Karnataka High Court Quashes RERA Authority's Refund Order Against Builder for Lack of Jurisdiction as Project Was Completed Before RERA Act Came Into Force. The Court held that the Real Estate (Regulation and Development) Act, 2016 applies only to ongoing projects where completion certificate is not issued, and since partial occupancy certificate was issued prior to the Act, the complaint was not maintainable and the order was without jurisdiction.

High Court: Karnataka High Court Bench: BENGALURU In Favour of Accused
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The case arose from a writ petition filed under Articles 226 and 227 of the Constitution of India by M/s Provident Housing Limited, a real estate developer, challenging an order of the Karnataka Real Estate Regulatory Authority (Authority) directing refund of Rs.6,84,494/- to a homebuyer. The dispute originated from an apartment project named Provident Sunworth in Bengaluru, for which the petitioner had obtained a partial occupancy certificate from the Bangalore Development Authority on 18-11-2015. The second respondent, an allottee, entered into a sale agreement and construction agreement on 10-09-2014. Subsequently, the homebuyer sought cancellation of the agreements in May 2017 on grounds that the petitioner had not acquired the land legally. The petitioner refunded Rs.17,85,212/- after deductions, and the homebuyer later approached the Authority for a refund of the deducted amount. The Authority passed an order on 30-09-2020 directing refund with interest, failing which interest at 2% per month would apply. The petitioner contended that the project was completed before the Real Estate (Regulation and Development) Act, 2016 came into force on 01-05-2016, as the occupancy certificate was issued in 2015. Hence, the project was not an ongoing project and the complaint was not maintainable. The Authority's order was alleged to be without jurisdiction. The respondent argued that the project was still ongoing because a full completion certificate was not issued, and that the writ petition was not maintainable due to the availability of an alternative remedy of appeal under Section 43(5) of the Act. The High Court considered two issues: maintainability of the complaint before the Authority and the tenability of the order. After examining the statutory provisions, particularly Section 3 of the RERA Act and the definition of completion certificate, the court held that the project had ceased to be ongoing because the occupancy certificate was issued before the Act commenced. Consequently, the complaint was not maintainable, and the order passed was a nullity. On the question of alternative remedy, the court ruled that when an order is patently without jurisdiction, a writ petition is maintainable despite the availability of an appeal, as such an order is void ab initio. The court refused to relegate the petitioner to the appellate tribunal and quashed the impugned order. The writ petition was allowed with no costs.

Headnote

A) Real Estate Law - Maintainability of Complaint - Definition of Ongoing Project - Real Estate (Regulation and Development) Act, 2016, Section 3 - The complainant entered into agreement in 2014 and a partial occupancy certificate was issued in 2015, before the Act came into force on 01-05-2016. The court examined the statutory framework and held that the Act applies only to ongoing projects where completion certificate has not been issued. Since the occupancy certificate was granted prior to the Act, the project ceased to be ongoing, rendering the complaint not maintainable before the RERA Authority (Paras 11-18).

B) Constitutional Law - Writ Jurisdiction - Availability of Alternative Remedy - Constitution of India, Article 226 - The RERA Act, 2016, Section 43(5) provides for an appeal, but the court held that when an authority acts wholly without jurisdiction, the resulting order is a nullity and a writ petition under Article 226 is maintainable. The petitioner was not required to exhaust the statutory remedy of appeal, as an order without jurisdiction can be challenged directly before the High Court (Paras 19-22).

C) Real Estate Law - Refund Orders - Jurisdictional Validity - Real Estate (Regulation and Development) Act, 2016, Sections 18, 31 - The RERA Authority directed refund of deducted amount with interest. The court found that because the complaint itself was not maintainable owing to lack of jurisdiction, the refund order was a nullity. The court emphasized that the amount in dispute is immaterial when the foundational jurisdiction to entertain the complaint is absent, and quashed the order (Paras 13-18, 22).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the complaint before the Karnataka Real Estate Regulatory Authority was maintainable given the timing of project completion and the Act's commencement; Whether the Authority's order was tenable in law

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The writ petition is allowed. The impugned order dated 30-09-2020 passed by the Karnataka Real Estate Regulatory Authority is quashed. No costs.

Law Points

  • Real Estate (Regulation and Development) Act
  • 2016 applies only to ongoing projects
  • project loses ongoing status once occupancy certificate is issued prior to Act's commencement
  • order passed without jurisdiction is a nullity and can be challenged under Article 226 despite availability of alternative remedy
Subscribe to unlock Law Points Subscribe Now

Case Details

2023 LawText (KAR) (01) 6

Writ Petition No. 18448 of 2021 (GM – RES)

2023-01-02

M. Nagaprasanna

Joseph Anthony, Rajashekhar K., Harish Kumar M.S.

M/s Provident Housing Limited

1. Karnataka Real Estate Regulatory Authority, 2. Mr. Shyama Shetty

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Articles 226 and 227 of the Constitution challenging the order of the Karnataka Real Estate Regulatory Authority directing refund of deducted amount with interest in a real estate dispute.

Remedy Sought

Petitioner sought to quash the order of the RERA Authority, contending that the complaint before the Authority was not maintainable because the project was not ongoing under the Real Estate (Regulation and Development) Act, 2016.

Filing Reason

The RERA Authority passed an order directing refund despite the project having received occupancy certificate before the Act came into force, thus acting without jurisdiction.

Previous Decisions

The Karnataka Real Estate Regulatory Authority passed the impugned order dated 30-09-2020 in CMP/UR/190214/0002137, directing the petitioner to refund Rs.6,84,494/- with interest.

Issues

Whether the complaint of the 2nd respondent before the Authority was maintainable? Whether the order passed by the Authority is tenable in law?

Submissions/Arguments

Petitioner argued that the project was not ongoing as partial occupancy certificate was issued before the Act came into force; therefore, the complaint was not maintainable and the Authority acted without jurisdiction. The writ petition is maintainable as the order is a nullity. Respondent contended that the project was still ongoing because complete occupancy certificate was not issued; the complaint was maintainable. The writ petition is not maintainable because the petitioner has an alternative remedy of appeal under Section 43(5) of the Act. The amount directed to be refunded is small and the builder should comply.

Ratio Decidendi

The Real Estate (Regulation and Development) Act, 2016 applies only to ongoing projects where completion certificate has not been issued. If an occupancy certificate (akin to completion certificate) was issued prior to the Act's commencement, the project ceases to be ongoing, and a complaint before the RERA Authority is not maintainable. An order passed without jurisdiction is a nullity and can be challenged under Article 226 of the Constitution, notwithstanding the availability of an alternative remedy under the statute.

Judgment Excerpts

The submission is that by the time the Act came into force, the project of the petitioner had lost its stage of being an ongoing project. In the light of the fact that the occupancy certificate was issued, the Act cannot be held to be applicable to the project. Therefore, the complaint was not maintainable. If the complaint was not maintainable, the order passed is a nullity.

Procedural History

The petitioner and second respondent entered into sale agreement and construction agreement on 10-09-2014 for an apartment in the project 'Provident Sunworth'. A partial occupancy certificate was issued by the Bangalore Development Authority on 18-11-2015. The second respondent sought cancellation of the agreements in May 2017. The petitioner cancelled the allotment and refunded Rs.17,85,212/- on 04-12-2017 after deductions. The second respondent filed a complaint before the Karnataka Real Estate Regulatory Authority seeking refund of Rs.6,84,494/- with interest. The Authority passed the impugned order on 30-09-2020 directing refund. The petitioner filed the present writ petition in 2021 challenging the order.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: 2(g), 2(q), 2(zn), 2(zk), 3, 18, 31, 43, 84
  • Constitution of India: Article 226, Article 227
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court at Aurangabad Hears Multiple Writ Petitions Relating to Co-operative Society Elections. Petitions Filed Under Article 226 of the Constitution of India Challenging Actions of State Co-operative Election Authority and Others.
Related Judgement
High Court Karnataka High Court Quashes RERA Authority's Refund Order Against Builder for Lack of Jurisdiction as Project Was Completed Before RERA Act Came Into Force. The Court held that the Real Estate (Regulation and Development) Act, 2016 applies only to o...