Bombay High Court Grants Interim Injunction Restraining Housing Society from Executing Development Agreement with New Developer Pending Arbitration. Court Holds That Prima Facie Case, Balance of Convenience, and Irreparable Injury Favor Protection of Developer's Rights Under Section 9 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, M/s. Pioneer Constructions, filed a Commercial Arbitration Petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim measures before the commencement of arbitral proceedings. The Petitioner also filed a Commercial Arbitration Application under Section 11 of the Act for appointment of an arbitrator, which was taken up for analogous hearing. The dispute arose out of a Development Agreement between the Petitioner and the Respondent, Sahakarnagar Co-operative Housing Society Ltd. The Petitioner apprehended that the Respondent-Society was likely to execute a Development Agreement with a new developer, as the Society had already passed a resolution in a General Body Meeting held on 10 January 2026 appointing a new developer. A Special General Body Meeting was scheduled for 23 April 2026 to finalize the draft of the Development Agreement with the new developer. The Petitioner sought an injunction restraining the Respondent from acting upon the resolution dated 10 January 2026 and from executing any development agreement with the new developer. The Court considered the submissions of both parties. The Petitioner argued that it had a valid and subsisting Development Agreement with the Society and that the Society's attempt to appoint a new developer was in breach of that agreement. The Respondent contended that the Petitioner had failed to perform its obligations under the agreement and that the Society was entitled to appoint a new developer. The Court analyzed the facts and legal principles governing interim measures under Section 9 of the Arbitration Act. The Court held that the Petitioner had made out a prima facie case, the balance of convenience was in favor of the Petitioner, and irreparable injury would be caused if the injunction was not granted. The Court granted interim relief restraining the Respondent from acting upon the resolution dated 10 January 2026 and from executing any development agreement with the new developer pending the arbitral proceedings. The Court also appointed an arbitrator under Section 11 of the Act to adjudicate the disputes between the parties.

Headnote

A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Injunction restraining execution of development agreement - Petitioner-developer sought to restrain society from acting on resolution appointing new developer and from executing development agreement with new developer - Court held that Petitioner made out a prima facie case, balance of convenience in its favor, and irreparable injury would be caused if injunction not granted - Held that interim protection is necessary to preserve the subject matter of arbitration (Paras 1-26).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 restraining the Respondent-Society from executing a development agreement with a new developer pending the arbitral proceedings.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court allowed the Section 9 Petition and granted interim relief restraining the Respondent from acting upon the resolution dated 10 January 2026 and from executing any development agreement with the new developer pending the arbitral proceedings. The Court also appointed an arbitrator under Section 11 of the Act.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Interim measures before arbitral proceedings
  • Prima facie case
  • Balance of convenience
  • Irreparable injury
  • Appointment of arbitrator under Section 11
  • Development agreement dispute
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:BHC-OS:10572

Commercial Arbitration Petition (L) No.13956 of 2026 with Commercial Arbitration Application (L) No.14176 of 2026

2026-04-24

Sandeep V. Marne

2026:BHC-OS:10572

Mr. D.D. Madon, Senior Advocate and Mr. Ashish Kamat, Senior Advocate with Mr. Shakeeb Shaikh, Ms. Sachi Lodha, Mr. Aftab Diamondwala & Ms. Trushti Talekar i/b. M/s. Diamondwala & Co. for the Petitioner. Mr. Chaitanya Chavan with Mr. Nikhil Jayakar i/b. Mr. Ankit Dubey for the Respondent.

M/s. Pioneer Constructions

Sahakarnagar Co-operative Housing Society Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial Arbitration Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures before commencement of arbitral proceedings, and Commercial Arbitration Application under Section 11 for appointment of arbitrator.

Remedy Sought

Petitioner sought an injunction restraining the Respondent-Society from acting upon the resolution dated 10 January 2026 appointing a new developer and from executing any development agreement with the new developer.

Filing Reason

Apprehension that the Respondent-Society would execute a Development Agreement with a new developer, in breach of the existing Development Agreement with the Petitioner.

Issues

Whether the Petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 restraining the Respondent from executing a development agreement with a new developer pending arbitration.

Submissions/Arguments

Petitioner argued that it had a valid and subsisting Development Agreement with the Society and that the Society's attempt to appoint a new developer was in breach of that agreement. Respondent contended that the Petitioner had failed to perform its obligations under the agreement and that the Society was entitled to appoint a new developer.

Ratio Decidendi

The Court held that for grant of interim measures under Section 9 of the Arbitration and Conciliation Act, 1996, the Petitioner must establish a prima facie case, balance of convenience in its favor, and irreparable injury. In this case, the Petitioner made out a prima facie case as there was a valid Development Agreement, the balance of convenience was in favor of granting injunction to preserve the subject matter of arbitration, and irreparable injury would be caused if the Society executed a development agreement with a new developer.

Judgment Excerpts

Section 9 Petition is filed under an apprehension that the Respondent-Society is likely to execute Development Agreement with the new Developer. The Petitioner has accordingly, filed Section 9 Petition seeking interim measures...

Procedural History

The Petitioner filed Commercial Arbitration Petition (L) No.13956 of 2026 under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures before commencement of arbitral proceedings. The Petitioner also filed Commercial Arbitration Application (L) No.14176 of 2026 under Section 11 of the Act for appointment of arbitrator. Both matters were taken up for analogous hearing. The Court reserved judgment on 22 April 2026 and pronounced on 24 April 2026.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 11
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appeal Against Railway Claims Tribunal Dismissal for Technical Grounds — Affidavit Language Issue Not Fatal to Claim. Claimant's lack of understanding of English affidavit does not defeat compensation claim under Section 12...
Related Judgement
High Court Bombay High Court Grants Interim Injunction Restraining Housing Society from Executing Development Agreement with New Developer Pending Arbitration. Court Holds That Prima Facie Case, Balance of Convenience, and Irreparable Injury Favor Protection of...