996 - Failure to Appoint - Where the Railways failed to appoint an arbitrator within 60 days of the demand for arbitration as per Clause 64(3)(a)(i) of GCC, the High Court rightly appointed an independent arbitrator, as the Railways forfeited its right to appoint under the contract. (Paras 13-15) B) Arbitration Law - Applicability of Amendment Act, 2015 - Section 21 of Principal Act, 1996 - Since the request for appointment of arbitrator was made before 23.10.2015, the pre-amendment provisions of the 1996 Act apply, and the High Court's appointment under Section 11(6) is valid. (Paras 10-11) C) Arbitration Law - 'Excepted Matters' - Clause 64 of GCC - The question whether a dispute falls under 'excepted matters' can be examined by the arbitrator, and the High Court did not err in leaving that issue to the arbitrator. (Para 14) D) Arbitration Law - 'No Claim' Certificate and Supplementary Agreement - Validity under Duress - The issue of whether the 'No Claim' certificate and supplementary agreement were signed under compulsion or undue influence requires evidence and is to be decided by the arbitrator, not by the court at the stage of appointment. (Paras 4, 8, 14)
Issue of Consideration
Whether the High Court was justified in appointing an independent arbitrator instead of directing appointment as per Clause 64 of the General Conditions of Contract (GCC) when the Railways failed to appoint an arbitrator within the stipulated time, and whether the disputes raised by the respondents are 'excepted matters' not referable to arbitration.
Final Decision
The Supreme Court dismissed both appeals, upholding the High Court's orders appointing independent arbitrators. The Court held that the Railways forfeited its right to appoint an arbitrator under Clause 64 by failing to appoint within 60 days, and the High Court was justified in appointing an independent arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The Court also held that the pre-amendment Act of 1996 applies, and the issue of 'excepted matters' and validity of 'No Claim' certificates can be examined by the arbitrator.
Law Points
- Appointment of arbitrator under Section 11(6) of Arbitration and Conciliation Act
- 1996
- Forfeiture of right to appoint arbitrator upon failure to appoint within stipulated time
- Applicability of pre-amendment Act of 1996 to requests made before 23.10.2015
- 'Excepted matters' under Clause 64 of GCC can be examined by arbitrator
- Validity of 'No Claim' certificate and supplementary agreement under duress to be decided by arbitrator



